1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7121104 MGR.NO. 055 PAGE 001 CONT 6244 SEC 82 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624482001 HWY SH0184 1805 N TIMBERLAND DR LUFK CNTY SABINE DIST 11 CONTRACT PRICE $ 280,250.00 REPORT DATE 12/18/2013 11.34.07 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD SEP 10,2012 TO JUL 10,2013 EST NO 012 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 10, 2012 TIME COMPUTED FROM SEP 10, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 45 294 37 257 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 13 1 1 TOTAL DAYS ALLOWED = 45 2 1 DATE WORK COMPLETED 07/10/13 3 1 DAYS CHARGED TO DATE = 43 4 1 HOLIDAY ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSPENDED LIQ DAMAGE RATE $ 590 6 1 SATURDAY 7 1 SUNDAY LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 ALL WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 304 43 261 1 SATURDAY 1 SUNDAY 1 HOLIDAY 1 TIME SUSPENDED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7121104 MGR.NO. 055 PAGE 001 CONT 6244 SEC 82 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624482001 HWY SH0184 1805 N TIMBERLAND DR LUFK CNTY SABINE DIST 11 CONTRACT PRICE $ 280,250.00 REPORT DATE 12/18/2013 11.34.08 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD SEP 10,2012 TO JUL 10,2013 EST NO 012 & FINAL DIST. 11 COUNTY SABINE CONTROL 6244-82-001 PROJECT RMC - 624482001 HIGHWAY SH0184 0LIMITS- SH 184, SP 165, LP 149 & FM 83 WITHIN SABINE COUNTY MAINT SECTION 0TYPE OF WORK- DITCH AND CULVERT CLEANING 0 0005 PREPARED BY PAUL D. MONTGOMERY, P.E., 05/17/12 0 0055 ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0480 CLEAN EXIST CULVS EA 50.000 20.000 200.000 4,000.00 0065 0760 DITCH CLEANING AND RESHAPING (FOOT) LF 150,000.000 159,326.000 1.730 275,633.98 0070 0500 MOBILIZATION LS 1.000 1.000 10,000.000 10,000.00 0075 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 250.000 750.00 0 SUBTOTAL BID ITEMS $ 290,383.98 0 TOTAL AMOUNT WORK DONE ROADWAY $ 290,383.98 0 TOTAL AMOUNT WORK DONE CONTROL 6244-82-001 $ 290,383.98 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7121104 MGR.NO. 055 PAGE 001 CONT 6244 SEC 82 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624482001 HWY SH0184 1805 N TIMBERLAND DR LUFK CNTY SABINE DIST 11 CONTRACT PRICE $ 280,250.00 REPORT DATE 12/18/2013 11.34.08 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD SEP 10,2012 TO JUL 10,2013 EST NO 012 & FINAL 0*********************************************************************************************************************************** -LIMITS - SH 184, SP 165, LP 149 & FM 83 WITHIN 0 SABINE COUNTY MAINT SECTION DATE WORK BEGAN SEP 10, 2012 WORKING DAYS USED 43 PERCENT COMPLETE 100.00 PERCENT TIME USED 95.50 DATE COMPLETED JUL 10 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6244-82-001 RMC - 624482001 11 SH0184 SABINE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0480 CLEAN EXIST CULVS EA 50.000 20.000 200.000 4,000.00 0500 MOBILIZATION LS 1.000 1.000 10,000.000 10,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 250.000 750.00 0760 DITCH CLEANING AND RESHAPING (FOOT) LF 150,000.000 159,326.000 1.730 275,633.98 0 SUBTOTAL BID ITEMS $ 290,383.98 0 CONTRACT TOTAL ALL ITEMS $ 290,383.98 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7121104 MGR.NO. 055 PAGE 001 CONT 6244 SEC 82 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624482001 HWY SH0184 1805 N TIMBERLAND DR LUFK CNTY SABINE DIST 11 CONTRACT PRICE $ 280,250.00 REPORT DATE 12/18/2013 11.34.08 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD SEP 10,2012 TO JUL 10,2013 EST NO 012 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 202 RMC - 624482001 6244-82-001 290,383.98 .00 290,383.98 .00 .00 290,383.98 290,383.98 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 290,383.98 .00 290,383.98 .00 .00 290,383.98 290,383.98 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7121104 MGR.NO. 055 PAGE 001 CONT 6244 SEC 82 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624482001 HWY SH0184 1805 N TIMBERLAND DR LUFK CNTY SABINE DIST 11 CONTRACT PRICE $ 280,250.00 REPORT DATE 12/18/2013 11.34.08 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD SEP 10,2012 TO JUL 10,2013 EST NO 012 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6244-82-001 RMC - 624482001 11 SH0184 SABINE -LIMITS - SH 184, SP 165, LP 149 & FM 83 WITHIN SABINE COUNTY MAINT SECTION - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 290,383.98