1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1084029 MGR.NO. 050 PAGE 001 CONT 6170 SEC 82 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 617082001 HWY SH0288 1033 E ORANGE ST ANGLETON CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 554,801.24 REPORT DATE 11/03/2009 15.47.42 CONTRACTOR PARK CONSTRUCTION 12674 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 018 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 01, 2008 TIME COMPUTED FROM MAY 01, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 260 518 89 429 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TIME SUSP - LETTER SUBMITTED TOTAL DAYS ALLOWED = 260 2 1 TIME SUSP - LETTER SUBMITTED DATE WORK COMPLETED 3 1 TIME SUSP - LETTER SUBMITTED DAYS CHARGED TO DATE = 93 4 1 TIME SUSP - LETTER SUBMITTED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSP - LETTER SUBMITTED LIQ DAMAGE RATE $ 500 6 1 TIME SUSP - LETTER SUBMITTED 7 1 TIME SUSP - LETTER SUBMITTED LIQUIDATED DAMAGES 8 1 TIME SUSP - LETTER SUBMITTED 0 DAYS AT $ 500 PER DAY 9 1 TIME SUSP - LETTER SUBMITTED TOTAL = $ .00 10 1 TIME SUSP - LETTER SUBMITTED 11 1 TIME SUSP - LETTER SUBMITTED CERTIFIED AS CORRECT AND 12 1 TIME SUSP - LETTER SUBMITTED ONE COPY HAS BEEN GIVEN 13 1 TIME SUSP - LETTER SUBMITTED TO THE CONTRACTOR 14 1 TIME SUSP - LETTER SUBMITTED 15 1 TIME SUSP - LETTER SUBMITTED 16 1 TIME SUSP - LETTER SUBMITTED ---------------------------- 17 1 TIME SUSP - LETTER SUBMITTED AREA/PROJECT ENGINEER 18 1 TIME SUSP - LETTER SUBMITTED 19 1 20 1 21 1 22 1 RAIN 23 1 TOO WET 24 1 SATURDAY 25 1 SUNDAY 26 1 RAIN 27 1 TOO WET 28 1 29 1 RAIN 30 1 RAIN 31 1 SATURDAY ----- ----- ----- 549 93 456 2 SATURDAY 1 SUNDAY 0 HOLIDAY 18 TIME SUSP - LETTER SUBMITTED 4 RAIN 2 TOO WET 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1084029 MGR.NO. 050 PAGE 001 CONT 6170 SEC 82 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 617082001 HWY SH0288 1033 E ORANGE ST ANGLETON CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 554,801.24 REPORT DATE 11/03/2009 15.47.42 CONTRACTOR PARK CONSTRUCTION 12674 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 018 DIST. 12 COUNTY BRAZORIA CONTROL 6170-82-001 PROJECT RMC - 617082001 HIGHWAY SH0288 0LIMITS- VARIOUS HWYS IN SOUTH BRAZORIA COUNTY VARIOUS HWYS IN SOUTH BRAZORIA COUNTY 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY MICHELLE E. MILLIARD, P.E. 0 0055 MOWING HIGHWAY RIGHT OF WAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 25,333.390 13,084.907 21.900 286,559.46 0060 0730 ADJ EST QUANTITY TO DATE 27,451.162 0 SUBTOTAL BID ITEMS $ 286,559.46 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY RIGHT OF WAY $ 286,559.46 0 0110 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0111 UNIFORM POLICE OFFICER 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6170-82-001 $ 286,559.46 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1084029 MGR.NO. 050 PAGE 001 CONT 6170 SEC 82 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 617082001 HWY SH0288 1033 E ORANGE ST ANGLETON CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 554,801.24 REPORT DATE 11/03/2009 15.47.43 CONTRACTOR PARK CONSTRUCTION 12674 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 018 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN SOUTH BRAZORIA COUNTY 0 VARIOUS HWYS IN SOUTH BRAZORIA COUNTY DATE WORK BEGAN MAY 1 , 2008 WORKING DAYS USED 93 PERCENT COMPLETE 51.65 PERCENT TIME USED 35.70 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6170-82-001 RMC - 617082001 12 SH0288 BRAZORIA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 25,333.390 13,084.907 21.900 286,559.46 0730 ADJ EST QUANTITY TO DATE 27,451.162 0 SUBTOTAL BID ITEMS $ 286,559.46 0 CONTRACT TOTAL ALL ITEMS $ 286,559.46 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1084029 MGR.NO. 050 PAGE 001 CONT 6170 SEC 82 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 617082001 HWY SH0288 1033 E ORANGE ST ANGLETON CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 554,801.24 REPORT DATE 11/03/2009 15.47.43 CONTRACTOR PARK CONSTRUCTION 12674 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 018 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 20 RMC - 617082001 6170-82-001 286,559.46 .00 286,559.46 .00 .00 286,559.46 284,676.06 1,883.40 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 286,559.46 .00 286,559.46 .00 .00 286,559.46 284,676.06 1,883.40 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1084029 MGR.NO. 050 PAGE 001 CONT 6170 SEC 82 JOB 001 RES ENGR HECKATHORN, LAWRENCE PROJ RMC - 617082001 HWY SH0288 1033 E ORANGE ST ANGLETON CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 554,801.24 REPORT DATE 11/03/2009 15.47.43 CONTRACTOR PARK CONSTRUCTION 12674 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 018 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6170-82-001 RMC - 617082001 12 SH0288 BRAZORIA -LIMITS - VARIOUS HWYS IN SOUTH BRAZORIA COUNTY VARIOUS HWYS IN SOUTH BRAZORIA COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 25,333.390 86.000 21.900 1,883.40 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 1,883.40 0 TOTAL AMOUNT WORK DONE TO DATE - $ 286,559.46