1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10081208 MGR.NO. 060 PAGE 001 CONT 6170 SEC 96 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 617096001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 280,710.00 REPORT DATE 10/08/2013 16.02.40 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD DEC 15,2008 TO SEP 30,2009 EST NO 011 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN FEB 16, 2009 TIME COMPUTED FROM DEC 15, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 260 260 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 09/30/09 3 1 DAYS CHARGED TO DATE = 290 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 WORK COMPLETED AND ACCEPTED 0 ----- ----- ----- 290 290 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10081208 MGR.NO. 060 PAGE 001 CONT 6170 SEC 96 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 617096001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 280,710.00 REPORT DATE 10/08/2013 16.02.41 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD DEC 15,2008 TO SEP 30,2009 EST NO 011 & FINAL INC. 00644 DIST. 12 COUNTY GALVESTON CONTROL 6170-96-001 PROJECT RMC - 617096001 HIGHWAY IH0045 0LIMITS- VARIOUS HWYS IN GALVESTON VARIOUS HWYS IN GALVESTON 0TYPE OF WORK- ASPHALT PAVEMENT REPAIR 0 0005 PREPARED BY JAMIE MEDINA 0 0055 ASPHALT PAVEMENT REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 4,700.000 6,412.867 39.300 252,025.67 0060 0351 ADJ EST QUANTITY TO DATE 6,412.867 0065 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 2,000.000 1,998.056 48.000 95,906.69 0070 9000*SLURRY SEALING PARKING AREA LS 1.000 1.000 54,660.520 54,660.52 0 SUBTOTAL BID ITEMS $ 402,592.88 0 TOTAL AMOUNT WORK DONE ASPHALT PAVEMENT REPAIR $ 402,592.88 0 0115 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0116 POLICE OFFICERS FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6170-96-001 $ 402,592.88 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10081208 MGR.NO. 060 PAGE 001 CONT 6170 SEC 96 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 617096001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 280,710.00 REPORT DATE 10/08/2013 16.02.41 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD DEC 15,2008 TO SEP 30,2009 EST NO 011 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN GALVESTON 0 VARIOUS HWYS IN GALVESTON DATE WORK BEGAN FEB 16, 2009 WORKING DAYS USED 290 PERCENT COMPLETE 100.00 PERCENT TIME USED 79.40 DATE COMPLETED SEP 30 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6170-96-001 RMC - 617096001 12 IH0045 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 4,700.000 6,412.867 39.300 252,025.67 0351 ADJ EST QUANTITY TO DATE 6,412.867 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 2,000.000 1,998.056 48.000 95,906.69 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* SLURRY SEALING PARKING AREA LS 1.000 1.000 54,660.520 54,660.52 0 SUBTOTAL BID ITEMS $ 402,592.88 0 CONTRACT TOTAL ALL ITEMS $ 402,592.88 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10081208 MGR.NO. 060 PAGE 001 CONT 6170 SEC 96 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 617096001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 280,710.00 REPORT DATE 10/08/2013 16.02.41 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD DEC 15,2008 TO SEP 30,2009 EST NO 011 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 RMC - 617096001 6170-96-001 402,592.88 .00 402,592.88 .00 .00 402,592.88 402,592.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 402,592.88 .00 402,592.88 .00 .00 402,592.88 402,592.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10081208 MGR.NO. 060 PAGE 001 CONT 6170 SEC 96 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 617096001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 280,710.00 REPORT DATE 10/08/2013 16.02.41 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD DEC 15,2008 TO SEP 30,2009 EST NO 011 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6170-96-001 RMC - 617096001 12 IH0045 GALVESTON -LIMITS - VARIOUS HWYS IN GALVESTON VARIOUS HWYS IN GALVESTON - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 402,592.88