1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7121201 MGR.NO. 060 PAGE 001 CONT 6244 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624401001 HWY FM0518 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 213,100.00 REPORT DATE 02/04/2014 17.21.44 CONTRACTOR TEXAS HIGHWAY MAINTENANCE, LLC 14117 EST PERIOD OCT 15,2012 TO SEP 04,2013 EST NO 013 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN DEC 03, 2012 TIME COMPUTED FROM OCT 15, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 321 321 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 13 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 09/04/13 3 1 DAYS CHARGED TO DATE = 325 4 1 WORK COMPLETED AND ACCEPTED ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 325 325 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7121201 MGR.NO. 060 PAGE 001 CONT 6244 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624401001 HWY FM0518 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 213,100.00 REPORT DATE 02/04/2014 17.21.44 CONTRACTOR TEXAS HIGHWAY MAINTENANCE, LLC 14117 EST PERIOD OCT 15,2012 TO SEP 04,2013 EST NO 013 & FINAL DIST. 12 COUNTY GALVESTON CONTROL 6244-01-001 PROJECT RMC - 624401001 HIGHWAY FM0518 0LIMITS- VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HWYS IN GALVESTON COUNTY 0TYPE OF WORK- FULL DEPTH CONCRETE REPAIR 0 0005 PREPARED BY JAMIE MEDINA 0 0055 FULL DEPTH CONCRETE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0361 FULL-DEPTH REPAIR CRCP (8") SY 100.000 83.701 124.000 10,378.92 0065 0361 FULL-DEPTH REPAIR CRCP (10") SY 100.000 92.056 125.000 11,507.00 0070 0361 FULL-DEPTH REPAIR CRCP (11") SY 100.000 74.987 130.000 9,748.31 0075 0529 CONC CURB (TY II) LF 100.000 0.000 2.000 .00 0080 7622 FIBER REINFORCED POLYMER PATCH MATERIAL LB 100,000.000 124,017.000 1.750 217,029.75 0085 9000*SAMI SCREED LB 12,800.000 12,758.000 1.850 23,602.30 0090 9000*UNIFORMED POLICE OFFICERS LS 5,000.000 0.000 1.000 .00 0095 9000*SKIDABRADER SURFACE TEXTURING SY 3,000.000 3,000.000 4.170 12,510.00 0 SUBTOTAL BID ITEMS $ 284,776.28 0 TOTAL AMOUNT WORK DONE FULL DEPTH CONCRETE REPAIR $ 284,776.28 0 0130 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0131 POLICE OFFICERS FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6244-01-001 $ 284,776.28 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7121201 MGR.NO. 060 PAGE 001 CONT 6244 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624401001 HWY FM0518 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 213,100.00 REPORT DATE 02/04/2014 17.21.44 CONTRACTOR TEXAS HIGHWAY MAINTENANCE, LLC 14117 EST PERIOD OCT 15,2012 TO SEP 04,2013 EST NO 013 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY 0 VARIOUS HWYS IN GALVESTON COUNTY DATE WORK BEGAN DEC 3 , 2012 WORKING DAYS USED 325 PERCENT COMPLETE 100.00 PERCENT TIME USED 89.00 DATE COMPLETED SEP 4 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6244-01-001 RMC - 624401001 12 FM0518 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0361 FULL-DEPTH REPAIR CRCP (8") SY 100.000 83.701 124.000 10,378.92 0361 FULL-DEPTH REPAIR CRCP (10") SY 100.000 92.056 125.000 11,507.00 0361 FULL-DEPTH REPAIR CRCP (11") SY 100.000 74.987 130.000 9,748.31 7622 FIBER REINFORCED POLYMER PATCH MATERIAL LB 100,000.000 124,017.000 1.750 217,029.75 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* SAMI SCREED LB 12,800.000 12,758.000 1.850 23,602.30 9000* SKIDABRADER SURFACE TEXTURING SY 3,000.000 3,000.000 4.170 12,510.00 0 SUBTOTAL BID ITEMS $ 284,776.28 0 CONTRACT TOTAL ALL ITEMS $ 284,776.28 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7121201 MGR.NO. 060 PAGE 001 CONT 6244 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624401001 HWY FM0518 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 213,100.00 REPORT DATE 02/04/2014 17.21.44 CONTRACTOR TEXAS HIGHWAY MAINTENANCE, LLC 14117 EST PERIOD OCT 15,2012 TO SEP 04,2013 EST NO 013 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 RMC - 624401001 6244-01-001 284,776.28 .00 284,776.28 .00 .00 284,776.28 284,776.28 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 284,776.28 .00 284,776.28 .00 .00 284,776.28 284,776.28 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7121201 MGR.NO. 060 PAGE 001 CONT 6244 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 624401001 HWY FM0518 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 213,100.00 REPORT DATE 02/04/2014 17.21.44 CONTRACTOR TEXAS HIGHWAY MAINTENANCE, LLC 14117 EST PERIOD OCT 15,2012 TO SEP 04,2013 EST NO 013 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6244-01-001 RMC - 624401001 12 FM0518 GALVESTON -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HWYS IN GALVESTON COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 284,776.28