1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5094004 MGR.NO. 058 PAGE 001 CONT 6192 SEC 37 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 619237001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 257,760.00 REPORT DATE 11/19/2009 07.47.15 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 15, 2009 TIME COMPUTED FROM JUL 01, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 92 92 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 123 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 123 123 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5094004 MGR.NO. 058 PAGE 001 CONT 6192 SEC 37 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 619237001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 257,760.00 REPORT DATE 11/19/2009 07.47.16 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 INC. 00644 DIST. 12 COUNTY WALLER CONTROL 6192-37-001 PROJECT RMC - 619237001 HIGHWAY US0290 0LIMITS- VARIOUS ROADWAYS IN WALLER COUNTY VARIOUS ROADWAYS IN WALLER COUNTY 0TYPE OF WORK- ASPHALT PAVEMENT REPAIR 0 0005 ASPHALT PAVEMENT REPAIR 0 0055 PREPARED BY TROY WAWAROFSKY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0104 REMOVING CONC (CURB) LF 100.000 0.000 12.000 .00 0065 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 1,500.000 428.333 59.000 25,271.65 0070 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 600.000 259.333 66.000 17,115.98 0075 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 1,500.000 612.112 75.200 46,030.82 0080 0361 FULL-DEPTH REPAIR CRCP (13") SY 64.000 0.000 240.000 .00 0085 0529 CONC CURB (TY II) LF 100.000 0.000 3.000 .00 0 SUBTOTAL BID ITEMS $ 88,418.45 0 TOTAL AMOUNT WORK DONE PREPARED BY TROY WAWAROFSKY $ 88,418.45 0 0135 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0136 POLICE OFFICER FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6192-37-001 $ 88,418.45 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5094004 MGR.NO. 058 PAGE 001 CONT 6192 SEC 37 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 619237001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 257,760.00 REPORT DATE 11/19/2009 07.47.16 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN WALLER COUNTY 0 VARIOUS ROADWAYS IN WALLER COUNTY DATE WORK BEGAN JUL 15, 2009 WORKING DAYS USED 123 PERCENT COMPLETE 34.30 PERCENT TIME USED 33.60 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6192-37-001 RMC - 619237001 12 US0290 WALLER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 1,500.000 428.333 59.000 25,271.65 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 600.000 259.333 66.000 17,115.98 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 1,500.000 612.112 75.200 46,030.82 0 SUBTOTAL BID ITEMS $ 88,418.45 0 CONTRACT TOTAL ALL ITEMS $ 88,418.45 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5094004 MGR.NO. 058 PAGE 001 CONT 6192 SEC 37 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 619237001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 257,760.00 REPORT DATE 11/19/2009 07.47.16 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 237 RMC - 619237001 6192-37-001 88,418.45 .00 88,418.45 .00 .00 88,418.45 88,418.45 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 88,418.45 .00 88,418.45 .00 .00 88,418.45 88,418.45 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5094004 MGR.NO. 058 PAGE 001 CONT 6192 SEC 37 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 619237001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 257,760.00 REPORT DATE 11/19/2009 07.47.16 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 004 INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6192-37-001 RMC - 619237001 12 US0290 WALLER -LIMITS - VARIOUS ROADWAYS IN WALLER COUNTY VARIOUS ROADWAYS IN WALLER COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 88,418.45