1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6101207 MGR.NO. 060 PAGE 001 CONT 6210 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 621001001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 286,825.00 REPORT DATE 02/27/2014 16.44.07 CONTRACTOR MAIN LANE INDUSTRIES, LTD. 11168 EST PERIOD SEP 01,2010 TO JUN 28,2011 EST NO 011 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 01, 2011 TIME COMPUTED FROM SEP 01, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 273 273 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 11 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 06/28/11 3 1 DAYS CHARGED TO DATE = 301 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 WORK COMPLETED AND ACCEPTED - ----- ----- ----- 301 301 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6101207 MGR.NO. 060 PAGE 001 CONT 6210 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 621001001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 286,825.00 REPORT DATE 02/27/2014 16.44.08 CONTRACTOR MAIN LANE INDUSTRIES, LTD. 11168 EST PERIOD SEP 01,2010 TO JUN 28,2011 EST NO 011 & FINAL DIST. 12 COUNTY GALVESTON CONTROL 6210-01-001 PROJECT RMC - 621001001 HIGHWAY IH0045 0LIMITS- VARIOUS HWYS IN GALVESTON VARIOUS HWYS IN GALVESTON 0TYPE OF WORK- ASPHALT PAVEMENT REPAIR 0 0005 PREPARED BY JAMIE MEDINA 0 0055 ASPHALT PAVEMENT REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 4,900.000 6,074.199 39.250 238,412.31 0065 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 2,000.000 1,999.111 47.250 94,457.99 0 SUBTOTAL BID ITEMS $ 332,870.30 0 TOTAL AMOUNT WORK DONE ASPHALT PAVEMENT REPAIR $ 332,870.30 0 0115 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0116 POLICE OFFICERS FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6210-01-001 $ 332,870.30 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6101207 MGR.NO. 060 PAGE 001 CONT 6210 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 621001001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 286,825.00 REPORT DATE 02/27/2014 16.44.08 CONTRACTOR MAIN LANE INDUSTRIES, LTD. 11168 EST PERIOD SEP 01,2010 TO JUN 28,2011 EST NO 011 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN GALVESTON 0 VARIOUS HWYS IN GALVESTON DATE WORK BEGAN JUN 1 , 2011 WORKING DAYS USED 301 PERCENT COMPLETE 100.00 PERCENT TIME USED 82.40 DATE COMPLETED JUN 28 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6210-01-001 RMC - 621001001 12 IH0045 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 4,900.000 6,074.199 39.250 238,412.31 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 2,000.000 1,999.111 47.250 94,457.99 0 SUBTOTAL BID ITEMS $ 332,870.30 0 CONTRACT TOTAL ALL ITEMS $ 332,870.30 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6101207 MGR.NO. 060 PAGE 001 CONT 6210 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 621001001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 286,825.00 REPORT DATE 02/27/2014 16.44.08 CONTRACTOR MAIN LANE INDUSTRIES, LTD. 11168 EST PERIOD SEP 01,2010 TO JUN 28,2011 EST NO 011 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 RMC - 621001001 6210-01-001 332,870.30 .00 332,870.30 .00 .00 332,870.30 332,870.30 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 332,870.30 .00 332,870.30 .00 .00 332,870.30 332,870.30 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6101207 MGR.NO. 060 PAGE 001 CONT 6210 SEC 01 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 621001001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 286,825.00 REPORT DATE 02/27/2014 16.44.08 CONTRACTOR MAIN LANE INDUSTRIES, LTD. 11168 EST PERIOD SEP 01,2010 TO JUN 28,2011 EST NO 011 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6210-01-001 RMC - 621001001 12 IH0045 GALVESTON -LIMITS - VARIOUS HWYS IN GALVESTON VARIOUS HWYS IN GALVESTON - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 332,870.30