1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9101209 MGR.NO. 061 PAGE 001 CONT 6211 SEC 82 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 621182001 HWY SH0099 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 267,975.00 REPORT DATE 08/07/2014 11.37.03 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 25,2010 TO JUL 18,2011 EST NO 011 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 25, 2010 TIME COMPUTED FROM OCT 25, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 249 249 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 11 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 07/18/11 3 1 DAYS CHARGED TO DATE = 263 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 WORK COMPLETED AWAITING ACCEPTANCE 16 1 WORK COMPLETED AWAITING ACCEPTANCE ---------------------------- 17 1 WORK COMPLETED AWAITING ACCEPTANCE AREA/PROJECT ENGINEER 18 1 FINAL ACCEPTANCE AND APPROVAL - - - - 0 ----- ----- ----- 267 263 4 0 SATURDAY 0 SUNDAY 0 HOLIDAY 3 WORK COMPLETED AWAITING ACCEPTANCE 1 FINAL ACCEPTANCE AND APPROVAL 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9101209 MGR.NO. 061 PAGE 001 CONT 6211 SEC 82 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 621182001 HWY SH0099 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 267,975.00 REPORT DATE 08/07/2014 11.37.03 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 25,2010 TO JUL 18,2011 EST NO 011 & FINAL INC. 00644 DIST. 12 COUNTY FORT BEND CONTROL 6211-82-001 PROJECT RMC - 621182001 HIGHWAY SH0099 0LIMITS- VARIOUS HWYS IN FORT BEND COUNTY VARIOUS HWYS IN FORT BEND COUNTY 0TYPE OF WORK- ASPHALT PAVEMENT REPAIR 0 0050 ASPHALT PAVEMENT REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY: MORRIS M. TOWNS 0 0075 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 7,500.000 8,456.500 35.730 302,150.75 0115 0351*FLEXIBLE PAVEMENT STRUCTURE REPAIR(2") SY 880.000 880.000 24.480 21,542.40 0 SUBTOTAL BID ITEMS $ 323,693.15 0 TOTAL AMOUNT WORK DONE ASPHALT PAVEMENT REPAIR $ 323,693.15 0 0125 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0126 POLICE OFFICERS 0 0136 0533*SHOULDER TEXTURING (MILLED)(ASPHALT) LF 400.000 400.000 20.610 8,244.00 0140 9000*UNIFORMED POLICE OFFICERS EA 8,000.000 0.000 1.000 .00 0 SUBTOTAL BID ITEMS $ 8,244.00 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ 8,244.00 0 TOTAL AMOUNT WORK DONE CONTROL 6211-82-001 $ 331,937.15 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9101209 MGR.NO. 061 PAGE 001 CONT 6211 SEC 82 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 621182001 HWY SH0099 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 267,975.00 REPORT DATE 08/07/2014 11.37.03 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 25,2010 TO JUL 18,2011 EST NO 011 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN FORT BEND COUNTY 0 VARIOUS HWYS IN FORT BEND COUNTY DATE WORK BEGAN OCT 25, 2010 WORKING DAYS USED 263 PERCENT COMPLETE 100.00 PERCENT TIME USED 72.00 DATE COMPLETED JUL 18 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6211-82-001 RMC - 621182001 12 SH0099 FORT BEND - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 7,500.000 8,456.500 35.730 302,150.75 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00351* FLEXIBLE PAVEMENT STRUCTURE REPAIR(2") SY 880.000 880.000 24.480 21,542.40 0533* SHOULDER TEXTURING (MILLED)(ASPHALT) LF 400.000 400.000 20.610 8,244.00 0 SUBTOTAL BID ITEMS $ 331,937.15 0 CONTRACT TOTAL ALL ITEMS $ 331,937.15 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9101209 MGR.NO. 061 PAGE 001 CONT 6211 SEC 82 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 621182001 HWY SH0099 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 267,975.00 REPORT DATE 08/07/2014 11.37.03 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 25,2010 TO JUL 18,2011 EST NO 011 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 80 RMC - 621182001 6211-82-001 331,937.15 .00 331,937.15 .00 .00 331,937.15 331,937.15 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 331,937.15 .00 331,937.15 .00 .00 331,937.15 331,937.15 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9101209 MGR.NO. 061 PAGE 001 CONT 6211 SEC 82 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 621182001 HWY SH0099 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 267,975.00 REPORT DATE 08/07/2014 11.37.03 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 25,2010 TO JUL 18,2011 EST NO 011 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6211-82-001 RMC - 621182001 12 SH0099 FORT BEND -LIMITS - VARIOUS HWYS IN FORT BEND COUNTY VARIOUS HWYS IN FORT BEND COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 331,937.15