1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10071231 MGR.NO. 063 PAGE 001 CONT 6168 SEC 85 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 616885001 HWY IH0045 2020 N LOOP WEST HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 47,696.52 REPORT DATE 08/23/2013 13.28.40 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 06,2007 TO NOV 05,2008 EST NO 014 & FINAL ON OUR OWN SERVICES, INC. 09648 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 06, 2007 TIME COMPUTED FROM NOV 06, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 366 361 361 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 08 1 1 TOTAL DAYS ALLOWED = 366 2 1 DATE WORK COMPLETED 11/05/08 3 1 DAYS CHARGED TO DATE = 366 4 1 ASSESSED LIQ DAMAGES = 0 5 1 WORK COMPLETED LIQ DAMAGE RATE $ 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 366 366 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10071231 MGR.NO. 063 PAGE 001 CONT 6168 SEC 85 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 616885001 HWY IH0045 2020 N LOOP WEST HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 47,696.52 REPORT DATE 08/23/2013 13.28.40 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 06,2007 TO NOV 05,2008 EST NO 014 & FINAL ON OUR OWN SERVICES, INC. 09648 DIST. 12 COUNTY HARRIS CONTROL 6168-85-001 PROJECT SUP - 616885001 HIGHWAY IH0045 0LIMITS- IH 45 US 59 INTERCHANGE 0TYPE OF WORK- LANDSCAPE MAINTENANCE 0 0005 PREPARED BY: CONNIE NOBLES 0 0055 LANDSCAPE MAINTENANCE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0751 LITTER PICKUP CYC 36.000 25.000 172.540 4,313.50 0065 0751 MOWING, TRIMMING, AND EDGING CYC 36.000 23.000 1,001.050 23,024.15 0070 0751 MULCH & RESHAPING OF PLANT BEDS CYC 1.000 0.000 1,150.080 .00 0075 0751 PLANT BED MAINTENANCE CYC 36.000 23.000 87.420 2,010.66 0080 0751 PRUNING CYC 1.000 9.000 1,150.080 10,350.72 0 SUBTOTAL BID ITEMS $ 39,699.03 0 TOTAL AMOUNT WORK DONE LANDSCAPE MAINTENANCE $ 39,699.03 0 TOTAL AMOUNT WORK DONE CONTROL 6168-85-001 $ 39,699.03 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10071231 MGR.NO. 063 PAGE 001 CONT 6168 SEC 85 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 616885001 HWY IH0045 2020 N LOOP WEST HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 47,696.52 REPORT DATE 08/23/2013 13.28.40 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 06,2007 TO NOV 05,2008 EST NO 014 & FINAL ON OUR OWN SERVICES, INC. 09648 0*********************************************************************************************************************************** -LIMITS - IH 45 0 US 59 INTERCHANGE DATE WORK BEGAN NOV 6 , 2007 WORKING DAYS USED 366 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED NOV 5 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6168-85-001 SUP - 616885001 12 IH0045 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0751 LITTER PICKUP CYC 36.000 25.000 172.540 4,313.50 0751 MOWING, TRIMMING, AND EDGING CYC 36.000 23.000 1,001.050 23,024.15 0751 PLANT BED MAINTENANCE CYC 36.000 23.000 87.420 2,010.66 0751 PRUNING CYC 1.000 9.000 1,150.080 10,350.72 0 SUBTOTAL BID ITEMS $ 39,699.03 0 CONTRACT TOTAL ALL ITEMS $ 39,699.03 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10071231 MGR.NO. 063 PAGE 001 CONT 6168 SEC 85 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 616885001 HWY IH0045 2020 N LOOP WEST HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 47,696.52 REPORT DATE 08/23/2013 13.28.40 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 06,2007 TO NOV 05,2008 EST NO 014 & FINAL ON OUR OWN SERVICES, INC. 09648 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 SUP - 616885001 6168-85-001 39,699.03 .00 39,699.03 .00 .00 39,699.03 39,699.03 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 39,699.03 .00 39,699.03 .00 .00 39,699.03 39,699.03 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10071231 MGR.NO. 063 PAGE 001 CONT 6168 SEC 85 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 616885001 HWY IH0045 2020 N LOOP WEST HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 47,696.52 REPORT DATE 08/23/2013 13.28.41 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 06,2007 TO NOV 05,2008 EST NO 014 & FINAL ON OUR OWN SERVICES, INC. 09648 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6168-85-001 SUP - 616885001 12 IH0045 HARRIS -LIMITS - IH 45 US 59 INTERCHANGE - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 39,699.03