1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9071206 MGR.NO. 061 PAGE 001 CONT 6165 SEC 59 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 616559001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 312,660.00 REPORT DATE 10/14/2013 16.30.47 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD NOV 26,2007 TO JAN 14,2009 EST NO 016 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 26, 2007 TIME COMPUTED FROM NOV 26, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 366 402 366 36 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 09 1 1 AWAITING FINAL INSPECTION TOTAL DAYS ALLOWED = 366 2 1 AWAITING FINAL INSPECTION DATE WORK COMPLETED 01/14/09 3 1 AWAITING FINAL INSPECTION DAYS CHARGED TO DATE = 366 4 1 AWAITING FINAL INSPECTION ASSESSED LIQ DAMAGES = 0 5 1 AWAITING FINAL INSPECTION LIQ DAMAGE RATE $ 0 6 1 AWAITING FINAL INSPECTION 7 1 AWAITING FINAL INSPECTION LIQUIDATED DAMAGES 8 1 AWAITING FINAL INSPECTION 0 DAYS AT $ 0 PER DAY 9 1 AWAITING FINAL INSPECTION TOTAL = $ .00 10 1 AWAITING FINAL INSPECTION 11 1 AWAITING FINAL INSPECTION CERTIFIED AS CORRECT AND 12 1 AWAITING FINAL INSPECTION ONE COPY HAS BEEN GIVEN 13 1 AWAITING FINAL INSPECTION TO THE CONTRACTOR 14 1 WORK ACCEPTED 0 ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 416 366 50 0 SATURDAY 0 SUNDAY 0 HOLIDAY 13 AWAITING FINAL INSPECTION 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9071206 MGR.NO. 061 PAGE 001 CONT 6165 SEC 59 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 616559001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 312,660.00 REPORT DATE 10/14/2013 16.30.47 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD NOV 26,2007 TO JAN 14,2009 EST NO 016 & FINAL INC. 00644 DIST. 12 COUNTY FORT BEND CONTROL 6165-59-001 PROJECT RMC - 616559001 HIGHWAY US0059 0LIMITS- VARIOUS HWYS IN FORT BEND COUNTY VARIOUS HWYS IN FORT BEND COUNTY 0TYPE OF WORK- ASPHALT PAVEMENT REPAIR 0 0050 ASPHALT PAVEMENT REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY: JILL M. OLSON, P.E. 0 0075 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 8,100.000 8,625.074 38.600 332,927.86 0080 9000*UNIFORM POLICE OFFICERS EA 8,000.000 437.460 1.000 437.46 0 SUBTOTAL BID ITEMS $ 333,365.32 0 TOTAL AMOUNT WORK DONE ASPHALT PAVEMENT REPAIR $ 333,365.32 0 0125 CONTRACTOR FORCE ACT OR AGR UNIT NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0126 PRICE 0127 POLICE OFFICERS 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACT OR AGR UNIT $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6165-59-001 $ 333,365.32 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9071206 MGR.NO. 061 PAGE 001 CONT 6165 SEC 59 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 616559001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 312,660.00 REPORT DATE 10/14/2013 16.30.47 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD NOV 26,2007 TO JAN 14,2009 EST NO 016 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN FORT BEND COUNTY 0 VARIOUS HWYS IN FORT BEND COUNTY DATE WORK BEGAN NOV 26, 2007 WORKING DAYS USED 366 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED JAN 14 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6165-59-001 RMC - 616559001 12 US0059 FORT BEND - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 8,100.000 8,625.074 38.600 332,927.86 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* UNIFORM POLICE OFFICERS EA 8,000.000 437.460 1.000 437.46 0 SUBTOTAL BID ITEMS $ 333,365.32 0 CONTRACT TOTAL ALL ITEMS $ 333,365.32 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9071206 MGR.NO. 061 PAGE 001 CONT 6165 SEC 59 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 616559001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 312,660.00 REPORT DATE 10/14/2013 16.30.47 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD NOV 26,2007 TO JAN 14,2009 EST NO 016 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 80 RMC - 616559001 6165-59-001 333,365.32 .00 333,365.32 .00 .00 333,365.32 333,365.32 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 333,365.32 .00 333,365.32 .00 .00 333,365.32 333,365.32 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9071206 MGR.NO. 061 PAGE 001 CONT 6165 SEC 59 JOB 001 RES ENGR HUNT, JAMES PROJ RMC - 616559001 HWY US0059 4235 SH 36 SOUTH ROSENBER CNTY FORT BEND DIST 12 CONTRACT PRICE $ 312,660.00 REPORT DATE 10/14/2013 16.30.47 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD NOV 26,2007 TO JAN 14,2009 EST NO 016 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6165-59-001 RMC - 616559001 12 US0059 FORT BEND -LIMITS - VARIOUS HWYS IN FORT BEND COUNTY VARIOUS HWYS IN FORT BEND COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 333,365.32