1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5090501 MGR.NO. 056 PAGE 001 CONT 6193 SEC 68 JOB 001 RES ENGR WILSON, BRYAN PROJ BPM - 619368001 HWY US0087 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 78,394.00 REPORT DATE 09/15/2009 11.16.47 CONTRACTOR BEAR CREEK CONSTRUCTION, LLC 12853 EST PERIOD JUL 28,2009 TO AUG 31,2009 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 28, 2009 TIME COMPUTED FROM JUL 28, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 34 4 1 3 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 NO WORK DAY - (NIGHT WORK PROJECT) TOTAL DAYS ALLOWED = 34 2 1 DATE WORK COMPLETED 08/26/09 3 1 DAYS CHARGED TO DATE = 19 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 425 6 1 7 1 NO WORK DAY - (NIGHT WORK PROJECT) LIQUIDATED DAMAGES 8 1 NO WORK DAY - (NIGHT WORK PROJECT) 0 DAYS AT $ 425 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 NO WORK DAY - (NIGHT WORK PROJECT) 15 1 NO WORK DAY - (NIGHT WORK PROJECT) 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 NO WORK DAY - (NIGHT WORK PROJECT) 22 1 NO WORK DAY - (NIGHT WORK PROJECT) 23 1 24 1 25 1 26 1 WORK COMPLETED AND ACCEPTED - - ----- ----- ----- 30 19 11 0 SATURDAY 0 SUNDAY 0 HOLIDAY 7 NO WORK DAY - (NIGHT WORK PROJECT) 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5090501 MGR.NO. 056 PAGE 001 CONT 6193 SEC 68 JOB 001 RES ENGR WILSON, BRYAN PROJ BPM - 619368001 HWY US0087 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 78,394.00 REPORT DATE 09/15/2009 11.16.48 CONTRACTOR BEAR CREEK CONSTRUCTION, LLC 12853 EST PERIOD JUL 28,2009 TO AUG 31,2009 EST NO 003 & FINAL DIST. 05 COUNTY LUBBOCK CONTROL 6193-68-001 PROJECT BPM - 619368001 HIGHWAY US0087 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- CONCRETE STRUCTURE REPAIR 0 0005 ESTIMATE CREATED 4-8-2009 MICHAEL STROOPE PE 0 0055 BEAM REPAIR, CONCRETE STRUCTURE REP NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0429 CONC STRUCT REPAIR SF 100.000 57.460 100.000 5,746.00 0065 0454 HEADER TYPE EXPANSION JOINT CF 59.200 58.845 420.000 24,714.90 0070 0454 JOINT SEALANT LF 364.000 363.800 7.500 2,728.50 0075 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 5,000.000 10,000.00 0080 0788 CONCRETE BEAM REPAIR EA 1.000 1.000 7,000.000 7,000.00 0085 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 68.000 15.000 350.000 5,250.00 0 SUBTOTAL BID ITEMS $ 55,439.40 0 TOTAL AMOUNT WORK DONE BEAM REPAIR, CONCRETE STRUCTURE REP $ 55,439.40 0 TOTAL AMOUNT WORK DONE CONTROL 6193-68-001 $ 55,439.40 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5090501 MGR.NO. 056 PAGE 001 CONT 6193 SEC 68 JOB 001 RES ENGR WILSON, BRYAN PROJ BPM - 619368001 HWY US0087 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 78,394.00 REPORT DATE 09/15/2009 11.16.48 CONTRACTOR BEAR CREEK CONSTRUCTION, LLC 12853 EST PERIOD JUL 28,2009 TO AUG 31,2009 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JUL 28, 2009 WORKING DAYS USED 19 PERCENT COMPLETE 100.00 PERCENT TIME USED 55.80 DATE COMPLETED AUG 26 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6193-68-001 BPM - 619368001 05 US0087 LUBBOCK - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0429 CONC STRUCT REPAIR SF 100.000 57.460 100.000 5,746.00 0454 HEADER TYPE EXPANSION JOINT CF 59.200 58.845 420.000 24,714.90 0454 JOINT SEALANT LF 364.000 363.800 7.500 2,728.50 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 5,000.000 10,000.00 0788 CONCRETE BEAM REPAIR EA 1.000 1.000 7,000.000 7,000.00 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 68.000 15.000 350.000 5,250.00 0 SUBTOTAL BID ITEMS $ 55,439.40 0 CONTRACT TOTAL ALL ITEMS $ 55,439.40 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5090501 MGR.NO. 056 PAGE 001 CONT 6193 SEC 68 JOB 001 RES ENGR WILSON, BRYAN PROJ BPM - 619368001 HWY US0087 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 78,394.00 REPORT DATE 09/15/2009 11.16.48 CONTRACTOR BEAR CREEK CONSTRUCTION, LLC 12853 EST PERIOD JUL 28,2009 TO AUG 31,2009 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 152 BPM - 619368001 6193-68-001 55,439.40 .00 55,439.40 .00 .00 55,439.40 55,439.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 55,439.40 .00 55,439.40 .00 .00 55,439.40 55,439.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5090501 MGR.NO. 056 PAGE 001 CONT 6193 SEC 68 JOB 001 RES ENGR WILSON, BRYAN PROJ BPM - 619368001 HWY US0087 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 78,394.00 REPORT DATE 09/15/2009 11.16.49 CONTRACTOR BEAR CREEK CONSTRUCTION, LLC 12853 EST PERIOD JUL 28,2009 TO AUG 31,2009 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6193-68-001 BPM - 619368001 05 US0087 LUBBOCK -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 55,439.40