1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11111103 MGR.NO. 054 PAGE 001 CONT 6235 SEC 46 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623546001 HWY FM0415 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 97,987.50 REPORT DATE 05/01/2012 14.48.54 CONTRACTOR ACE CONTRACTORS, INC. 7036 EST PERIOD MAR 15,2012 TO APR 09,2012 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 19, 2012 TIME COMPUTED FROM MAR 15, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 91 17 4 13 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 12 1 1 SUNDAY TOTAL DAYS ALLOWED = 91 2 1 RAIN DATE WORK COMPLETED 04/09/12 3 1 TOO WET DAYS CHARGED TO DATE = 7 4 1 TOO WET ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 570 6 1 7 1 SATURDAY LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 570 PER DAY 9 1 WORK COMPLETED AND ACCEPTED TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 26 7 19 1 SATURDAY 2 SUNDAY 0 HOLIDAY 1 RAIN 2 TOO WET 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11111103 MGR.NO. 054 PAGE 001 CONT 6235 SEC 46 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623546001 HWY FM0415 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 97,987.50 REPORT DATE 05/01/2012 14.48.55 CONTRACTOR ACE CONTRACTORS, INC. 7036 EST PERIOD MAR 15,2012 TO APR 09,2012 EST NO 003 & FINAL DIST. 11 COUNTY SHELBY CONTROL 6235-46-001 PROJECT RMC - 623546001 HIGHWAY FM0415 0LIMITS- FM 415 & VARIOUS LOCATIONS WITHIN NACOGDOCHES COUNTY MAINT SECTION 0TYPE OF WORK- REMOVAL OF HIGH EDGES 0 0005 PREPARED BY C. MICHAEL LEE, P.E., 10/05/11 0 0055 ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0150 BLADING STA 2,533.000 2,533.000 37.500 94,987.50 0065 0500 MOBILIZATION LS 1.000 1.000 1,000.000 1,000.00 0070 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 500.000 2,000.00 0 SUBTOTAL BID ITEMS $ 97,987.50 0 TOTAL AMOUNT WORK DONE ROADWAY $ 97,987.50 0 TOTAL AMOUNT WORK DONE CONTROL 6235-46-001 $ 97,987.50 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11111103 MGR.NO. 054 PAGE 001 CONT 6235 SEC 46 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623546001 HWY FM0415 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 97,987.50 REPORT DATE 05/01/2012 14.48.55 CONTRACTOR ACE CONTRACTORS, INC. 7036 EST PERIOD MAR 15,2012 TO APR 09,2012 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - FM 415 & VARIOUS LOCATIONS WITHIN 0 NACOGDOCHES COUNTY MAINT SECTION DATE WORK BEGAN MAR 19, 2012 WORKING DAYS USED 7 PERCENT COMPLETE 100.00 PERCENT TIME USED 7.60 DATE COMPLETED APR 9 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6235-46-001 RMC - 623546001 11 FM0415 SHELBY - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0150 BLADING STA 2,533.000 2,533.000 37.500 94,987.50 0500 MOBILIZATION LS 1.000 1.000 1,000.000 1,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 500.000 2,000.00 0 SUBTOTAL BID ITEMS $ 97,987.50 0 CONTRACT TOTAL ALL ITEMS $ 97,987.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11111103 MGR.NO. 054 PAGE 001 CONT 6235 SEC 46 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623546001 HWY FM0415 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 97,987.50 REPORT DATE 05/01/2012 14.48.55 CONTRACTOR ACE CONTRACTORS, INC. 7036 EST PERIOD MAR 15,2012 TO APR 09,2012 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 210 RMC - 623546001 6235-46-001 97,987.50 .00 97,987.50 .00 .00 97,987.50 97,987.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 97,987.50 .00 97,987.50 .00 .00 97,987.50 97,987.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11111103 MGR.NO. 054 PAGE 001 CONT 6235 SEC 46 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 623546001 HWY FM0415 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 97,987.50 REPORT DATE 05/01/2012 14.48.56 CONTRACTOR ACE CONTRACTORS, INC. 7036 EST PERIOD MAR 15,2012 TO APR 09,2012 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6235-46-001 RMC - 623546001 11 FM0415 SHELBY -LIMITS - FM 415 & VARIOUS LOCATIONS WITHIN NACOGDOCHES COUNTY MAINT SECTION - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 97,987.50