1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10124025 MGR.NO. 060 PAGE 001 CONT 6245 SEC 76 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624576001 HWY FM0517 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 364,320.00 REPORT DATE 05/03/2013 07.45.40 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN FEB 05, 2013 TIME COMPUTED FROM DEC 15, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 107 107 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 137 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 137 137 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10124025 MGR.NO. 060 PAGE 001 CONT 6245 SEC 76 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624576001 HWY FM0517 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 364,320.00 REPORT DATE 05/03/2013 07.45.41 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 DIST. 12 COUNTY GALVESTON CONTROL 6245-76-001 PROJECT RMC - 624576001 HIGHWAY FM0517 0LIMITS- VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HWYS IN GALVESTON COUNTY 0TYPE OF WORK- DITCH CLEANING & RESHAPING 0 0005 PREPARED BY JAMIE MEDINA 0 0055 DITCH CLEANING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0760 DITCH CLEANING AND RESHAPING (FOOT) LF 316,800.000 245,225.000 1.150 282,008.75 0 SUBTOTAL BID ITEMS $ 282,008.75 0 TOTAL AMOUNT WORK DONE DITCH CLEANING $ 282,008.75 0 TOTAL AMOUNT WORK DONE CONTROL 6245-76-001 $ 282,008.75 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10124025 MGR.NO. 060 PAGE 001 CONT 6245 SEC 76 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624576001 HWY FM0517 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 364,320.00 REPORT DATE 05/03/2013 07.45.41 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY 0 VARIOUS HWYS IN GALVESTON COUNTY DATE WORK BEGAN FEB 5 , 2013 WORKING DAYS USED 137 PERCENT COMPLETE 77.40 PERCENT TIME USED 37.50 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6245-76-001 RMC - 624576001 12 FM0517 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0760 DITCH CLEANING AND RESHAPING (FOOT) LF 316,800.000 245,225.000 1.150 282,008.75 0 SUBTOTAL BID ITEMS $ 282,008.75 0 CONTRACT TOTAL ALL ITEMS $ 282,008.75 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10124025 MGR.NO. 060 PAGE 001 CONT 6245 SEC 76 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624576001 HWY FM0517 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 364,320.00 REPORT DATE 05/03/2013 07.45.41 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 RMC - 624576001 6245-76-001 282,008.75 .00 282,008.75 .00 .00 282,008.75 169,297.25 112,711.50 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 282,008.75 .00 282,008.75 .00 .00 282,008.75 169,297.25 112,711.50 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10124025 MGR.NO. 060 PAGE 001 CONT 6245 SEC 76 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624576001 HWY FM0517 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 364,320.00 REPORT DATE 05/03/2013 07.45.41 CONTRACTOR TEXAS DRAINAGE INC. 12914 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 005 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6245-76-001 RMC - 624576001 12 FM0517 GALVESTON -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HWYS IN GALVESTON COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0760 DITCH CLEANING AND RESHAPING LF 316,800.000 98,010.000 1.150 112,711.50 (FOOT) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 112,711.50 0 TOTAL AMOUNT WORK DONE TO DATE - $ 282,008.75