1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7091203 MGR.NO. 061 PAGE 001 CONT 6193 SEC 86 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 619386001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 224,144.23 REPORT DATE 10/31/2013 15.46.13 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD SEP 09,2009 TO SEP 09,2010 EST NO 014 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 09, 2009 TIME COMPUTED FROM SEP 09, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 357 357 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 10 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 09/09/10 3 1 DAYS CHARGED TO DATE = 364 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 WORK COMPLETED 0 DAYS AT $ 0 PER DAY 9 1 WORK ACCEPTED TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 366 364 2 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7091203 MGR.NO. 061 PAGE 001 CONT 6193 SEC 86 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 619386001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 224,144.23 REPORT DATE 10/31/2013 15.46.14 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD SEP 09,2009 TO SEP 09,2010 EST NO 014 & FINAL DIST. 12 COUNTY FORT BEND CONTROL 6193-86-001 PROJECT RMC - 619386001 HIGHWAY US0059 0LIMITS- VARIOUS HWYS IN FORT BEND COUNTY VARIOUS HWYS IN FORT BEND COUNTY 0TYPE OF WORK- REFLECTIVE PAVEMENT MARKINGS (GRAPHICS) 0 0050 REFL PAVEMNT MRKINGS (GRAPHICS) NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY MORRIS M. TOWNS 0 0075 0662 WK ZN PAV MRK NON-REMOV (W) 4" (BRK) LF 6,000.000 80.000 .400 32.00 0075 0662 ADJ EST QUANTITY TO DATE 80.000 0080 0662 WK ZN PAV MRK NON-REMOV (W) 4" (DOT) LF 600.000 653.000 .710 463.63 0085 0662 WK ZN PAV MRK NON-REMOV (W) 4" (SLD) LF 24,500.000 5,336.000 .440 2,347.84 0085 0662 ADJ EST QUANTITY TO DATE 5,336.000 0090 0662 WK ZN PAV MRK NON-REMOV (W) 6" (BRK) LF 200.000 80.000 .520 41.60 0095 0662 WK ZN PAV MRK NON-REMOV (W) 6" (SLD) LF 500.000 275.000 .470 129.25 0100 0662 WK ZN PAV MRK NON-REMOV (W) 8" (SLD) LF 9,500.000 10,696.000 .810 8,663.76 0105 0662 WK ZN PAV MRK NON-REMOV (W) 12" (SLD) LF 5,000.000 4,286.000 2.280 9,772.08 0110 0662 WK ZN PAV MRK NON-REMOV (W) 24" (SLD) LF 4,500.000 4,122.000 3.490 14,385.78 0115 0662 WK ZN PAV MRK NON-REMOV (W) (ARROW) EA 125.000 113.000 110.000 12,430.00 0120 0662 WK ZN PAV MRK NON-REMOV (W) (DBL ARROW) EA 19.000 21.000 130.000 2,730.00 0125 0662 WK ZN PAV MRK NON-REMOV (W) (RR XING) EA 19.000 12.000 169.020 2,028.24 0130 0662 WK ZN PAV MRK NON-REMOV(W)(UTURN ARROW) EA 22.000 20.000 92.990 1,859.80 0135 0662 WK ZN PAV MRK NON-REMOV (W) (WORD) EA 125.000 107.000 87.080 9,317.56 1 0140 0662 WK ZN PAV MRK NON-REMOV (W)36"(YLD TRI) EA 50.000 62.000 46.210 2,865.02 0145 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (BRK) LF 1,000.000 20.000 .400 8.00 0150 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (SLD) LF 22,000.000 6,543.000 .430 2,813.49 0150 0662 ADJ EST QUANTITY TO DATE 6,543.000 0155 0662 WK ZN PAV MRK NON-REMOV (Y) 6" (SLD) LF 500.000 1,570.000 .480 753.60 0160 0662 WK ZN PAV MRK NON-REMOV (Y) 24" (SLD) LF 1,300.000 1,300.000 3.570 4,641.00 0165 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 6,000.000 80.000 .480 38.40 0170 0666 REFL PAV MRK TY I (W) 4" (DOT)(100MIL) LF 600.000 653.000 .750 489.75 0175 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 24,500.000 50,591.000 .500 25,295.50 0175 0666 ADJ EST QUANTITY TO DATE 54,657.340 0180 0666 REFL PAV MRK TY I (W) 6" (BRK)(100MIL) LF 200.000 80.000 .650 52.00 0185 0666 REFL PAV MRK TY I (W) 6" (SLD)(100MIL) LF 500.000 275.000 .560 154.00 0190 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 9,500.000 11,365.000 .930 10,569.45 0195 0666 REFL PAV MRK TY I (W) 12"(SLD)(100MIL) LF 5,000.000 5,000.000 2.250 11,250.00 0200 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 4,500.000 4,500.000 4.240 19,080.00 0205 0666 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 125.000 125.000 80.000 10,000.00 0210 0666 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) EA 19.000 23.000 77.060 1,772.38 0215 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 19.000 13.000 154.040 2,002.52 0220 0666 REFL PAV MRK TY I(W)(UTURN ARW)(100MIL) EA 22.000 20.000 112.410 2,248.20 0225 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 125.000 125.000 88.180 11,022.50 0230 0666 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL) EA 50.000 62.000 52.630 3,263.06 0235 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 1,000.000 3,760.000 .490 1,842.40 0235 0666 ADJ EST QUANTITY TO DATE 5,832.650 0240 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 22,000.000 24,077.000 .590 14,205.43 0245 0666 REFL PAV MRK TY I (Y) 6" (SLD)(100MIL) LF 500.000 1,570.000 .570 894.90 0250 0666 REFL PAV MRK TY I (Y) 24"(SLD)(100MIL) LF 1,300.000 1,300.000 4.310 5,603.00 0255 0666 REF PAV MRK TY I (BLACK)6"(BRK)(100MIL) LF 200.000 0.000 .490 .00 1 0260 0672 REFL PAV MRKR TY II-A-A EA 1,000.000 646.000 3.000 1,938.00 0265 0672 REFL PAV MRKR TY II-C-R EA 1,500.000 1,062.000 3.000 3,186.00 0270 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 54,100.000 11,320.000 .130 1,471.60 0275 0677 ELIM EXT PAV MRK & MRKS ( 6") LF 1,200.000 1,785.000 .140 249.90 0280 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 9,500.000 11,818.000 .310 3,663.58 0285 0677 ELIM EXT PAV MRK & MRKS (12") LF 5,000.000 4,741.000 .030 142.23 0290 0677 ELIM EXT PAV MRK & MRKS (24") LF 5,800.000 5,287.000 .050 264.35 0295 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 125.000 119.000 2.800 333.20 0300 0677 ELIM EXT PAV MRK & MRKS (DBL ARROW) EA 19.000 13.000 4.000 52.00 0305 0677 ELIM EXT PAV MRK & MRKS (RR XING) EA 19.000 11.000 7.000 77.00 0310 0677 ELIM EXT PAV MRK & MRKS (UTURN ARR) EA 22.000 20.000 5.400 108.00 0315 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 125.000 111.000 2.800 310.80 0320 0678 PAV SURF PREP FOR MRK ( 4") LF 54,100.000 75,337.000 .010 753.37 0325 0678 PAV SURF PREP FOR MRK ( 6") LF 1,200.000 1,925.000 .010 19.25 0330 0678 PAV SURF PREP FOR MRK ( 8") LF 9,500.000 11,365.000 .010 113.65 0335 0678 PAV SURF PREP FOR MRK (12") LF 5,000.000 5,000.000 .030 150.00 0340 0678 PAV SURF PREP FOR MRK (24") LF 5,800.000 5,401.000 .030 162.03 0345 0678 PAV SURF PREP FOR MRK (ARROW) EA 125.000 125.000 1.400 175.00 0350 0678 PAV SURF PREP FOR MRK (DBL ARROW) EA 19.000 23.000 2.750 63.25 0355 0678 PAV SURF PREP FOR MRK (RR XING) EA 19.000 13.000 5.500 71.50 0360 0678 PAV SURF PREP FOR MRK (UTURN ARR) EA 22.000 20.000 2.800 56.00 0365 0678 PAV SURF PREP FOR MRK (WORD) EA 125.000 125.000 1.900 237.50 0370 0678 PAV SURF PREP FOR MRK (36") (YLD TRI) EA 50.000 62.000 2.800 173.60 0375 0668*PREFAB PAV MRK TY B (W) ( 4") (SLD) LF 431.000 431.000 3.480 1,499.88 0380 0668*PREFAB PAV MRK TY B (W) ( 8") (SLD) LF 862.000 862.000 6.960 5,999.52 0385 0668*PREFAB PAV MRK TY B (W) (SYMBOL) EA 1.000 1.000 522.140 522.14 0390 0668*PREFAB PAV MRK TY B (Y) ( 4") (SLD) LF 431.000 431.000 3.480 1,499.88 0395 0668*PREFAB PAV MRK TY B (W)(7")(BRK) CNTST LF 330.000 300.000 6.270 1,881.00 0400 0666*PAVEMENT SEALER 4" LF 862.000 862.000 .240 206.88 0405 0666*PAVEMENT SEALER 8" LF 330.000 330.000 .300 99.00 1 SUBTOTAL BID ITEMS $ 220,546.25 0 TOTAL AMOUNT WORK DONE REFL PAVEMNT MRKINGS (GRAPHICS) $ 220,546.25 0 0420 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0421 POLICE OFFICERS FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6193-86-001 $ 220,546.25 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7091203 MGR.NO. 061 PAGE 001 CONT 6193 SEC 86 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 619386001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 224,144.23 REPORT DATE 10/31/2013 15.46.15 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD SEP 09,2009 TO SEP 09,2010 EST NO 014 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN FORT BEND COUNTY 0 VARIOUS HWYS IN FORT BEND COUNTY DATE WORK BEGAN SEP 9 , 2009 WORKING DAYS USED 364 PERCENT COMPLETE 100.00 PERCENT TIME USED 99.70 DATE COMPLETED SEP 9 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6193-86-001 RMC - 619386001 12 US0059 FORT BEND - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0662 WK ZN PAV MRK NON-REMOV (W) 4" (BRK) LF 6,000.000 80.000 .400 32.00 0662 ADJ EST QUANTITY TO DATE 80.000 0662 WK ZN PAV MRK NON-REMOV (W) 4" (DOT) LF 600.000 653.000 .710 463.63 0662 WK ZN PAV MRK NON-REMOV (W) 4" (SLD) LF 24,500.000 5,336.000 .440 2,347.84 0662 ADJ EST QUANTITY TO DATE 5,336.000 0662 WK ZN PAV MRK NON-REMOV (W) 6" (BRK) LF 200.000 80.000 .520 41.60 0662 WK ZN PAV MRK NON-REMOV (W) 6" (SLD) LF 500.000 275.000 .470 129.25 0662 WK ZN PAV MRK NON-REMOV (W) 8" (SLD) LF 9,500.000 10,696.000 .810 8,663.76 0662 WK ZN PAV MRK NON-REMOV (W) 12" (SLD) LF 5,000.000 4,286.000 2.280 9,772.08 0662 WK ZN PAV MRK NON-REMOV (W) 24" (SLD) LF 4,500.000 4,122.000 3.490 14,385.78 0662 WK ZN PAV MRK NON-REMOV (W) (ARROW) EA 125.000 113.000 110.000 12,430.00 0662 WK ZN PAV MRK NON-REMOV (W) (DBL ARROW) EA 19.000 21.000 130.000 2,730.00 0662 WK ZN PAV MRK NON-REMOV (W) (RR XING) EA 19.000 12.000 169.020 2,028.24 0662 WK ZN PAV MRK 1 NON-REMOV(W)(UTURN ARROW) EA 22.000 20.000 92.990 1,859.80 0662 WK ZN PAV MRK NON-REMOV (W) (WORD) EA 125.000 107.000 87.080 9,317.56 0662 WK ZN PAV MRK NON-REMOV (W)36"(YLD TRI) EA 50.000 62.000 46.210 2,865.02 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (BRK) LF 1,000.000 20.000 .400 8.00 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (SLD) LF 22,000.000 6,543.000 .430 2,813.49 0662 ADJ EST QUANTITY TO DATE 6,543.000 0662 WK ZN PAV MRK NON-REMOV (Y) 6" (SLD) LF 500.000 1,570.000 .480 753.60 0662 WK ZN PAV MRK NON-REMOV (Y) 24" (SLD) LF 1,300.000 1,300.000 3.570 4,641.00 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 6,000.000 80.000 .480 38.40 0666 REFL PAV MRK TY I (W) 4" (DOT)(100MIL) LF 600.000 653.000 .750 489.75 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 24,500.000 50,591.000 .500 25,295.50 0666 ADJ EST QUANTITY TO DATE 54,657.340 0666 REFL PAV MRK TY I (W) 6" (BRK)(100MIL) LF 200.000 80.000 .650 52.00 0666 REFL PAV MRK TY I (W) 6" (SLD)(100MIL) LF 500.000 275.000 .560 154.00 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 9,500.000 11,365.000 .930 10,569.45 0666 REFL PAV MRK TY I (W) 12"(SLD)(100MIL) LF 5,000.000 5,000.000 2.250 11,250.00 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 4,500.000 4,500.000 4.240 19,080.00 0666 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 125.000 125.000 80.000 10,000.00 0666 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) EA 19.000 23.000 77.060 1,772.38 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 19.000 13.000 154.040 2,002.52 0666 REFL PAV MRK TY I(W)(UTURN ARW)(100MIL) EA 22.000 20.000 112.410 2,248.20 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 125.000 125.000 88.180 11,022.50 0666 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL) EA 50.000 62.000 52.630 3,263.06 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 1,000.000 3,760.000 .490 1,842.40 0666 ADJ EST QUANTITY TO DATE 5,832.650 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 22,000.000 24,077.000 .590 14,205.43 0666 REFL PAV MRK TY I (Y) 6" (SLD)(100MIL) LF 500.000 1,570.000 .570 894.90 0666 REFL PAV MRK TY I (Y) 1 24"(SLD)(100MIL) LF 1,300.000 1,300.000 4.310 5,603.00 0672 REFL PAV MRKR TY II-A-A EA 1,000.000 646.000 3.000 1,938.00 0672 REFL PAV MRKR TY II-C-R EA 1,500.000 1,062.000 3.000 3,186.00 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 54,100.000 11,320.000 .130 1,471.60 0677 ELIM EXT PAV MRK & MRKS ( 6") LF 1,200.000 1,785.000 .140 249.90 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 9,500.000 11,818.000 .310 3,663.58 0677 ELIM EXT PAV MRK & MRKS (12") LF 5,000.000 4,741.000 .030 142.23 0677 ELIM EXT PAV MRK & MRKS (24") LF 5,800.000 5,287.000 .050 264.35 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 125.000 119.000 2.800 333.20 0677 ELIM EXT PAV MRK & MRKS (DBL ARROW) EA 19.000 13.000 4.000 52.00 0677 ELIM EXT PAV MRK & MRKS (RR XING) EA 19.000 11.000 7.000 77.00 0677 ELIM EXT PAV MRK & MRKS (UTURN ARR) EA 22.000 20.000 5.400 108.00 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 125.000 111.000 2.800 310.80 0678 PAV SURF PREP FOR MRK ( 4") LF 54,100.000 75,337.000 .010 753.37 0678 PAV SURF PREP FOR MRK ( 6") LF 1,200.000 1,925.000 .010 19.25 0678 PAV SURF PREP FOR MRK ( 8") LF 9,500.000 11,365.000 .010 113.65 0678 PAV SURF PREP FOR MRK (12") LF 5,000.000 5,000.000 .030 150.00 0678 PAV SURF PREP FOR MRK (24") LF 5,800.000 5,401.000 .030 162.03 0678 PAV SURF PREP FOR MRK (ARROW) EA 125.000 125.000 1.400 175.00 0678 PAV SURF PREP FOR MRK (DBL ARROW) EA 19.000 23.000 2.750 63.25 0678 PAV SURF PREP FOR MRK (RR XING) EA 19.000 13.000 5.500 71.50 0678 PAV SURF PREP FOR MRK (UTURN ARR) EA 22.000 20.000 2.800 56.00 0678 PAV SURF PREP FOR MRK (WORD) EA 125.000 125.000 1.900 237.50 0678 PAV SURF PREP FOR MRK (36") (YLD TRI) EA 50.000 62.000 2.800 173.60 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00666* PAVEMENT SEALER 4" LF 862.000 862.000 .240 206.88 0666* PAVEMENT SEALER 8" LF 330.000 330.000 .300 99.00 0668* PREFAB PAV MRK TY B (W) ( 4") (SLD) LF 431.000 431.000 3.480 1,499.88 0668* PREFAB PAV MRK TY B (W) ( 8") (SLD) LF 862.000 862.000 6.960 5,999.52 0668* PREFAB PAV MRK TY B (W) (SYMBOL) EA 1.000 1.000 522.140 522.14 0668* PREFAB PAV MRK TY B (Y) ( 1 4") (SLD) LF 431.000 431.000 3.480 1,499.88 0668* PREFAB PAV MRK TY B (W)(7")(BRK) CNTST LF 330.000 300.000 6.270 1,881.00 0 SUBTOTAL BID ITEMS $ 220,546.25 0 CONTRACT TOTAL ALL ITEMS $ 220,546.25 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7091203 MGR.NO. 061 PAGE 001 CONT 6193 SEC 86 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 619386001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 224,144.23 REPORT DATE 10/31/2013 15.46.15 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD SEP 09,2009 TO SEP 09,2010 EST NO 014 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 80 RMC - 619386001 6193-86-001 220,546.25 .00 220,546.25 .00 .00 220,546.25 220,546.25 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 220,546.25 .00 220,546.25 .00 .00 220,546.25 220,546.25 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7091203 MGR.NO. 061 PAGE 001 CONT 6193 SEC 86 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 619386001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 224,144.23 REPORT DATE 10/31/2013 15.46.16 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD SEP 09,2009 TO SEP 09,2010 EST NO 014 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6193-86-001 RMC - 619386001 12 US0059 FORT BEND -LIMITS - VARIOUS HWYS IN FORT BEND COUNTY VARIOUS HWYS IN FORT BEND COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 220,546.25