1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10094012 MGR.NO. 770 PAGE 001 CONT 6200 SEC 97 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 620097001 HWY SH0087 7600 WASHINGTON AVE. HOUS CNTY GALVESTON DIST 12 CONTRACT PRICE $ 3,990,000.00 REPORT DATE 08/14/2014 09.46.38 CONTRACTOR ORION CONSTRUCTION, L.P. 11629 EST PERIOD JAN 26,2010 TO JUN 30,2010 EST NO 007 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JAN 26, 2010 TIME COMPUTED FROM FEB 03, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 126 69 57 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 10 1 1 AWAITING FINAL INSPECTION TOTAL DAYS ALLOWED = 30 2 1 AWAITING FINAL INSPECTION DATE WORK COMPLETED 06/30/10 3 1 AWAITING FINAL INSPECTION DAYS CHARGED TO DATE = 69 4 1 AWAITING FINAL INSPECTION ASSESSED LIQ DAMAGES = 39 5 1 AWAITING FINAL INSPECTION LIQ DAMAGE RATE $ 800 6 1 AWAITING FINAL INSPECTION 7 1 AWAITING FINAL INSPECTION LIQUIDATED DAMAGES 8 1 AWAITING FINAL INSPECTION 39 DAYS AT $ 800 PER DAY 9 1 AWAITING FINAL INSPECTION TOTAL = $ 31,200.00 10 1 AWAITING FINAL INSPECTION 11 1 AWAITING FINAL INSPECTION CERTIFIED AS CORRECT AND 12 1 AWAITING FINAL INSPECTION ONE COPY HAS BEEN GIVEN 13 1 AWAITING FINAL INSPECTION TO THE CONTRACTOR 14 1 AWAITING FINAL INSPECTION 15 1 AWAITING FINAL INSPECTION 16 1 AWAITING FINAL INSPECTION ---------------------------- 17 1 AWAITING FINAL INSPECTION AREA/PROJECT ENGINEER 18 1 AWAITING FINAL INSPECTION 19 1 AWAITING FINAL INSPECTION 20 1 AWAITING FINAL INSPECTION 21 1 AWAITING FINAL INSPECTION 22 1 AWAITING FINAL INSPECTION 23 1 AWAITING FINAL INSPECTION 24 1 AWAITING FINAL INSPECTION 25 1 AWAITING FINAL INSPECTION 26 1 AWAITING FINAL INSPECTION 27 1 AWAITING FINAL INSPECTION 28 1 AWAITING FINAL INSPECTION 29 1 AWAITING FINAL INSPECTION 30 1 WORK ACCEPTED 0 ----- ----- ----- 156 69 87 0 SATURDAY 0 SUNDAY 0 HOLIDAY 29 AWAITING FINAL INSPECTION 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10094012 MGR.NO. 770 PAGE 001 CONT 6200 SEC 97 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 620097001 HWY SH0087 7600 WASHINGTON AVE. HOUS CNTY GALVESTON DIST 12 CONTRACT PRICE $ 3,990,000.00 REPORT DATE 08/14/2014 09.46.39 CONTRACTOR ORION CONSTRUCTION, L.P. 11629 EST PERIOD JAN 26,2010 TO JUN 30,2010 EST NO 007 & FINAL DIST. 12 COUNTY GALVESTON CONTROL 6200-97-001 PROJECT RMC - 620097001 HIGHWAY SH0087 0LIMITS- BOLIVAR FERRY LANDING . 0TYPE OF WORK- DREDGING 0 0005 PREPARED BY CHRISTY FREEZE 0 0055 DREDGING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7103 MOBILIZATION FOR DREDGING EA 1.000 1.000 315,000.000 315,000.00 0065 7410 DREDGING CY 350,000.000 353,168.000 10.500 3,708,264.00 0 SUBTOTAL BID ITEMS $ 4,023,264.00 0 TOTAL AMOUNT WORK DONE DREDGING $ 4,023,264.00 0 TOTAL AMOUNT WORK DONE CONTROL 6200-97-001 $ 4,023,264.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10094012 MGR.NO. 770 PAGE 001 CONT 6200 SEC 97 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 620097001 HWY SH0087 7600 WASHINGTON AVE. HOUS CNTY GALVESTON DIST 12 CONTRACT PRICE $ 3,990,000.00 REPORT DATE 08/14/2014 09.46.39 CONTRACTOR ORION CONSTRUCTION, L.P. 11629 EST PERIOD JAN 26,2010 TO JUN 30,2010 EST NO 007 & FINAL 0*********************************************************************************************************************************** -LIMITS - BOLIVAR FERRY LANDING 0 . DATE WORK BEGAN JAN 26, 2010 WORKING DAYS USED 69 PERCENT COMPLETE 100.00 PERCENT TIME USED 230.00 DATE COMPLETED JUN 30 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6200-97-001 RMC - 620097001 12 SH0087 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7103 MOBILIZATION FOR DREDGING EA 1.000 1.000 315,000.000 315,000.00 7410 DREDGING CY 350,000.000 353,168.000 10.500 3,708,264.00 0 SUBTOTAL BID ITEMS $ 4,023,264.00 0 CONTRACT TOTAL ALL ITEMS $ 4,023,264.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10094012 MGR.NO. 770 PAGE 001 CONT 6200 SEC 97 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 620097001 HWY SH0087 7600 WASHINGTON AVE. HOUS CNTY GALVESTON DIST 12 CONTRACT PRICE $ 3,990,000.00 REPORT DATE 08/14/2014 09.46.39 CONTRACTOR ORION CONSTRUCTION, L.P. 11629 EST PERIOD JAN 26,2010 TO JUN 30,2010 EST NO 007 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 RMC - 620097001 6200-97-001 4,023,264.00 .00 4,023,264.00 .00 31,200.00 3,992,064.00 3,992,064.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 4,023,264.00 .00 4,023,264.00 .00 31,200.00 3,992,064.00 3,992,064.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10094012 MGR.NO. 770 PAGE 001 CONT 6200 SEC 97 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 620097001 HWY SH0087 7600 WASHINGTON AVE. HOUS CNTY GALVESTON DIST 12 CONTRACT PRICE $ 3,990,000.00 REPORT DATE 08/14/2014 09.46.39 CONTRACTOR ORION CONSTRUCTION, L.P. 11629 EST PERIOD JAN 26,2010 TO JUN 30,2010 EST NO 007 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6200-97-001 RMC - 620097001 12 SH0087 GALVESTON -LIMITS - BOLIVAR FERRY LANDING . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 4,023,264.00