1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8091103 MGR.NO. 030 PAGE 001 CONT 6198 SEC 05 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 619805001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY ANGELINA DIST 11 CONTRACT PRICE $ 234,400.00 REPORT DATE 02/23/2010 10.59.38 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 23,2009 TO FEB 27,2010 EST NO 007 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 06, 2009 TIME COMPUTED FROM SEP 23, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 180 131 53 78 BROUGHT FORWARD ADDL DAYS GRANTED = 0 FEB 10 1 1 AWAITING FINAL INSPECTION TOTAL DAYS ALLOWED = 180 2 1 AWAITING FINAL INSPECTION DATE WORK COMPLETED 02/17/10 3 1 AWAITING FINAL INSPECTION DAYS CHARGED TO DATE = 53 4 1 AWAITING FINAL INSPECTION ASSESSED LIQ DAMAGES = 0 5 1 AWAITING FINAL INSPECTION LIQ DAMAGE RATE $ 500 6 1 AWAITING FINAL INSPECTION 7 1 AWAITING FINAL INSPECTION LIQUIDATED DAMAGES 8 1 AWAITING FINAL INSPECTION 0 DAYS AT $ 500 PER DAY 9 1 AWAITING FINAL INSPECTION TOTAL = $ .00 10 1 AWAITING FINAL INSPECTION 11 1 AWAITING FINAL INSPECTION CERTIFIED AS CORRECT AND 12 1 AWAITING FINAL INSPECTION ONE COPY HAS BEEN GIVEN 13 1 AWAITING FINAL INSPECTION TO THE CONTRACTOR 14 1 AWAITING FINAL INSPECTION 15 1 AWAITING FINAL INSPECTION 16 1 AWAITING FINAL INSPECTION ---------------------------- 17 1 WORK COMPLETED AND ACCEPTED AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 148 53 95 0 SATURDAY 0 SUNDAY 0 HOLIDAY 16 AWAITING FINAL INSPECTION 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8091103 MGR.NO. 030 PAGE 001 CONT 6198 SEC 05 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 619805001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY ANGELINA DIST 11 CONTRACT PRICE $ 234,400.00 REPORT DATE 02/23/2010 10.59.38 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 23,2009 TO FEB 27,2010 EST NO 007 & FINAL DIST. 11 COUNTY ANGELINA CONTROL 6198-05-001 PROJECT RMC - 619805001 HIGHWAY US0059 0LIMITS- US 59 & VARIOUS LOCATIONS WITHIN LUFKIN DISTRICT (9 COUNTIES) 0TYPE OF WORK- INSTALLATION OF WATERBASE STRIPING 0 0005 PREPARED BY HERBERT E. BICKLEY, P.E., 06/10/09 0 0055 ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0666 REF PAV MRK TY II (W) 4" (BRK) LF 150,000.000 19,970.000 .080 1,597.60 0065 0666 REF PAV MRK TY II (W) 4" (SLD) LF 1,000,000.000 1,519,942.000 .080 121,595.36 0065 0666 ADJ EST QUANTITY TO DATE 1,519,942.000 0070 0666 REF PAV MRK TY II (W) 8" (SLD) LF 8,000.000 8,786.000 .400 3,514.40 0070 0666 ADJ EST QUANTITY TO DATE 8,786.000 0075 0666 REF PAV MRK TY II (Y) 4" (BRK) LF 340,000.000 166,345.000 .080 13,307.60 0080 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 1,400,000.000 1,890,805.000 .080 151,264.40 0080 0666 ADJ EST QUANTITY TO DATE 1,890,805.000 0 SUBTOTAL BID ITEMS $ 291,279.36 0 TOTAL AMOUNT WORK DONE ROADWAY $ 291,279.36 0 TOTAL AMOUNT WORK DONE CONTROL 6198-05-001 $ 291,279.36 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8091103 MGR.NO. 030 PAGE 001 CONT 6198 SEC 05 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 619805001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY ANGELINA DIST 11 CONTRACT PRICE $ 234,400.00 REPORT DATE 02/23/2010 10.59.38 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 23,2009 TO FEB 27,2010 EST NO 007 & FINAL 0*********************************************************************************************************************************** -LIMITS - US 59 & VARIOUS LOCATIONS WITHIN 0 LUFKIN DISTRICT (9 COUNTIES) DATE WORK BEGAN OCT 6 , 2009 WORKING DAYS USED 53 PERCENT COMPLETE 100.00 PERCENT TIME USED 29.40 DATE COMPLETED FEB 17 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6198-05-001 RMC - 619805001 11 US0059 ANGELINA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0666 REF PAV MRK TY II (W) 4" (BRK) LF 150,000.000 19,970.000 .080 1,597.60 0666 REF PAV MRK TY II (W) 4" (SLD) LF 1,000,000.000 1,519,942.000 .080 121,595.36 0666 ADJ EST QUANTITY TO DATE 1,519,942.000 0666 REF PAV MRK TY II (W) 8" (SLD) LF 8,000.000 8,786.000 .400 3,514.40 0666 ADJ EST QUANTITY TO DATE 8,786.000 0666 REF PAV MRK TY II (Y) 4" (BRK) LF 340,000.000 166,345.000 .080 13,307.60 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 1,400,000.000 1,890,805.000 .080 151,264.40 0666 ADJ EST QUANTITY TO DATE 1,890,805.000 0 SUBTOTAL BID ITEMS $ 291,279.36 0 CONTRACT TOTAL ALL ITEMS $ 291,279.36 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8091103 MGR.NO. 030 PAGE 001 CONT 6198 SEC 05 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 619805001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY ANGELINA DIST 11 CONTRACT PRICE $ 234,400.00 REPORT DATE 02/23/2010 10.59.38 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 23,2009 TO FEB 27,2010 EST NO 007 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 3 RMC - 619805001 6198-05-001 291,279.36 .00 291,279.36 .00 .00 291,279.36 291,279.36 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 291,279.36 .00 291,279.36 .00 .00 291,279.36 291,279.36 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8091103 MGR.NO. 030 PAGE 001 CONT 6198 SEC 05 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 619805001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY ANGELINA DIST 11 CONTRACT PRICE $ 234,400.00 REPORT DATE 02/23/2010 10.59.39 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 23,2009 TO FEB 27,2010 EST NO 007 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6198-05-001 RMC - 619805001 11 US0059 ANGELINA -LIMITS - US 59 & VARIOUS LOCATIONS WITHIN LUFKIN DISTRICT (9 COUNTIES) - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 291,279.36