1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6071205 MGR.NO. 052 PAGE 001 CONT 6160 SEC 26 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 616026001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 59,400.00 REPORT DATE 06/25/2013 15.06.34 CONTRACTOR KWN CONSTRUCTION & DEMOLITION 13127 EST PERIOD AUG 01,2007 TO SEP 25,2007 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 15, 2007 TIME COMPUTED FROM AUG 01, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 731 31 31 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 07 1 1 TOTAL DAYS ALLOWED = 731 2 1 DATE WORK COMPLETED 09/25/07 3 1 DAYS CHARGED TO DATE = 56 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 - - ----- ----- ----- 56 56 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6071205 MGR.NO. 052 PAGE 001 CONT 6160 SEC 26 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 616026001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 59,400.00 REPORT DATE 06/25/2013 15.06.34 CONTRACTOR KWN CONSTRUCTION & DEMOLITION 13127 EST PERIOD AUG 01,2007 TO SEP 25,2007 EST NO 003 & FINAL DIST. 12 COUNTY HARRIS CONTROL 6160-26-001 PROJECT RMC - 616026001 HIGHWAY IH0010 0LIMITS- VARIOUS HWYS IN EAST HARRIS COUNTY VARIOUS HWYS IN EAST HARRIS COUNTY 0TYPE OF WORK- GRAFFITI REMOVAL 0 0050 GRAFFITI REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY RHONDA K. ROBERTS 0 0075 0740 GRAFFITI REMOVAL (BLAST CLEANING) SF 25,000.000 0.000 .920 .00 0080 0740 GRAFFITI REMOVAL (PAINTING) SF 70,000.000 0.000 .520 .00 0 TOTAL AMOUNT WORK DONE GRAFFITI REMOVAL $ .00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6071205 MGR.NO. 052 PAGE 001 CONT 6160 SEC 26 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 616026001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 59,400.00 REPORT DATE 06/25/2013 15.06.35 CONTRACTOR KWN CONSTRUCTION & DEMOLITION 13127 EST PERIOD AUG 01,2007 TO SEP 25,2007 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN EAST HARRIS COUNTY 0 VARIOUS HWYS IN EAST HARRIS COUNTY DATE WORK BEGAN AUG 15, 2007 WORKING DAYS USED 56 PERCENT COMPLETE 0.00 PERCENT TIME USED 7.60 DATE COMPLETED SEP 25 2007 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6160-26-001 RMC - 616026001 12 IH0010 HARRIS 0***** NO WORK TO DATE FOR CONTRACT ***** 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6071205 MGR.NO. 052 PAGE 001 CONT 6160 SEC 26 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 616026001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 59,400.00 REPORT DATE 06/25/2013 15.06.35 CONTRACTOR KWN CONSTRUCTION & DEMOLITION 13127 EST PERIOD AUG 01,2007 TO SEP 25,2007 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 RMC - 616026001 6160-26-001 .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6071205 MGR.NO. 052 PAGE 001 CONT 6160 SEC 26 JOB 001 RES ENGR ALLEN, QUINCY PROJ RMC - 616026001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 59,400.00 REPORT DATE 06/25/2013 15.06.35 CONTRACTOR KWN CONSTRUCTION & DEMOLITION 13127 EST PERIOD AUG 01,2007 TO SEP 25,2007 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6160-26-001 RMC - 616026001 12 IH0010 HARRIS -LIMITS - VARIOUS HWYS IN EAST HARRIS COUNTY VARIOUS HWYS IN EAST HARRIS COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 0.00