1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8072203 MGR.NO. 005 PAGE 001 CONT 6153 SEC 41 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 615341001 HWY IH0035 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 93,855.00 REPORT DATE 11/20/2009 14.32.22 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JAN 28,2008 TO SEP 30,2009 EST NO 021 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JAN 28, 2008 TIME COMPUTED FROM JAN 28, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 612 423 189 BROUGHT FORWARD ADDL DAYS GRANTED = 60 SEP 09 1 1 TOTAL DAYS ALLOWED = 425 2 1 DATE WORK COMPLETED 09/30/09 3 1 WORK COMPLETED DAYS CHARGED TO DATE = 425 4 1 WORK COMPLETED ASSESSED LIQ DAMAGES = 0 5 1 WORK COMPLETED LIQ DAMAGE RATE $ 400 6 1 WORK COMPLETED 7 1 WORK COMPLETED LIQUIDATED DAMAGES 8 1 WORK COMPLETED 0 DAYS AT $ 400 PER DAY 9 1 WORK COMPLETED TOTAL = $ .00 10 1 WORK COMPLETED 11 1 WORK COMPLETED CERTIFIED AS CORRECT AND 12 1 WORK COMPLETED ONE COPY HAS BEEN GIVEN 13 1 WORK COMPLETED TO THE CONTRACTOR 14 1 WORK COMPLETED 15 1 WORK COMPLETED 16 1 WORK COMPLETED ---------------------------- 17 1 WORK COMPLETED AREA/PROJECT ENGINEER 18 1 WORK COMPLETED 19 1 WORK COMPLETED 20 1 WORK COMPLETED 21 1 WORK COMPLETED 22 1 WORK COMPLETED 23 1 WORK COMPLETED 24 1 WORK COMPLETED 25 1 WORK COMPLETED 26 1 WORK COMPLETED 27 1 WORK COMPLETED 28 1 WORK COMPLETED 29 1 WORK COMPLETED 30 1 WORK COMPLETED AND ACCEPTED 0 ----- ----- ----- 642 425 217 0 SATURDAY 0 SUNDAY 0 HOLIDAY 27 WORK COMPLETED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8072203 MGR.NO. 005 PAGE 001 CONT 6153 SEC 41 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 615341001 HWY IH0035 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 93,855.00 REPORT DATE 11/20/2009 14.32.22 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JAN 28,2008 TO SEP 30,2009 EST NO 021 & FINAL DIST. 22 COUNTY WEBB CONTROL 6153-41-001 PROJECT RMC - 615341001 HIGHWAY IH0035 0LIMITS- IH 35 IH 35 0TYPE OF WORK- MAINTENANCE OF LARGE SIGNS ALONG IH 35 0 0050 LARGE GUIDE SIGNS CONTRACT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY NPM 6-28-07 0 0075 0416 DRILL SHAFT (SIGN MTS)(24 IN) LF 110.000 238.500 50.000 11,925.00 0075 0416 ADJ EST QUANTITY TO DATE 238.500 0080 0432 RIPRAP (CONC)(CL B)(5 IN) CY 40.000 27.641 200.000 5,528.20 0080 0432 ADJ EST QUANTITY TO DATE 27.641 0085 0636 REPLACE EXISTING ALUMINUM SIGNS (TY G) SF 1,665.000 4,351.810 37.000 161,016.97 0085 0636 ADJ EST QUANTITY TO DATE 4,351.810 0090 0647 INSTALL LRSS (STRUCT STEEL) LB 3,750.000 13,481.680 5.000 67,408.40 0090 0647 ADJ EST QUANTITY TO DATE 13,481.680 0095 9000*REPLACE EXISTING ALUMINUM SIGNS (TY G) SF 125.000 0.000 27.000 .00 0095 9000 ADJ EST QUANTITY TO DATE 0.000 0 SUBTOTAL BID ITEMS $ 245,878.57 0 TOTAL AMOUNT WORK DONE LARGE GUIDE SIGNS CONTRACT $ 245,878.57 0 TOTAL AMOUNT WORK DONE CONTROL 6153-41-001 $ 245,878.57 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8072203 MGR.NO. 005 PAGE 001 CONT 6153 SEC 41 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 615341001 HWY IH0035 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 93,855.00 REPORT DATE 11/20/2009 14.32.23 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JAN 28,2008 TO SEP 30,2009 EST NO 021 & FINAL 0*********************************************************************************************************************************** -LIMITS - IH 35 0 IH 35 DATE WORK BEGAN JAN 28, 2008 WORKING DAYS USED 425 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED SEP 30 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6153-41-001 RMC - 615341001 22 IH0035 WEBB - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0416 DRILL SHAFT (SIGN MTS)(24 IN) LF 110.000 238.500 50.000 11,925.00 0416 ADJ EST QUANTITY TO DATE 238.500 0432 RIPRAP (CONC)(CL B)(5 IN) CY 40.000 27.641 200.000 5,528.20 0432 ADJ EST QUANTITY TO DATE 27.641 0636 REPLACE EXISTING ALUMINUM SIGNS (TY G) SF 1,665.000 4,351.810 37.000 161,016.97 0636 ADJ EST QUANTITY TO DATE 4,351.810 0647 INSTALL LRSS (STRUCT STEEL) LB 3,750.000 13,481.680 5.000 67,408.40 0647 ADJ EST QUANTITY TO DATE 13,481.680 0 SUBTOTAL BID ITEMS $ 245,878.57 0 CONTRACT TOTAL ALL ITEMS $ 245,878.57 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8072203 MGR.NO. 005 PAGE 001 CONT 6153 SEC 41 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 615341001 HWY IH0035 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 93,855.00 REPORT DATE 11/20/2009 14.32.23 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JAN 28,2008 TO SEP 30,2009 EST NO 021 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 240 RMC - 615341001 6153-41-001 245,878.57 .00 245,878.57 .00 .00 245,878.57 245,760.42 118.15 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 245,878.57 .00 245,878.57 .00 .00 245,878.57 245,760.42 118.15 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8072203 MGR.NO. 005 PAGE 001 CONT 6153 SEC 41 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 615341001 HWY IH0035 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 93,855.00 REPORT DATE 11/20/2009 14.32.23 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JAN 28,2008 TO SEP 30,2009 EST NO 021 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6153-41-001 RMC - 615341001 22 IH0035 WEBB -LIMITS - IH 35 IH 35 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 80 0432 RIPRAP (CONC)(CL B)(5 IN) CY 40.000 0.600 200.000 120.00 85 0636 REPLACE EXISTING ALUMINUM SF 1,665.000 -0.050 37.000 -1.85 SIGNS (TY G) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 118.15 0 TOTAL AMOUNT WORK DONE TO DATE - $ 245,878.57