1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12080501 MGR.NO. 056 PAGE 001 CONT 6180 SEC 47 JOB 001 RES ENGR WILSON, BRYAN P.E. PROJ BPM - 618047001 HWY LP0289 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 264,400.00 REPORT DATE 09/16/2009 12.35.50 CONTRACTOR M & S CONCRETE CO. 11220 EST PERIOD MAY 01,2009 TO AUG 31,2009 EST NO 005 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 01, 2009 TIME COMPUTED FROM MAY 01, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 60 92 62 30 BROUGHT FORWARD ADDL DAYS GRANTED = 22 AUG 09 1 1 SATURDAY TOTAL DAYS ALLOWED = 82 2 1 SUNDAY DATE WORK COMPLETED 08/31/09 3 1 DAYS CHARGED TO DATE = 82 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 400 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 SATURDAY 16 1 SUNDAY ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 SATURDAY 23 1 SUNDAY 24 1 25 1 26 1 27 1 28 1 29 1 SATURDAY 30 1 SUNDAY 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 123 82 41 5 SATURDAY 5 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12080501 MGR.NO. 056 PAGE 001 CONT 6180 SEC 47 JOB 001 RES ENGR WILSON, BRYAN P.E. PROJ BPM - 618047001 HWY LP0289 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 264,400.00 REPORT DATE 09/16/2009 12.35.50 CONTRACTOR M & S CONCRETE CO. 11220 EST PERIOD MAY 01,2009 TO AUG 31,2009 EST NO 005 & FINAL DIST. 05 COUNTY LUBBOCK CONTROL 6180-47-001 PROJECT BPM - 618047001 HIGHWAY LP0289 0LIMITS- VARIOUS LOCATIONS IN LUBBOCK COUNTY 0TYPE OF WORK- STRUCTURAL CONCRETE REPAIR 0 0005 ESTIMATE CREATED 9-18-2008 MICHAEL STROOPE PE 0 0055 STRUCTURAL CONCRETE REPAIR, RIPRAP NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0401 FLOWABLE BACKFILL CY 330.000 166.204 160.000 26,592.64 0065 0429 CONC STRUCT REPAIR SF 1,020.000 1,495.053 100.000 149,505.30 0070 0432 RIPRAP (CONC)(4 IN) CY 56.000 46.166 600.000 27,699.60 0075 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 15,000.000 60,000.00 0080 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 160.000 6.000 100.000 600.00 0 SUBTOTAL BID ITEMS $ 264,397.54 0 TOTAL AMOUNT WORK DONE STRUCTURAL CONCRETE REPAIR, RIPRAP $ 264,397.54 0 TOTAL AMOUNT WORK DONE CONTROL 6180-47-001 $ 264,397.54 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12080501 MGR.NO. 056 PAGE 001 CONT 6180 SEC 47 JOB 001 RES ENGR WILSON, BRYAN P.E. PROJ BPM - 618047001 HWY LP0289 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 264,400.00 REPORT DATE 09/16/2009 12.35.51 CONTRACTOR M & S CONCRETE CO. 11220 EST PERIOD MAY 01,2009 TO AUG 31,2009 EST NO 005 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS 0 IN LUBBOCK COUNTY DATE WORK BEGAN MAY 1 , 2009 WORKING DAYS USED 82 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED AUG 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6180-47-001 BPM - 618047001 05 LP0289 LUBBOCK - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0401 FLOWABLE BACKFILL CY 330.000 166.204 160.000 26,592.64 0429 CONC STRUCT REPAIR SF 1,020.000 1,495.053 100.000 149,505.30 0432 RIPRAP (CONC)(4 IN) CY 56.000 46.166 600.000 27,699.60 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 15,000.000 60,000.00 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 160.000 6.000 100.000 600.00 0 SUBTOTAL BID ITEMS $ 264,397.54 0 CONTRACT TOTAL ALL ITEMS $ 264,397.54 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12080501 MGR.NO. 056 PAGE 001 CONT 6180 SEC 47 JOB 001 RES ENGR WILSON, BRYAN P.E. PROJ BPM - 618047001 HWY LP0289 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 264,400.00 REPORT DATE 09/16/2009 12.35.51 CONTRACTOR M & S CONCRETE CO. 11220 EST PERIOD MAY 01,2009 TO AUG 31,2009 EST NO 005 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 152 BPM - 618047001 6180-47-001 264,397.54 .00 264,397.54 .00 .00 264,397.54 264,397.54 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 264,397.54 .00 264,397.54 .00 .00 264,397.54 264,397.54 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12080501 MGR.NO. 056 PAGE 001 CONT 6180 SEC 47 JOB 001 RES ENGR WILSON, BRYAN P.E. PROJ BPM - 618047001 HWY LP0289 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 264,400.00 REPORT DATE 09/16/2009 12.35.51 CONTRACTOR M & S CONCRETE CO. 11220 EST PERIOD MAY 01,2009 TO AUG 31,2009 EST NO 005 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6180-47-001 BPM - 618047001 05 LP0289 LUBBOCK -LIMITS - VARIOUS LOCATIONS IN LUBBOCK COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 264,397.54