1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1110501 MGR.NO. 051 PAGE 001 CONT 6212 SEC 53 JOB 001 RES ENGR JEREMY DEARING PROJ RMC - 621253001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY BAILEY DIST 05 CONTRACT PRICE $ 24,043.50 REPORT DATE 08/30/2012 10.08.20 CONTRACTOR CNR GROUND SOLUTIONS 14943 EST PERIOD APR 04,2011 TO JUN 06,2011 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 04, 2011 TIME COMPUTED FROM APR 04, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 45 64 0 64 BROUGHT FORWARD ADDL DAYS GRANTED = 0 *** ESTIMATE ALREADY POSTED *** TOTAL DAYS ALLOWED = 45 DATE WORK COMPLETED 06/06/11 DAYS CHARGED TO DATE = 0 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 400 0 LIQUIDATED DAMAGES 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 64 0 64 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1110501 MGR.NO. 051 PAGE 001 CONT 6212 SEC 53 JOB 001 RES ENGR JEREMY DEARING PROJ RMC - 621253001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY BAILEY DIST 05 CONTRACT PRICE $ 24,043.50 REPORT DATE 08/30/2012 10.08.21 CONTRACTOR CNR GROUND SOLUTIONS 14943 EST PERIOD APR 04,2011 TO JUN 06,2011 EST NO 003 & FINAL DIST. 05 COUNTY BAILEY CONTROL 6212-53-001 PROJECT RMC - 621253001 HIGHWAY US0084 0LIMITS- VARIOUS COUNTIES IN LUBBOCK DISTRICT BAILEY,HOCKLEY,LUBBOCK,PARMER,SWISHER 0TYPE OF WORK- TREE REMOVAL 0 0005 PREPARED OCTOBER 20, 2010 BY JEREMY T. DEARING 0 0055 ROADWAY NET LENGTH 0.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0752 TREE REMOVAL (4"-12" DIA) EA 11.000 0.000 286.000 .00 0065 0752 TREE REMOVAL (12"-18" DIA) EA 7.000 0.000 286.000 .00 0070 0752 TREE REMOVAL (18"-24" DIA) EA 7.000 0.000 286.000 .00 0075 0752 TREE REMOVAL (24"-30" DIA) EA 23.000 0.000 286.000 .00 0080 0752 TREE REMOVAL (30"-36" DIA) EA 13.000 0.000 286.000 .00 0085 0752 TREE REMOVAL (36"-42" DIA) EA 13.000 0.000 286.000 .00 0090 0752 TREE REMOVAL (42"-48" DIA) EA 10.000 0.000 287.950 .00 0 TOTAL AMOUNT WORK DONE ROADWAY $ .00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1110501 MGR.NO. 051 PAGE 001 CONT 6212 SEC 53 JOB 001 RES ENGR JEREMY DEARING PROJ RMC - 621253001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY BAILEY DIST 05 CONTRACT PRICE $ 24,043.50 REPORT DATE 08/30/2012 10.08.21 CONTRACTOR CNR GROUND SOLUTIONS 14943 EST PERIOD APR 04,2011 TO JUN 06,2011 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS COUNTIES IN LUBBOCK DISTRICT 0 BAILEY,HOCKLEY,LUBBOCK,PARMER,SWISHER DATE WORK BEGAN APR 4 , 2011 WORKING DAYS USED 0 PERCENT COMPLETE 0.00 PERCENT TIME USED 0.00 DATE COMPLETED JUN 6 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6212-53-001 RMC - 621253001 05 US0084 BAILEY 0***** NO WORK TO DATE FOR CONTRACT ***** 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1110501 MGR.NO. 051 PAGE 001 CONT 6212 SEC 53 JOB 001 RES ENGR JEREMY DEARING PROJ RMC - 621253001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY BAILEY DIST 05 CONTRACT PRICE $ 24,043.50 REPORT DATE 08/30/2012 10.08.21 CONTRACTOR CNR GROUND SOLUTIONS 14943 EST PERIOD APR 04,2011 TO JUN 06,2011 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 9 RMC - 621253001 6212-53-001 .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1110501 MGR.NO. 051 PAGE 001 CONT 6212 SEC 53 JOB 001 RES ENGR JEREMY DEARING PROJ RMC - 621253001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY BAILEY DIST 05 CONTRACT PRICE $ 24,043.50 REPORT DATE 08/30/2012 10.08.21 CONTRACTOR CNR GROUND SOLUTIONS 14943 EST PERIOD APR 04,2011 TO JUN 06,2011 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6212-53-001 RMC - 621253001 05 US0084 BAILEY -LIMITS - VARIOUS COUNTIES IN LUBBOCK DISTRICT BAILEY,HOCKLEY,LUBBOCK,PARMER,SWISHER - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 0.00