1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12121231 MGR.NO. 064 PAGE 001 CONT 6250 SEC 97 JOB 001 RES ENGR VOLK, JEFFREY PROJ SUP - 625097001 HWY IH0010 7022 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 291,827.99 REPORT DATE 05/08/2013 07.38.03 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 THE TEXAS HOUSE 09728 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN DEC 10, 2012 TIME COMPUTED FROM DEC 10, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 112 112 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 142 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 142 142 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12121231 MGR.NO. 064 PAGE 001 CONT 6250 SEC 97 JOB 001 RES ENGR VOLK, JEFFREY PROJ SUP - 625097001 HWY IH0010 7022 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 291,827.99 REPORT DATE 05/08/2013 07.38.03 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 THE TEXAS HOUSE 09728 DIST. 12 COUNTY HARRIS CONTROL 6250-97-001 PROJECT SUP - 625097001 HIGHWAY IH0010 0LIMITS- VARIOUS HWYS IN EAST HARRIS COUNTY VARIOUS HWYS IN EAST HARRIS COUNTY 0TYPE OF WORK- LITTER REMOVAL 0 0050 LITTER REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY RHONDA K. LANGE 0 0075 0734 LITTER REMOVAL(SPOT) AC 250.000 0.000 13.000 .00 0080 0734 LITTER REMOVAL - TRACT (1) CYC 7.000 0.000 1,387.360 .00 0085 0734 LITTER REMOVAL - TRACT (2) CYC 13.000 6.000 2,298.042 13,788.25 0090 0734 LITTER REMOVAL - TRACT (3) CYC 13.000 6.000 2,304.850 13,829.10 0095 0734 LITTER REMOVAL - TRACT (4) CYC 8.000 5.000 2,405.400 12,027.00 0100 0734 LITTER REMOVAL - TRACT (5) CYC 13.000 5.000 5,254.240 26,271.20 0105 0734 LITTER REMOVAL - TRACT (6) CYC 17.000 8.000 1,604.600 12,836.80 0110 0734 LITTER REMOVAL - TRACT (7) CYC 17.000 8.000 1,879.380 15,035.04 0115 0734 LITTER REMOVAL - TRACT (8) CYC 8.000 4.000 1,535.650 6,142.60 0120 0734 LITTER REMOVAL - TRACT (9) CYC 8.000 0.000 1,724.120 .00 0125 0734 LITTER REMOVAL - TRACT (10) CYC 9.000 5.000 436.700 2,183.50 0130 0734 LITTER REMOVAL - TRACT (11) CYC 17.000 8.000 1,490.720 11,925.76 0135 0734 LITTER REMOVAL - TRACT (12) CYC 12.000 5.000 800.990 4,004.95 0140 0734 LITTER REMOVAL - TRACT (13) CYC 13.000 0.000 500.526 .00 0145 0734 LITTER REMOVAL - TRACT (14) CYC 8.000 4.000 97.934 391.74 0 SUBTOTAL BID ITEMS $ 118,435.94 0 TOTAL AMOUNT WORK DONE LITTER REMOVAL $ 118,435.94 0 TOTAL AMOUNT WORK DONE CONTROL 6250-97-001 $ 118,435.94 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12121231 MGR.NO. 064 PAGE 001 CONT 6250 SEC 97 JOB 001 RES ENGR VOLK, JEFFREY PROJ SUP - 625097001 HWY IH0010 7022 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 291,827.99 REPORT DATE 05/08/2013 07.38.04 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 THE TEXAS HOUSE 09728 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN EAST HARRIS COUNTY 0 VARIOUS HWYS IN EAST HARRIS COUNTY DATE WORK BEGAN DEC 10, 2012 WORKING DAYS USED 142 PERCENT COMPLETE 40.58 PERCENT TIME USED 38.90 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6250-97-001 SUP - 625097001 12 IH0010 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (2) CYC 13.000 6.000 2,298.042 13,788.25 0734 LITTER REMOVAL - TRACT (3) CYC 13.000 6.000 2,304.850 13,829.10 0734 LITTER REMOVAL - TRACT (4) CYC 8.000 5.000 2,405.400 12,027.00 0734 LITTER REMOVAL - TRACT (5) CYC 13.000 5.000 5,254.240 26,271.20 0734 LITTER REMOVAL - TRACT (6) CYC 17.000 8.000 1,604.600 12,836.80 0734 LITTER REMOVAL - TRACT (7) CYC 17.000 8.000 1,879.380 15,035.04 0734 LITTER REMOVAL - TRACT (8) CYC 8.000 4.000 1,535.650 6,142.60 0734 LITTER REMOVAL - TRACT (10) CYC 9.000 5.000 436.700 2,183.50 0734 LITTER REMOVAL - TRACT (11) CYC 17.000 8.000 1,490.720 11,925.76 0734 LITTER REMOVAL - TRACT (12) CYC 12.000 5.000 800.990 4,004.95 0734 LITTER REMOVAL - TRACT (14) CYC 8.000 4.000 97.934 391.74 0 SUBTOTAL BID ITEMS $ 118,435.94 0 CONTRACT TOTAL ALL ITEMS $ 118,435.94 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12121231 MGR.NO. 064 PAGE 001 CONT 6250 SEC 97 JOB 001 RES ENGR VOLK, JEFFREY PROJ SUP - 625097001 HWY IH0010 7022 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 291,827.99 REPORT DATE 05/08/2013 07.38.04 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 THE TEXAS HOUSE 09728 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 SUP - 625097001 6250-97-001 118,435.94 .00 118,435.94 .00 .00 118,435.94 97,662.98 20,772.96 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 118,435.94 .00 118,435.94 .00 .00 118,435.94 97,662.98 20,772.96 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12121231 MGR.NO. 064 PAGE 001 CONT 6250 SEC 97 JOB 001 RES ENGR VOLK, JEFFREY PROJ SUP - 625097001 HWY IH0010 7022 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 291,827.99 REPORT DATE 05/08/2013 07.38.04 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 THE TEXAS HOUSE 09728 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6250-97-001 SUP - 625097001 12 IH0010 HARRIS -LIMITS - VARIOUS HWYS IN EAST HARRIS COUNTY VARIOUS HWYS IN EAST HARRIS COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 85 0734 LITTER REMOVAL - TRACT (2) CYC 13.000 2.000 2,298.042 4,596.08 90 0734 LITTER REMOVAL - TRACT (3) CYC 13.000 1.000 2,304.850 2,304.85 95 0734 LITTER REMOVAL - TRACT (4) CYC 8.000 1.000 2,405.400 2,405.40 100 0734 LITTER REMOVAL - TRACT (5) CYC 13.000 1.000 5,254.240 5,254.24 105 0734 LITTER REMOVAL - TRACT (6) CYC 17.000 1.000 1,604.600 1,604.60 110 0734 LITTER REMOVAL - TRACT (7) CYC 17.000 1.000 1,879.380 1,879.38 125 0734 LITTER REMOVAL - TRACT (10) CYC 9.000 1.000 436.700 436.70 130 0734 LITTER REMOVAL - TRACT (11) CYC 17.000 1.000 1,490.720 1,490.72 135 0734 LITTER REMOVAL - TRACT (12) CYC 12.000 1.000 800.990 800.99 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 20,772.96 0 TOTAL AMOUNT WORK DONE TO DATE - $ 118,435.94