1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3091102 MGR.NO. 055 PAGE 001 CONT 6188 SEC 06 JOB 001 RES ENGR CARRELL, JUDY PROJ EMC - 618806001 HWY FM2427 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 129,843.00 REPORT DATE 06/11/2009 15.16.37 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD MAR 23,2009 TO MAY 15,2009 EST NO 004 & FINAL SERVICES, INC. 11075 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 23, 2009 TIME COMPUTED FROM MAR 23, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 21 39 23 16 BROUGHT FORWARD ADDL DAYS GRANTED = 35 MAY 09 1 1 TIME SUSPENDED TOTAL DAYS ALLOWED = 56 2 1 SATURDAY DATE WORK COMPLETED 05/15/09 3 1 SUNDAY DAYS CHARGED TO DATE = 23 4 1 TIME SUSPENDED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSPENDED LIQ DAMAGE RATE $ 0 6 1 TIME SUSPENDED 7 1 TIME SUSPENDED LIQUIDATED DAMAGES 8 1 TIME SUSPENDED 0 DAYS AT $ 0 PER DAY 9 1 SATURDAY TOTAL = $ .00 10 1 SUNDAY 11 1 TIME SUSPENDED CERTIFIED AS CORRECT AND 12 1 TIME SUSPENDED ONE COPY HAS BEEN GIVEN 13 1 TIME SUSPENDED TO THE CONTRACTOR 14 1 TIME SUSPENDED 15 1 WORK COMPLETED AND ACCEPTED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 54 23 31 2 SATURDAY 2 SUNDAY 0 HOLIDAY 10 TIME SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3091102 MGR.NO. 055 PAGE 001 CONT 6188 SEC 06 JOB 001 RES ENGR CARRELL, JUDY PROJ EMC - 618806001 HWY FM2427 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 129,843.00 REPORT DATE 06/11/2009 15.16.38 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD MAR 23,2009 TO MAY 15,2009 EST NO 004 & FINAL SERVICES, INC. 11075 DIST. 11 COUNTY SHELBY CONTROL 6188-06-001 PROJECT EMC - 618806001 HIGHWAY FM2427 0LIMITS- FM 2427 @ SOUTH CREEK WITHIN SAN AUG MAINT SECTION (SHELBY COUNTY) 0TYPE OF WORK- BOX CULVERT REPLACEMENT 0 0005 PREPARED BY C. MICHAEL LEE, P.E., 03/19/09 0 0055 ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0110 EXCAVATION (SPECIAL) CY 180.000 80.000 7.000 560.00 0065 0132 EMBANKMENT (VEHICLE)(ORD COMP)(TY A) CY 280.000 320.000 14.000 4,480.00 0070 0164 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 750.000 1,597.500 .100 159.75 0075 0168 VEGETATIVE WATERING MG 4.000 0.000 10.000 .00 0080 0340 D-GR HMA(METH) TY-D PG64-22 TON 122.000 66.890 102.000 6,822.78 0085 0400 CEM STABIL BKFL CY 55.000 59.300 88.000 5,218.40 0090 0420 CL E CONC (SEAL) CY 18.000 25.350 296.000 7,503.60 0095 0432 RIPRAP (CONC)(5 IN) CY 16.600 26.356 300.000 7,906.80 0100 0462 CONC BOX CULV (6 FT X 6 FT) LF 132.000 132.000 323.000 42,636.00 0105 0466 WINGWALL (FW-0)(HW=9 FT) EA 2.000 2.000 9,300.000 18,600.00 0110 0496 REMOV STR (WINGWALL) EA 2.000 2.000 400.000 800.00 0115 0496 REMOV STR (BOX CULVERT) LF 132.000 132.000 35.000 4,620.00 0120 0500 MOBILIZATION LS 1.000 1.000 13,000.000 13,000.00 0125 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 700.000 1,400.00 0130 0506 BACKHOE WORK (EROSION & SEDM CONT) HR 2.000 0.000 55.000 .00 0135 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 100.000 200.000 3.000 600.00 0140 0540 MTL W-BEAM GD FEN (TIM POST) LF 250.000 250.000 25.000 6,250.00 0145 0544 GDRAIL END TRT(INST)(WOOD POST)(TY III) EA 4.000 4.000 2,250.000 9,000.00 0150 0658 INSTL DEL ASSM (D-SW)SZ 1(FLX)GF3(BI) EA 6.000 6.000 40.000 240.00 0155 0432*RIPRAP (STONE COMMON)(DRY)(18 IN) CY 14.000 12.100 138.000 1,669.80 0165 9000*TYPE III BARRICADES/ROAD 1 CLOSED SIGNS LS 1.000 1.000 594.380 594.38 0 SUBTOTAL BID ITEMS $ 132,061.51 0 TOTAL AMOUNT WORK DONE ROADWAY $ 132,061.51 0 TOTAL AMOUNT WORK DONE CONTROL 6188-06-001 $ 132,061.51 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3091102 MGR.NO. 055 PAGE 001 CONT 6188 SEC 06 JOB 001 RES ENGR CARRELL, JUDY PROJ EMC - 618806001 HWY FM2427 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 129,843.00 REPORT DATE 06/11/2009 15.16.38 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD MAR 23,2009 TO MAY 15,2009 EST NO 004 & FINAL SERVICES, INC. 11075 0*********************************************************************************************************************************** -LIMITS - FM 2427 @ SOUTH CREEK WITHIN SAN AUG 0 MAINT SECTION (SHELBY COUNTY) DATE WORK BEGAN MAR 23, 2009 WORKING DAYS USED 23 PERCENT COMPLETE 100.00 PERCENT TIME USED 41.00 DATE COMPLETED MAY 15 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6188-06-001 EMC - 618806001 11 FM2427 SHELBY - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0110 EXCAVATION (SPECIAL) CY 180.000 80.000 7.000 560.00 0132 EMBANKMENT (VEHICLE)(ORD COMP)(TY A) CY 280.000 320.000 14.000 4,480.00 0164 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 750.000 1,597.500 .100 159.75 0340 D-GR HMA(METH) TY-D PG64-22 TON 122.000 66.890 102.000 6,822.78 0400 CEM STABIL BKFL CY 55.000 59.300 88.000 5,218.40 0420 CL E CONC (SEAL) CY 18.000 25.350 296.000 7,503.60 0432 RIPRAP (CONC)(5 IN) CY 16.600 26.356 300.000 7,906.80 0462 CONC BOX CULV (6 FT X 6 FT) LF 132.000 132.000 323.000 42,636.00 0466 WINGWALL (FW-0)(HW=9 FT) EA 2.000 2.000 9,300.000 18,600.00 0496 REMOV STR (WINGWALL) EA 2.000 2.000 400.000 800.00 0496 REMOV STR (BOX CULVERT) LF 132.000 132.000 35.000 4,620.00 0500 MOBILIZATION LS 1.000 1.000 13,000.000 13,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 700.000 1,400.00 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 100.000 200.000 3.000 600.00 0540 MTL W-BEAM GD FEN (TIM POST) LF 250.000 250.000 25.000 6,250.00 0544 GDRAIL END TRT(INST)(WOOD POST)(TY III) EA 4.000 4.000 2,250.000 9,000.00 0658 INSTL DEL ASSM (D-SW)SZ 1(FLX)GF3(BI) EA 6.000 6.000 40.000 240.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 10432* RIPRAP (STONE COMMON)(DRY)(18 IN) CY 14.000 12.100 138.000 1,669.80 9000* TYPE III BARRICADES/ROAD CLOSED SIGNS LS 1.000 1.000 594.380 594.38 0 SUBTOTAL BID ITEMS $ 132,061.51 0 CONTRACT TOTAL ALL ITEMS $ 132,061.51 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3091102 MGR.NO. 055 PAGE 001 CONT 6188 SEC 06 JOB 001 RES ENGR CARRELL, JUDY PROJ EMC - 618806001 HWY FM2427 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 129,843.00 REPORT DATE 06/11/2009 15.16.38 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD MAR 23,2009 TO MAY 15,2009 EST NO 004 & FINAL SERVICES, INC. 11075 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 210 EMC - 618806001 6188-06-001 132,061.51 .00 132,061.51 .00 .00 132,061.51 132,061.51 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 132,061.51 .00 132,061.51 .00 .00 132,061.51 132,061.51 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3091102 MGR.NO. 055 PAGE 001 CONT 6188 SEC 06 JOB 001 RES ENGR CARRELL, JUDY PROJ EMC - 618806001 HWY FM2427 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 129,843.00 REPORT DATE 06/11/2009 15.16.38 CONTRACTOR A R BROTHERS CONSTRUCTION EST PERIOD MAR 23,2009 TO MAY 15,2009 EST NO 004 & FINAL SERVICES, INC. 11075 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6188-06-001 EMC - 618806001 11 FM2427 SHELBY -LIMITS - FM 2427 @ SOUTH CREEK WITHIN SAN AUG MAINT SECTION (SHELBY COUNTY) - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 132,061.51