1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9121231 MGR.NO. 058 PAGE 001 CONT 6249 SEC 85 JOB 001 RES ENGR GARCIA, JESSE PROJ SUP - 624985001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 465,446.88 REPORT DATE 04/29/2013 14.04.37 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO MAR 31,2013 EST NO 006 RUCON, INC. 10168 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 01, 2012 TIME COMPUTED FROM OCT 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 151 151 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 13 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 182 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 182 182 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9121231 MGR.NO. 058 PAGE 001 CONT 6249 SEC 85 JOB 001 RES ENGR GARCIA, JESSE PROJ SUP - 624985001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 465,446.88 REPORT DATE 04/29/2013 14.04.38 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO MAR 31,2013 EST NO 006 RUCON, INC. 10168 DIST. 12 COUNTY HARRIS CONTROL 6249-85-001 PROJECT SUP - 624985001 HIGHWAY US0290 0LIMITS- VARIOUS HIGHWAYS IN WEST HARRIS CO. . 0TYPE OF WORK- LITTER PICKUP 0 0005 PREPARED BY JESUS R. GARCIA, JR., P.E. 0 0055 LITTER PICKUP NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL(SPOT) AC 150.000 0.000 13.000 .00 0065 0734 LITTER REMOVAL - TRACT (1) CYC 13.000 6.000 355.410 2,132.46 0070 0734 LITTER REMOVAL - TRACT (2) CYC 13.000 6.000 96.490 578.94 0075 0734 LITTER REMOVAL - TRACT (3) CYC 26.000 13.000 376.730 4,897.49 0080 0734 LITTER REMOVAL - TRACT (4) CYC 26.000 13.000 628.530 8,170.89 0085 0734 LITTER REMOVAL - TRACT (5) CYC 26.000 13.000 320.940 4,172.22 0090 0734 LITTER REMOVAL - TRACT (6) CYC 26.000 13.000 320.940 4,172.22 0095 0734 LITTER REMOVAL - TRACT (7) CYC 52.000 25.000 2,129.580 53,239.50 0100 0734 LITTER REMOVAL - TRACT (8) CYC 52.000 25.000 1,418.800 35,470.00 0105 0734 LITTER REMOVAL - TRACT (9) CYC 2.000 1.000 1,256.900 1,256.90 0110 0734 LITTER REMOVAL - TRACT (10) CYC 26.000 10.000 276.900 2,769.00 0115 0734 LITTER REMOVAL - TRACT (11) CYC 4.000 2.000 2,072.300 4,144.60 0120 0734 LITTER REMOVAL - TRACT (12) CYC 13.000 6.000 176.930 1,061.58 0125 0734 LITTER REMOVAL - TRACT (13) CYC 4.000 2.000 585.480 1,170.96 0130 0734 LITTER REMOVAL - TRACT (14) CYC 8.000 4.000 1,294.580 5,178.32 0135 0734 LITTER REMOVAL - TRACT (15) CYC 12.000 6.000 208.400 1,250.40 0140 0734 LITTER REMOVAL - TRACT (16) CYC 12.000 6.000 213.400 1,280.40 0145 0734 LITTER REMOVAL - TRACT (17) CYC 9.000 3.000 802.670 2,408.01 0150 0734 LITTER REMOVAL - TRACT (18) CYC 12.000 6.000 638.540 3,831.24 0155 0734 LITTER REMOVAL - TRACT (19) CYC 26.000 13.000 387.620 5,039.06 0160 0734 LITTER REMOVAL - TRACT (20) CYC 13.000 6.000 2,208.580 13,251.48 0165 0734 LITTER REMOVAL - TRACT (21) CYC 12.000 6.000 191.640 1,149.84 0170 0734 LITTER REMOVAL - TRACT (22) CYC 12.000 6.000 1,114.160 6,684.96 0175 0734 LITTER REMOVAL - TRACT (23) CYC 26.000 12.000 1,022.410 12,268.92 0180 0734 LITTER REMOVAL - TRACT (24) CYC 26.000 13.000 968.690 12,592.97 0185 0734 LITTER REMOVAL - TRACT (25) CYC 26.000 13.000 1,215.140 15,796.82 0190 0734 LITTER REMOVAL - TRACT (26) CYC 26.000 13.000 1,519.620 19,755.06 0 SUBTOTAL BID ITEMS $ 223,724.24 1 TOTAL AMOUNT WORK DONE LITTER PICKUP $ 223,724.24 0 TOTAL AMOUNT WORK DONE CONTROL 6249-85-001 $ 223,724.24 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9121231 MGR.NO. 058 PAGE 001 CONT 6249 SEC 85 JOB 001 RES ENGR GARCIA, JESSE PROJ SUP - 624985001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 465,446.88 REPORT DATE 04/29/2013 14.04.38 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO MAR 31,2013 EST NO 006 RUCON, INC. 10168 0*********************************************************************************************************************************** -LIMITS - VARIOUS HIGHWAYS IN WEST HARRIS CO. 0 . DATE WORK BEGAN OCT 1 , 2012 WORKING DAYS USED 182 PERCENT COMPLETE 48.06 PERCENT TIME USED 49.80 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6249-85-001 SUP - 624985001 12 US0290 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) CYC 13.000 6.000 355.410 2,132.46 0734 LITTER REMOVAL - TRACT (2) CYC 13.000 6.000 96.490 578.94 0734 LITTER REMOVAL - TRACT (3) CYC 26.000 13.000 376.730 4,897.49 0734 LITTER REMOVAL - TRACT (4) CYC 26.000 13.000 628.530 8,170.89 0734 LITTER REMOVAL - TRACT (5) CYC 26.000 13.000 320.940 4,172.22 0734 LITTER REMOVAL - TRACT (6) CYC 26.000 13.000 320.940 4,172.22 0734 LITTER REMOVAL - TRACT (7) CYC 52.000 25.000 2,129.580 53,239.50 0734 LITTER REMOVAL - TRACT (8) CYC 52.000 25.000 1,418.800 35,470.00 0734 LITTER REMOVAL - TRACT (9) CYC 2.000 1.000 1,256.900 1,256.90 0734 LITTER REMOVAL - TRACT (10) CYC 26.000 10.000 276.900 2,769.00 0734 LITTER REMOVAL - TRACT (11) CYC 4.000 2.000 2,072.300 4,144.60 0734 LITTER REMOVAL - TRACT (12) CYC 13.000 6.000 176.930 1,061.58 0734 LITTER REMOVAL - TRACT (13) CYC 4.000 2.000 585.480 1,170.96 0734 LITTER REMOVAL - TRACT (14) CYC 8.000 4.000 1,294.580 5,178.32 0734 LITTER REMOVAL - TRACT (15) CYC 12.000 6.000 208.400 1,250.40 0734 LITTER REMOVAL - TRACT (16) CYC 12.000 6.000 213.400 1,280.40 0734 LITTER REMOVAL - TRACT (17) CYC 9.000 3.000 802.670 2,408.01 0734 LITTER REMOVAL - TRACT (18) CYC 12.000 6.000 638.540 3,831.24 0734 LITTER REMOVAL - TRACT (19) CYC 26.000 13.000 387.620 5,039.06 0734 LITTER REMOVAL - TRACT (20) CYC 13.000 6.000 2,208.580 13,251.48 0734 LITTER REMOVAL - TRACT (21) CYC 12.000 6.000 191.640 1,149.84 0734 LITTER REMOVAL - TRACT (22) CYC 12.000 6.000 1,114.160 6,684.96 0734 LITTER REMOVAL - TRACT (23) CYC 26.000 12.000 1,022.410 12,268.92 0734 LITTER REMOVAL - TRACT (24) CYC 26.000 13.000 968.690 12,592.97 0734 LITTER REMOVAL - TRACT (25) CYC 26.000 13.000 1,215.140 15,796.82 10734 LITTER REMOVAL - TRACT (26) CYC 26.000 13.000 1,519.620 19,755.06 0 SUBTOTAL BID ITEMS $ 223,724.24 0 CONTRACT TOTAL ALL ITEMS $ 223,724.24 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9121231 MGR.NO. 058 PAGE 001 CONT 6249 SEC 85 JOB 001 RES ENGR GARCIA, JESSE PROJ SUP - 624985001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 465,446.88 REPORT DATE 04/29/2013 14.04.38 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO MAR 31,2013 EST NO 006 RUCON, INC. 10168 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 SUP - 624985001 6249-85-001 223,724.24 .00 223,724.24 .00 .00 223,724.24 183,773.14 39,951.10 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 223,724.24 .00 223,724.24 .00 .00 223,724.24 183,773.14 39,951.10 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9121231 MGR.NO. 058 PAGE 001 CONT 6249 SEC 85 JOB 001 RES ENGR GARCIA, JESSE PROJ SUP - 624985001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 465,446.88 REPORT DATE 04/29/2013 14.04.39 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD MAR 01,2013 TO MAR 31,2013 EST NO 006 RUCON, INC. 10168 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6249-85-001 SUP - 624985001 12 US0290 HARRIS -LIMITS - VARIOUS HIGHWAYS IN WEST HARRIS CO. . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0734 LITTER REMOVAL - TRACT (1) CYC 13.000 1.000 355.410 355.41 70 0734 LITTER REMOVAL - TRACT (2) CYC 13.000 1.000 96.490 96.49 75 0734 LITTER REMOVAL - TRACT (3) CYC 26.000 3.000 376.730 1,130.19 80 0734 LITTER REMOVAL - TRACT (4) CYC 26.000 3.000 628.530 1,885.59 85 0734 LITTER REMOVAL - TRACT (5) CYC 26.000 3.000 320.940 962.82 90 0734 LITTER REMOVAL - TRACT (6) CYC 26.000 3.000 320.940 962.82 95 0734 LITTER REMOVAL - TRACT (7) CYC 52.000 4.000 2,129.580 8,518.32 100 0734 LITTER REMOVAL - TRACT (8) CYC 52.000 4.000 1,418.800 5,675.20 120 0734 LITTER REMOVAL - TRACT (12) CYC 13.000 1.000 176.930 176.93 130 0734 LITTER REMOVAL - TRACT (14) CYC 8.000 1.000 1,294.580 1,294.58 135 0734 LITTER REMOVAL - TRACT (15) CYC 12.000 1.000 208.400 208.40 140 0734 LITTER REMOVAL - TRACT (16) CYC 12.000 1.000 213.400 213.40 150 0734 LITTER REMOVAL - TRACT (18) CYC 12.000 1.000 638.540 638.54 155 0734 LITTER REMOVAL - TRACT (19) CYC 26.000 3.000 387.620 1,162.86 160 0734 LITTER REMOVAL - TRACT (20) CYC 13.000 1.000 2,208.580 2,208.58 165 0734 LITTER REMOVAL - TRACT (21) CYC 12.000 1.000 191.640 191.64 170 0734 LITTER REMOVAL - TRACT (22) CYC 12.000 1.000 1,114.160 1,114.16 175 0734 LITTER REMOVAL - TRACT (23) CYC 26.000 2.000 1,022.410 2,044.82 180 0734 LITTER REMOVAL - TRACT (24) CYC 26.000 3.000 968.690 2,906.07 185 0734 LITTER REMOVAL - TRACT (25) CYC 26.000 3.000 1,215.140 3,645.42 190 0734 LITTER REMOVAL - TRACT (26) CYC 26.000 3.000 1,519.620 4,558.86 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 39,951.10 0 TOTAL AMOUNT WORK DONE TO DATE - $ 223,724.24