1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4090501 MGR.NO. 053 PAGE 001 CONT 6187 SEC 69 JOB 001 RES ENGR PEREZ, STEVAN PROJ RMC - 618769001 HWY FM0292 P.O. BOX 868 LITTLEFIELD CNTY PARMER DIST 05 CONTRACT PRICE $ 66,206.00 REPORT DATE 09/01/2009 11.16.14 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUN 23,2009 TO JUL 31,2009 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 30, 2009 TIME COMPUTED FROM JUN 23, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 40 8 1 7 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 09 1 1 CHARGE DAY BUT CONTRACTOR NOT STARTED TOTAL DAYS ALLOWED = 40 2 1 CHARGE DAY BUT CONTRACTOR NOT STARTED DATE WORK COMPLETED 07/31/09 3 1 CHARGE DAY BUT CONTRACTOR NOT STARTED DAYS CHARGED TO DATE = 20 4 1 HOLIDAY ASSESSED LIQ DAMAGES = 0 5 1 SUNDAY LIQ DAMAGE RATE $ 425 6 1 CHARGE DAY BUT CONTRACTOR NOT STARTED 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 425 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 SATURDAY CERTIFIED AS CORRECT AND 12 1 SUNDAY ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 SATURDAY 19 1 SUNDAY 20 1 21 1 22 1 TOO WET 23 1 24 1 25 1 SATURDAY 26 1 SUNDAY 27 1 28 1 UNAVAILABILITY OF MATERIAL 29 1 UNAVAILABILITY OF MATERIAL 30 1 WORK COMPLETED 31 1 ----- ----- ----- 39 20 19 3 SATURDAY 4 SUNDAY 1 HOLIDAY 1 TOO WET 2 UNAVAILABILITY OF MATERIAL 1 WORK COMPLETED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4090501 MGR.NO. 053 PAGE 001 CONT 6187 SEC 69 JOB 001 RES ENGR PEREZ, STEVAN PROJ RMC - 618769001 HWY FM0292 P.O. BOX 868 LITTLEFIELD CNTY PARMER DIST 05 CONTRACT PRICE $ 66,206.00 REPORT DATE 09/01/2009 11.16.15 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUN 23,2009 TO JUL 31,2009 EST NO 003 & FINAL DIST. 05 COUNTY PARMER CONTROL 6187-69-001 PROJECT RMC - 618769001 HIGHWAY FM0292 0LIMITS- VARIOUS LOCATIONS IN PARMER COUNTY 0TYPE OF WORK- INSTALL CONCRETE RAIL, SET AND INLET 0 0005 PREPARED ON NOVEMBER 25, 2008 0 0055 ROADWAY NET LENGTH 0.018 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0432 RIPRAP (MOW STRIP)(5 IN) CY 6.800 6.800 750.000 5,100.00 0065 0450 RAIL (TY T501)(RETROFIT) LF 99.320 99.320 300.000 29,796.00 0070 0464 RC PIPE (CL III)(24 IN) LF 6.000 6.000 300.000 1,800.00 0075 0465 INLET (COMPL)(SPL) EA 1.000 1.000 17,000.000 17,000.00 0080 0467 SET (TY II)(24 IN)(RCP)(6:1)(C) EA 1.000 1.000 3,000.000 3,000.00 0085 0480 CLEAN EXIST CULVS EA 1.000 1.000 2,000.000 2,000.00 0090 0540 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 1.000 1.000 2,000.000 2,000.00 0095 0542 REMOVING METAL BEAM GUARD FENCE LF 57.000 57.000 30.000 1,710.00 0100 0542 REMOVING TERMINAL ANCHOR SECTION EA 1.000 1.000 1,200.000 1,200.00 0105 0544 GDRAIL END TRT(INST)(WOOD POST)(TY III) EA 1.000 1.000 2,600.000 2,600.00 0 SUBTOTAL BID ITEMS $ 66,206.00 0 TOTAL AMOUNT WORK DONE ROADWAY $ 66,206.00 0 TOTAL AMOUNT WORK DONE CONTROL 6187-69-001 $ 66,206.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4090501 MGR.NO. 053 PAGE 001 CONT 6187 SEC 69 JOB 001 RES ENGR PEREZ, STEVAN PROJ RMC - 618769001 HWY FM0292 P.O. BOX 868 LITTLEFIELD CNTY PARMER DIST 05 CONTRACT PRICE $ 66,206.00 REPORT DATE 09/01/2009 11.16.15 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUN 23,2009 TO JUL 31,2009 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS 0 IN PARMER COUNTY DATE WORK BEGAN JUN 30, 2009 WORKING DAYS USED 20 PERCENT COMPLETE 100.00 PERCENT TIME USED 50.00 DATE COMPLETED JUL 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6187-69-001 RMC - 618769001 05 FM0292 PARMER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0432 RIPRAP (MOW STRIP)(5 IN) CY 6.800 6.800 750.000 5,100.00 0450 RAIL (TY T501)(RETROFIT) LF 99.320 99.320 300.000 29,796.00 0464 RC PIPE (CL III)(24 IN) LF 6.000 6.000 300.000 1,800.00 0465 INLET (COMPL)(SPL) EA 1.000 1.000 17,000.000 17,000.00 0467 SET (TY II)(24 IN)(RCP)(6:1)(C) EA 1.000 1.000 3,000.000 3,000.00 0480 CLEAN EXIST CULVS EA 1.000 1.000 2,000.000 2,000.00 0540 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 1.000 1.000 2,000.000 2,000.00 0542 REMOVING METAL BEAM GUARD FENCE LF 57.000 57.000 30.000 1,710.00 0542 REMOVING TERMINAL ANCHOR SECTION EA 1.000 1.000 1,200.000 1,200.00 0544 GDRAIL END TRT(INST)(WOOD POST)(TY III) EA 1.000 1.000 2,600.000 2,600.00 0 SUBTOTAL BID ITEMS $ 66,206.00 0 CONTRACT TOTAL ALL ITEMS $ 66,206.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4090501 MGR.NO. 053 PAGE 001 CONT 6187 SEC 69 JOB 001 RES ENGR PEREZ, STEVAN PROJ RMC - 618769001 HWY FM0292 P.O. BOX 868 LITTLEFIELD CNTY PARMER DIST 05 CONTRACT PRICE $ 66,206.00 REPORT DATE 09/01/2009 11.16.15 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUN 23,2009 TO JUL 31,2009 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 185 RMC - 618769001 6187-69-001 66,206.00 .00 66,206.00 .00 .00 66,206.00 66,206.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 66,206.00 .00 66,206.00 .00 .00 66,206.00 66,206.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4090501 MGR.NO. 053 PAGE 001 CONT 6187 SEC 69 JOB 001 RES ENGR PEREZ, STEVAN PROJ RMC - 618769001 HWY FM0292 P.O. BOX 868 LITTLEFIELD CNTY PARMER DIST 05 CONTRACT PRICE $ 66,206.00 REPORT DATE 09/01/2009 11.16.15 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUN 23,2009 TO JUL 31,2009 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6187-69-001 RMC - 618769001 05 FM0292 PARMER -LIMITS - VARIOUS LOCATIONS IN PARMER COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 66,206.00