1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2081206 MGR.NO. 054 PAGE 001 CONT 6174 SEC 15 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ RMC - 617415001 HWY IH0045 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 95,763.60 REPORT DATE 12/10/2013 16.54.20 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD MAR 29,2008 TO NOV 30,2008 EST NO 010 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 29, 2008 TIME COMPUTED FROM MAR 29, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 366 217 217 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 08 1 1 TOTAL DAYS ALLOWED = 366 2 1 DATE WORK COMPLETED 11/30/08 3 1 DAYS CHARGED TO DATE = 247 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 247 247 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2081206 MGR.NO. 054 PAGE 001 CONT 6174 SEC 15 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ RMC - 617415001 HWY IH0045 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 95,763.60 REPORT DATE 12/10/2013 16.54.20 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD MAR 29,2008 TO NOV 30,2008 EST NO 010 & FINAL INC. 00644 DIST. 12 COUNTY HARRIS CONTROL 6174-15-001 PROJECT RMC - 617415001 HIGHWAY IH0045 0LIMITS- VARIOUS HWYS IN SOUTH HARRIS COUNTY VARIOUS HWYS IN SOUTH HARRIS COUNTY 0TYPE OF WORK- FLEXIBLE PAVEMENT STRUCTURE REPAIR 0 0050 FLEXIBLE PAVE STRUCT REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY SEVERO BASQUEZ JR. 0 0075 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 840.000 808.040 70.100 56,643.60 0080 0700 POTHOLE REPAIR (SAW-CUT) SY 876.000 1,040.770 42.100 43,816.42 0085 9000*UNIFORMED POLICE OFFICER LS 7,000.000 2,117.280 1.000 2,117.28 0 SUBTOTAL BID ITEMS $ 102,577.30 0 TOTAL AMOUNT WORK DONE FLEXIBLE PAVE STRUCT REPAIR $ 102,577.30 0 0130 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0131 POLICE OFFICERS FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 0185 CONTRACTOR FORCE ACT OR AGR UNIT NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0186 PRICE 0187 TEMP EROSN, SEDMENT & WTR-POL CONT 1 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACT OR AGR UNIT $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6174-15-001 $ 102,577.30 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2081206 MGR.NO. 054 PAGE 001 CONT 6174 SEC 15 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ RMC - 617415001 HWY IH0045 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 95,763.60 REPORT DATE 12/10/2013 16.54.20 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD MAR 29,2008 TO NOV 30,2008 EST NO 010 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN SOUTH HARRIS COUNTY 0 VARIOUS HWYS IN SOUTH HARRIS COUNTY DATE WORK BEGAN MAR 29, 2008 WORKING DAYS USED 247 PERCENT COMPLETE 100.00 PERCENT TIME USED 67.40 DATE COMPLETED NOV 30 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6174-15-001 RMC - 617415001 12 IH0045 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") SY 840.000 808.040 70.100 56,643.60 0700 POTHOLE REPAIR (SAW-CUT) SY 876.000 1,040.770 42.100 43,816.42 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* UNIFORMED POLICE OFFICER LS 7,000.000 2,117.280 1.000 2,117.28 0 SUBTOTAL BID ITEMS $ 102,577.30 0 CONTRACT TOTAL ALL ITEMS $ 102,577.30 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2081206 MGR.NO. 054 PAGE 001 CONT 6174 SEC 15 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ RMC - 617415001 HWY IH0045 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 95,763.60 REPORT DATE 12/10/2013 16.54.20 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD MAR 29,2008 TO NOV 30,2008 EST NO 010 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 RMC - 617415001 6174-15-001 102,577.30 .00 102,577.30 .00 .00 102,577.30 102,577.30 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102,577.30 .00 102,577.30 .00 .00 102,577.30 102,577.30 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2081206 MGR.NO. 054 PAGE 001 CONT 6174 SEC 15 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ RMC - 617415001 HWY IH0045 702 FM 1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 95,763.60 REPORT DATE 12/10/2013 16.54.20 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD MAR 29,2008 TO NOV 30,2008 EST NO 010 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6174-15-001 RMC - 617415001 12 IH0045 HARRIS -LIMITS - VARIOUS HWYS IN SOUTH HARRIS COUNTY VARIOUS HWYS IN SOUTH HARRIS COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 102,577.30