1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7121102 MGR.NO. 055 PAGE 001 CONT 6244 SEC 74 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624474001 HWY FM2390 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 169,821.73 REPORT DATE 12/17/2013 10.47.17 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD AUG 20,2012 TO MAR 25,2013 EST NO 009 & FINAL SERVICES, INC. 11075 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 20, 2012 TIME COMPUTED FROM AUG 20, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 85 193 70 123 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 13 1 1 TIME SUSPENDED TOTAL DAYS ALLOWED = 85 2 1 TIME SUSPENDED DATE WORK COMPLETED 03/25/13 3 1 TIME SUSPENDED DAYS CHARGED TO DATE = 70 4 1 TIME SUSPENDED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSPENDED LIQ DAMAGE RATE $ 590 6 1 TIME SUSPENDED 7 1 TIME SUSPENDED LIQUIDATED DAMAGES 8 1 TIME SUSPENDED 0 DAYS AT $ 590 PER DAY 9 1 TIME SUSPENDED TOTAL = $ .00 10 1 TIME SUSPENDED 11 1 TIME SUSPENDED CERTIFIED AS CORRECT AND 12 1 TIME SUSPENDED ONE COPY HAS BEEN GIVEN 13 1 TIME SUSPENDED TO THE CONTRACTOR 14 1 TIME SUSPENDED 15 1 TIME SUSPENDED 16 1 TIME SUSPENDED ---------------------------- 17 1 TIME SUSPENDED AREA/PROJECT ENGINEER 18 1 TIME SUSPENDED 19 1 TIME SUSPENDED 20 1 TIME SUSPENDED 21 1 TIME SUSPENDED 22 1 TIME SUSPENDED 23 1 TIME SUSPENDED 24 1 TIME SUSPENDED 25 1 CONTRACT ACCEPTED - - ----- ----- ----- 218 70 148 0 SATURDAY 0 SUNDAY 0 HOLIDAY 24 TIME SUSPENDED 1 CONTRACT ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7121102 MGR.NO. 055 PAGE 001 CONT 6244 SEC 74 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624474001 HWY FM2390 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 169,821.73 REPORT DATE 12/17/2013 10.47.18 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD AUG 20,2012 TO MAR 25,2013 EST NO 009 & FINAL SERVICES, INC. 11075 DIST. 11 COUNTY SAN AUGUSTINE CONTROL 6244-74-001 PROJECT RMC - 624474001 HIGHWAY FM2390 0LIMITS- FM 2390 & VARIOUS LOCATIONS WITHIN SAN AUGUSTINE & NACOGDOCHES MAINT SECT 0TYPE OF WORK- CULVERT REPLACEMENT 0 0005 PREPARED BY C. MICHAEL LEE, P.E., 05/17/12 0 0055 ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0132 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 327.000 130.000 17.000 2,210.00 0065 0158 SPEC EXCAV WORK (HYD EXCAVATOR) HR 32.000 4.000 63.000 252.00 0070 0164 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 1,048.000 3,341.000 .200 668.20 0075 0164 BROADCAST SEED (TEMP) (WARM) SY 524.000 708.000 .200 141.60 0080 0168 VEGETATIVE WATERING MG 7.000 0.000 45.000 .00 0085 0169 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 565.000 0.000 1.500 .00 0090 0400 CEM STABIL BKFL CY 209.000 230.600 90.000 20,754.00 0095 0400 CUT & RESTORING PAV SY 109.500 118.580 86.000 10,197.88 0100 0402 TRENCH EXCAVATION PROTECTION LF 236.000 313.000 5.000 1,565.00 0105 0420 CL C CONC (COLLAR) EA 11.000 3.000 150.000 450.00 0110 0432 RIPRAP (CONC)(5 IN) CY 2.000 1.840 512.000 942.08 0115 0464 RC PIPE (CL III)(18 IN) LF 178.000 178.000 42.080 7,490.24 0120 0464 RC PIPE (CL III)(24 IN) LF 196.000 188.000 78.890 14,831.32 0125 0464 RC PIPE (CL III)(30 IN) LF 86.000 86.000 88.690 7,627.34 0130 0464 RC PIPE (CL III)(36 IN) LF 12.000 12.000 82.380 988.56 0135 0464 RC PIPE (CL III)(42 IN) LF 76.000 68.000 144.250 9,809.00 0140 0465 INLET (COMPL)(TY H)(MOD) EA 2.000 2.000 2,352.000 4,704.00 0145 0466 HEADWALL (CH-PW-0)(DIA= 36 IN) EA 1.000 1.000 4,364.000 4,364.00 0150 0466 HEADWALL (CH-PW-0)(DIA= 42 IN) EA 1.000 1.000 4,916.000 4,916.00 0155 0466 HEADWALL (CH-PW-0)(DIA= 48 IN) EA 1.000 0.000 6,028.000 .00 0160 0466 HEADWALL (CH-PW-0)(DIA= 60 IN) EA 1.000 1.000 7,597.000 7,597.00 1 0165 0466 HEADWALL (CH-PW-0)(DIA= 72 IN) EA 1.000 1.000 9,210.000 9,210.00 0170 0467 SET (TY II)(24 IN)(RCP)(3:1)(C) EA 1.000 1.000 508.000 508.00 0175 0467 SET (TY II)(30 IN)(RCP)(3:1)(C) EA 1.000 1.000 766.000 766.00 0180 0467 SET (TY II)(18 IN)(RCP)(4:1)(C) EA 12.000 12.000 375.000 4,500.00 0185 0467 SET (TY II)(24 IN)(RCP)(4:1)(C) EA 6.000 7.000 652.000 4,564.00 0190 0467 SET (TY II)(30 IN)(RCP)(4:1)(C) EA 2.000 2.000 1,099.000 2,198.00 0195 0467 SET (TY II)(36 IN)(RCP)(4:1)(C) EA 1.000 1.000 1,568.000 1,568.00 0200 0467 SET (TY II)(42 IN)(RCP)(4:1)(C) EA 2.000 2.000 2,757.000 5,514.00 0205 0480 CLEAN EXIST CULVS EA 1.000 0.000 436.000 .00 0210 0496 REMOV STR (PIPE) LF 425.000 425.000 8.450 3,591.25 0215 0500 MOBILIZATION LS 1.000 1.000 20,000.000 20,000.00 0220 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 1,000.000 2,000.00 0225 0506 BACKHOE WORK (EROSION & SEDM CONT) HR 45.000 3.000 48.000 144.00 0230 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 685.000 0.000 1.000 .00 0235 0658 INSTL OM ASSM (OM-2Z)(FLX)GND EA 30.000 30.000 50.000 1,500.00 0 SUBTOTAL BID ITEMS $ 155,571.47 0 TOTAL AMOUNT WORK DONE ROADWAY $ 155,571.47 0 TOTAL AMOUNT WORK DONE CONTROL 6244-74-001 $ 155,571.47 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7121102 MGR.NO. 055 PAGE 001 CONT 6244 SEC 74 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624474001 HWY FM2390 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 169,821.73 REPORT DATE 12/17/2013 10.47.18 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD AUG 20,2012 TO MAR 25,2013 EST NO 009 & FINAL SERVICES, INC. 11075 0*********************************************************************************************************************************** -LIMITS - FM 2390 & VARIOUS LOCATIONS WITHIN 0 SAN AUGUSTINE & NACOGDOCHES MAINT SECT DATE WORK BEGAN AUG 20, 2012 WORKING DAYS USED 70 PERCENT COMPLETE 100.00 PERCENT TIME USED 82.30 DATE COMPLETED MAR 25 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6244-74-001 RMC - 624474001 11 FM2390 SAN AUGUSTINE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0132 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 327.000 130.000 17.000 2,210.00 0158 SPEC EXCAV WORK (HYD EXCAVATOR) HR 32.000 4.000 63.000 252.00 0164 BROADCAST SEED (PERM) (RURAL) (SANDY) SY 1,048.000 3,341.000 .200 668.20 0164 BROADCAST SEED (TEMP) (WARM) SY 524.000 708.000 .200 141.60 0400 CEM STABIL BKFL CY 209.000 230.600 90.000 20,754.00 0400 CUT & RESTORING PAV SY 109.500 118.580 86.000 10,197.88 0402 TRENCH EXCAVATION PROTECTION LF 236.000 313.000 5.000 1,565.00 0420 CL C CONC (COLLAR) EA 11.000 3.000 150.000 450.00 0432 RIPRAP (CONC)(5 IN) CY 2.000 1.840 512.000 942.08 0464 RC PIPE (CL III)(18 IN) LF 178.000 178.000 42.080 7,490.24 0464 RC PIPE (CL III)(24 IN) LF 196.000 188.000 78.890 14,831.32 0464 RC PIPE (CL III)(30 IN) LF 86.000 86.000 88.690 7,627.34 0464 RC PIPE (CL III)(36 IN) LF 12.000 12.000 82.380 988.56 0464 RC PIPE (CL III)(42 IN) LF 76.000 68.000 144.250 9,809.00 0465 INLET (COMPL)(TY H)(MOD) EA 2.000 2.000 2,352.000 4,704.00 0466 HEADWALL (CH-PW-0)(DIA= 36 IN) EA 1.000 1.000 4,364.000 4,364.00 0466 HEADWALL (CH-PW-0)(DIA= 42 IN) EA 1.000 1.000 4,916.000 4,916.00 0466 HEADWALL (CH-PW-0)(DIA= 60 IN) EA 1.000 1.000 7,597.000 7,597.00 0466 HEADWALL (CH-PW-0)(DIA= 72 1 IN) EA 1.000 1.000 9,210.000 9,210.00 0467 SET (TY II)(24 IN)(RCP)(3:1)(C) EA 1.000 1.000 508.000 508.00 0467 SET (TY II)(30 IN)(RCP)(3:1)(C) EA 1.000 1.000 766.000 766.00 0467 SET (TY II)(18 IN)(RCP)(4:1)(C) EA 12.000 12.000 375.000 4,500.00 0467 SET (TY II)(24 IN)(RCP)(4:1)(C) EA 6.000 7.000 652.000 4,564.00 0467 SET (TY II)(30 IN)(RCP)(4:1)(C) EA 2.000 2.000 1,099.000 2,198.00 0467 SET (TY II)(36 IN)(RCP)(4:1)(C) EA 1.000 1.000 1,568.000 1,568.00 0467 SET (TY II)(42 IN)(RCP)(4:1)(C) EA 2.000 2.000 2,757.000 5,514.00 0496 REMOV STR (PIPE) LF 425.000 425.000 8.450 3,591.25 0500 MOBILIZATION LS 1.000 1.000 20,000.000 20,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 1,000.000 2,000.00 0506 BACKHOE WORK (EROSION & SEDM CONT) HR 45.000 3.000 48.000 144.00 0658 INSTL OM ASSM (OM-2Z)(FLX)GND EA 30.000 30.000 50.000 1,500.00 0 SUBTOTAL BID ITEMS $ 155,571.47 0 CONTRACT TOTAL ALL ITEMS $ 155,571.47 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7121102 MGR.NO. 055 PAGE 001 CONT 6244 SEC 74 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624474001 HWY FM2390 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 169,821.73 REPORT DATE 12/17/2013 10.47.18 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD AUG 20,2012 TO MAR 25,2013 EST NO 009 & FINAL SERVICES, INC. 11075 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 203 RMC - 624474001 6244-74-001 155,571.47 .00 155,571.47 .00 .00 155,571.47 155,571.47 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 155,571.47 .00 155,571.47 .00 .00 155,571.47 155,571.47 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7121102 MGR.NO. 055 PAGE 001 CONT 6244 SEC 74 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624474001 HWY FM2390 1805 N TIMBERLAND DR LUFK CNTY SAN AUGUSTINE DIST 11 CONTRACT PRICE $ 169,821.73 REPORT DATE 12/17/2013 10.47.18 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD AUG 20,2012 TO MAR 25,2013 EST NO 009 & FINAL SERVICES, INC. 11075 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6244-74-001 RMC - 624474001 11 FM2390 SAN AUGUSTINE -LIMITS - FM 2390 & VARIOUS LOCATIONS WITHIN SAN AUGUSTINE & NACOGDOCHES MAINT SECT - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 155,571.47