1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3091201 MGR.NO. 061 PAGE 001 CONT 6182 SEC 10 JOB 001 RES ENGR HUNT, JAMES PROJ BPM - 618210001 HWY SH0036 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 129,660.00 REPORT DATE 08/25/2009 13.55.06 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 01,2009 TO JUL 30,2009 EST NO 004 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 24, 2009 TIME COMPUTED FROM APR 24, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 45 68 16 52 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 09 1 1 AWAITING FINAL INSPECTION TOTAL DAYS ALLOWED = 45 2 1 AWAITING FINAL INSPECTION DATE WORK COMPLETED 07/30/09 3 1 AWAITING FINAL INSPECTION DAYS CHARGED TO DATE = 16 4 1 SATURDAY ASSESSED LIQ DAMAGES = 0 5 1 SUNDAY LIQ DAMAGE RATE $ 400 6 1 AWAITING FINAL INSPECTION 7 1 AWAITING FINAL INSPECTION LIQUIDATED DAMAGES 8 1 AWAITING FINAL INSPECTION 0 DAYS AT $ 400 PER DAY 9 1 AWAITING FINAL INSPECTION TOTAL = $ .00 10 1 AWAITING FINAL INSPECTION 11 1 SATURDAY CERTIFIED AS CORRECT AND 12 1 SUNDAY ONE COPY HAS BEEN GIVEN 13 1 AWAITING FINAL INSPECTION TO THE CONTRACTOR 14 1 AWAITING FINAL INSPECTION 15 1 AWAITING FINAL INSPECTION 16 1 AWAITING FINAL INSPECTION ---------------------------- 17 1 AWAITING FINAL INSPECTION AREA/PROJECT ENGINEER 18 1 SATURDAY 19 1 SUNDAY 20 1 AWAITING FINAL INSPECTION 21 1 AWAITING FINAL INSPECTION 22 1 AWAITING FINAL INSPECTION 23 1 AWAITING FINAL INSPECTION 24 1 AWAITING FINAL INSPECTION 25 1 SATURDAY 26 1 SUNDAY 27 1 AWAITING FINAL INSPECTION 28 1 AWAITING FINAL INSPECTION 29 1 AWAITING FINAL INSPECTION 30 1 WORK COMPLETED AND ACCEPTED 0 ----- ----- ----- 98 16 82 4 SATURDAY 4 SUNDAY 0 HOLIDAY 21 AWAITING FINAL INSPECTION 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3091201 MGR.NO. 061 PAGE 001 CONT 6182 SEC 10 JOB 001 RES ENGR HUNT, JAMES PROJ BPM - 618210001 HWY SH0036 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 129,660.00 REPORT DATE 08/25/2009 13.55.06 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 01,2009 TO JUL 30,2009 EST NO 004 DIST. 12 COUNTY FORT BEND CONTROL 6182-10-001 PROJECT BPM - 618210001 HIGHWAY SH0036 0LIMITS- AT BIG CREEK AT BIG CREEK 0TYPE OF WORK- BRIDGE DECK, BEAM AND BENT CAP REPAIR 0 0050 BRIDGE DECK,BM AND BENT CAP REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY JILL M. CARMACK, P.E. 0 0075 0429 CONC STRUCT REPAIR SF 328.000 293.793 120.000 35,255.16 0080 0500 MOBILIZATION LS 1.000 1.000 12,800.000 12,800.00 0085 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 1,000.000 3,000.00 0090 0552 WIRE FENCE (TY A) LF 100.000 100.000 10.000 1,000.00 0095 0552 GATE (TY 1) EA 2.000 2.000 750.000 1,500.00 0100 0788 CONCRETE BEAM REPAIR EA 24.000 28.000 3,000.000 84,000.00 0 SUBTOTAL BID ITEMS $ 137,555.16 0 TOTAL AMOUNT WORK DONE BRIDGE DECK,BM AND BENT CAP REPAIR $ 137,555.16 0 0150 CONTRACTOR FORCE ACT OR AGR UNIT NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0151 PRICE 0152 TEMP EROSN, SEDMENT & WTR POLL CONT 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACT OR AGR UNIT $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6182-10-001 $ 137,555.16 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3091201 MGR.NO. 061 PAGE 001 CONT 6182 SEC 10 JOB 001 RES ENGR HUNT, JAMES PROJ BPM - 618210001 HWY SH0036 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 129,660.00 REPORT DATE 08/25/2009 13.55.06 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 01,2009 TO JUL 30,2009 EST NO 004 0*********************************************************************************************************************************** -LIMITS - AT BIG CREEK 0 AT BIG CREEK DATE WORK BEGAN APR 24, 2009 WORKING DAYS USED 16 PERCENT COMPLETE 100.00 PERCENT TIME USED 35.50 DATE COMPLETED JUL 30 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6182-10-001 BPM - 618210001 12 SH0036 FORT BEND - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0429 CONC STRUCT REPAIR SF 328.000 293.793 120.000 35,255.16 0500 MOBILIZATION LS 1.000 1.000 12,800.000 12,800.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 1,000.000 3,000.00 0552 WIRE FENCE (TY A) LF 100.000 100.000 10.000 1,000.00 0552 GATE (TY 1) EA 2.000 2.000 750.000 1,500.00 0788 CONCRETE BEAM REPAIR EA 24.000 28.000 3,000.000 84,000.00 0 SUBTOTAL BID ITEMS $ 137,555.16 0 CONTRACT TOTAL ALL ITEMS $ 137,555.16 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3091201 MGR.NO. 061 PAGE 001 CONT 6182 SEC 10 JOB 001 RES ENGR HUNT, JAMES PROJ BPM - 618210001 HWY SH0036 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 129,660.00 REPORT DATE 08/25/2009 13.55.06 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 01,2009 TO JUL 30,2009 EST NO 004 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 80 BPM - 618210001 6182-10-001 137,555.16 .00 137,555.16 .00 .00 137,555.16 137,555.16 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 137,555.16 .00 137,555.16 .00 .00 137,555.16 137,555.16 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3091201 MGR.NO. 061 PAGE 001 CONT 6182 SEC 10 JOB 001 RES ENGR HUNT, JAMES PROJ BPM - 618210001 HWY SH0036 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 129,660.00 REPORT DATE 08/25/2009 13.55.06 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 01,2009 TO JUL 30,2009 EST NO 004 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6182-10-001 BPM - 618210001 12 SH0036 FORT BEND -LIMITS - AT BIG CREEK AT BIG CREEK - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 137,555.16