1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10081104 MGR.NO. PAGE 001 CONT 6177 SEC 79 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 617779001 HWY FM0945 1805 N TIMBERLAND DR LUFK CNTY SAN JACINTO DIST 11 CONTRACT PRICE $ 57,350.00 REPORT DATE 07/15/2009 08.49.52 CONTRACTOR NIXON ENGINEERING, L.L.C. 13850 EST PERIOD MAR 03,2009 TO JUN 26,2009 EST NO 005 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 16, 2009 TIME COMPUTED FROM MAR 03, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 90 90 26 64 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 09 1 1 TOTAL DAYS ALLOWED = 90 2 1 DATE WORK COMPLETED 06/26/09 3 1 DAYS CHARGED TO DATE = 43 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 SATURDAY 7 1 SUNDAY LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 400 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 SATURDAY TO THE CONTRACTOR 14 1 SUNDAY 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 SATURDAY 21 1 SUNDAY 22 1 23 1 TIME SUSPENDED 24 1 TIME SUSPENDED 25 1 TIME SUSPENDED 26 1 WORK COMPLETED AND ACCEPTED - - ----- ----- ----- 116 43 73 3 SATURDAY 3 SUNDAY 0 HOLIDAY 3 TIME SUSPENDED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10081104 MGR.NO. PAGE 001 CONT 6177 SEC 79 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 617779001 HWY FM0945 1805 N TIMBERLAND DR LUFK CNTY SAN JACINTO DIST 11 CONTRACT PRICE $ 57,350.00 REPORT DATE 07/15/2009 08.49.53 CONTRACTOR NIXON ENGINEERING, L.L.C. 13850 EST PERIOD MAR 03,2009 TO JUN 26,2009 EST NO 005 & FINAL DIST. 11 COUNTY SAN JACINTO CONTROL 6177-79-001 PROJECT RMC - 617779001 HIGHWAY FM0945 0LIMITS- FM 945 & VARIOUS LOCATIONS WITHIN SAN JACINTO MAINT SECTION 0TYPE OF WORK- REMOVING AND INSTALLING SIGNS 0 0005 PREPARED BY DARRYL DINCANS, P.E., 07/14/08 0 0055 ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0644 INS SM RD SN SUP&AM TY 10BWG(1) SA(P) EA 38.000 32.000 200.000 6,400.00 0065 0644 INS SM RD SN SUP&AM TY 10BWG(1) SA(T) EA 9.000 10.000 250.000 2,500.00 0070 0644 INS SM RD SN SUP&AM TY 10BWG(1) SA(U) EA 2.000 2.000 400.000 800.00 0075 0644 INS SM RD SN SUP&AM TY S80(1) SA(T) EA 2.000 2.000 500.000 1,000.00 0080 0644 INS SM RD SN SUP&AM TY S80(1) SA(U) EA 2.000 2.000 500.000 1,000.00 0085 0644 INS SM RD SN SUP&AM TY TWT(1) WA(P) EA 220.000 219.000 170.000 37,230.00 0090 0644 INS SM RD SN SUP&AM TY TWT(1) WA(T) EA 8.000 9.000 300.000 2,700.00 0095 0644 REMOVE SM RD SN SUP & AM EA 6.000 4.000 400.000 1,600.00 0100 0658 INSTL OM ASSM (OM-3L)(TWT)WS EA 5.000 0.000 250.000 .00 0105 0658 INSTL OM ASSM (OM-3R)(TWT)WS EA 5.000 0.000 250.000 .00 0 SUBTOTAL BID ITEMS $ 53,230.00 0 TOTAL AMOUNT WORK DONE ROADWAY $ 53,230.00 0 TOTAL AMOUNT WORK DONE CONTROL 6177-79-001 $ 53,230.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10081104 MGR.NO. PAGE 001 CONT 6177 SEC 79 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 617779001 HWY FM0945 1805 N TIMBERLAND DR LUFK CNTY SAN JACINTO DIST 11 CONTRACT PRICE $ 57,350.00 REPORT DATE 07/15/2009 08.49.53 CONTRACTOR NIXON ENGINEERING, L.L.C. 13850 EST PERIOD MAR 03,2009 TO JUN 26,2009 EST NO 005 & FINAL 0*********************************************************************************************************************************** -LIMITS - FM 945 & VARIOUS LOCATIONS WITHIN 0 SAN JACINTO MAINT SECTION DATE WORK BEGAN MAR 16, 2009 WORKING DAYS USED 43 PERCENT COMPLETE 100.00 PERCENT TIME USED 47.70 DATE COMPLETED JUN 26 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6177-79-001 RMC - 617779001 11 FM0945 SAN JACINTO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0644 INS SM RD SN SUP&AM TY 10BWG(1) SA(P) EA 38.000 32.000 200.000 6,400.00 0644 INS SM RD SN SUP&AM TY 10BWG(1) SA(T) EA 9.000 10.000 250.000 2,500.00 0644 INS SM RD SN SUP&AM TY 10BWG(1) SA(U) EA 2.000 2.000 400.000 800.00 0644 INS SM RD SN SUP&AM TY S80(1) SA(T) EA 2.000 2.000 500.000 1,000.00 0644 INS SM RD SN SUP&AM TY S80(1) SA(U) EA 2.000 2.000 500.000 1,000.00 0644 INS SM RD SN SUP&AM TY TWT(1) WA(P) EA 220.000 219.000 170.000 37,230.00 0644 INS SM RD SN SUP&AM TY TWT(1) WA(T) EA 8.000 9.000 300.000 2,700.00 0644 REMOVE SM RD SN SUP & AM EA 6.000 4.000 400.000 1,600.00 0 SUBTOTAL BID ITEMS $ 53,230.00 0 CONTRACT TOTAL ALL ITEMS $ 53,230.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10081104 MGR.NO. PAGE 001 CONT 6177 SEC 79 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 617779001 HWY FM0945 1805 N TIMBERLAND DR LUFK CNTY SAN JACINTO DIST 11 CONTRACT PRICE $ 57,350.00 REPORT DATE 07/15/2009 08.49.53 CONTRACTOR NIXON ENGINEERING, L.L.C. 13850 EST PERIOD MAR 03,2009 TO JUN 26,2009 EST NO 005 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 204 RMC - 617779001 6177-79-001 53,230.00 .00 53,230.00 .00 .00 53,230.00 53,230.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 53,230.00 .00 53,230.00 .00 .00 53,230.00 53,230.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10081104 MGR.NO. PAGE 001 CONT 6177 SEC 79 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 617779001 HWY FM0945 1805 N TIMBERLAND DR LUFK CNTY SAN JACINTO DIST 11 CONTRACT PRICE $ 57,350.00 REPORT DATE 07/15/2009 08.49.54 CONTRACTOR NIXON ENGINEERING, L.L.C. 13850 EST PERIOD MAR 03,2009 TO JUN 26,2009 EST NO 005 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6177-79-001 RMC - 617779001 11 FM0945 SAN JACINTO -LIMITS - FM 945 & VARIOUS LOCATIONS WITHIN SAN JACINTO MAINT SECTION - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 53,230.00