1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7094003 MGR.NO. 775 PAGE 001 CONT 6158 SEC 97 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 615897001 HWY IH0610 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 1,649,800.00 REPORT DATE 05/09/2014 08.32.46 CONTRACTOR LINDSEY ELECTRIC, L.P. 10649 EST PERIOD SEP 03,2009 TO JUL 01,2011 EST NO 024 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 03, 2009 TIME COMPUTED FROM SEP 03, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 666 666 0 BROUGHT FORWARD ADDL DAYS GRANTED = 1 JUL 11 1 1 TOTAL DAYS ALLOWED = 731 DATE WORK COMPLETED 07/01/11 DAYS CHARGED TO DATE = 667 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 667 667 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7094003 MGR.NO. 775 PAGE 001 CONT 6158 SEC 97 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 615897001 HWY IH0610 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 1,649,800.00 REPORT DATE 05/09/2014 08.32.46 CONTRACTOR LINDSEY ELECTRIC, L.P. 10649 EST PERIOD SEP 03,2009 TO JUL 01,2011 EST NO 024 & FINAL DIST. 12 COUNTY HARRIS CONTROL 6158-97-001 PROJECT RMC - 615897001 HIGHWAY IH0610 0LIMITS- VARIOUS HWYS IN HOUSTON DISTRICT VARIOUS HWYS IN HOUSTON DISTRICT 0TYPE OF WORK- MAINTENANCE OF TRAFFIC SIGNALS 0 0050 MAINTENANCE OF TRAFFIC SIGNALS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 TRNSP OPRS/SIGNALS, MAINT., AND CONSTRUCTION 0 0075 0690 INSTALL OF SIGNAL RELATED SIGNS EA 275.000 579.000 150.000 86,850.00 0080 0690 INSTALL OF PEDESTRIAN PUSH BUTTONS EA 250.000 198.000 40.000 7,920.00 0085 0690 INSTALL OF FND FOR GROUND MNT CABINETS EA 6.000 2.000 500.000 1,000.00 0090 0690 INSTALL OF CONTROL CABINET (GRND MNT) EA 10.000 5.000 550.000 2,750.00 0095 0690 INSTALL OF FLASHER CABINET EA 50.000 130.000 200.000 26,000.00 0100 0690 INSTAL RM CONDUIT BY TRENCHING (1") LF 1,000.000 310.000 6.000 1,860.00 0105 0690 INSTAL RM CONDUIT BY TRENCHING (2") LF 2,000.000 1,009.000 9.000 9,081.00 0110 0690 INSTAL RM CONDUIT BY TRENCHING (3") LF 500.000 90.000 14.000 1,260.00 0115 0690 INSTAL RM CONDUIT BY TRENCHING (4") LF 500.000 40.000 22.000 880.00 0120 0690 INSTAL PVC CONDUIT BY TRENCHING (1") LF 1,000.000 120.000 4.000 480.00 0125 0690 INSTAL PVC CONDUIT BY TRENCHING (2") LF 2,000.000 80.000 6.000 480.00 0130 0690 INSTAL PVC CONDUIT BY TRENCHING (3") LF 500.000 0.000 6.000 .00 0135 0690 INSTAL PVC CONDUIT BY TRENCHING (4") LF 1,000.000 0.000 9.000 .00 0140 0690 INSTL CBL (1 CONDR NO. 6 BARE) LF 1,000.000 1,023.000 .600 613.80 0145 0690 INSTL CBL (1 CONDR NO. 2/0) LF 1,500.000 0.000 1.000 .00 0150 0690 INSTL CBL (1 CONDR NO. 1/0) LF 3,500.000 435.000 1.000 435.00 1 0155 0690 INSTL CBL (2 CONDR NO. 12 SHIELDED) LF 40,000.000 10,550.000 1.000 10,550.00 0160 0690 INSTL CBL (2 CONDR NO. 12) LF 40,000.000 42,394.000 1.500 63,591.00 0165 0690 INSTL CBL (4 CONDR NO. 12) LF 40,000.000 60,923.000 2.000 121,846.00 0170 0690 INSTL CBL (7 CONDR NO. 12) LF 20,000.000 30,607.000 2.500 76,517.50 0175 0690 INSTL CBL (1 CONDR NO. 6) LF 10,000.000 9,585.000 1.000 9,585.00 0180 0690 INSTL CBL(MULTI CONDR COMMUN25PR NO.22) LF 15,000.000 8,065.000 2.000 16,130.00 0185 0690 SPAN CABLE (5/16") LF 26,000.000 50,250.000 2.200 110,550.00 0190 0690 SPAN CABLE (3/8") LF 10,000.000 1,450.000 2.200 3,190.00 0195 0690 INSTL OF CBL BY MESSENGER CBL(2 CONDR) LF 30,000.000 25,199.000 1.500 37,798.50 0200 0690 INSTL OF CBL BY MESSENGER CBL(4 CONDR) LF 18,000.000 16,376.000 1.500 24,564.00 0205 0690 INSTL OF CBL BY MESSENGER CBL(7 CONDR) LF 26,000.000 26,506.000 1.500 39,759.00 0210 0690 INSTL CBL BY MESSENGER (1 CONDR POWER) LF 2,000.000 145.000 1.100 159.50 0215 0690 INSTLCBLMSNGRMULTICONDRCOMM UN25PRNO.22) LF 24,000.000 22,938.000 2.750 63,079.50 0220 0690 INSTL PHOTO CELL EA 80.000 13.000 20.000 260.00 0225 0690 INSTAL OF FND FOR STRAIN SGL POLE EA 20.000 6.000 500.000 3,000.00 0230 0690 INSTAL OF FND FOR PEDESTAL POLE EA 100.000 314.000 200.000 62,800.00 0235 0690 INSTAL OF FND FOR MAST ARM POLE EA 10.000 3.000 1,000.000 3,000.00 0240 0690 INSTAL OF SIGNAL POLE (STEEL SERV) EA 30.000 5.000 200.000 1,000.00 0245 0690 INSTAL OF TIMBER POLE (35') EA 20.000 6.000 300.000 1,800.00 0250 0690 INSTAL OF TIMBER POLE (40') EA 25.000 27.000 300.000 8,100.00 0255 0690 INSTAL OF TIMBER POLE (45') EA 10.000 1.000 300.000 300.00 0260 0690 INSTL OF MAST ARM SGL POLE (SINGLE ARM) EA 8.000 3.000 400.000 1,200.00 0265 0690 INSTL OF MAST ARM SGL POLE (DUAL ARM) EA 8.000 1.000 500.000 500.00 0270 0690 INSTL SGL POLE(4 1/2"OD PED W/TRANS BS) EA 125.000 309.000 300.000 92,700.00 0275 0690 INSTL STEEL STRAIN POLE EA 10.000 13.000 300.000 3,900.00 0280 0690 INSTL LUMINAIRE HEAD AND MAST ARMS EA 30.000 30.000 200.000 6,000.00 0285 0690 SOLDER AND WEATHERPROOF SPLICE EA 600.000 1,487.000 40.000 59,480.00 0290 0690 INSTL SGL HD ASSM(LED)(1W1S)PED W/BRKT EA 125.000 193.000 400.000 77,200.00 0295 0690 INSTL SGL HD ASSM(LED)(1W1S)W/BRKT BKPL EA 125.000 495.000 275.000 136,125.00 0300 0690 INSTL SGL HD ASSM(LED)(1W2S)W/BRKT BKPL EA 25.000 0.000 200.000 .00 0305 0690 INSTL SGL HD ASSM(LED)(1W3S)W/BRKT BKPL EA 675.000 363.000 565.000 205,095.00 1 0310 0690 INSTL SGL HD ASSM(LED)(1W4S)W/BRKT BKPL EA 100.000 78.000 650.000 50,700.00 0315 0690 INSTLSGLHDASSM (CLSLED)(1W5S)W/BRKT BKPL EA 15.000 6.000 900.000 5,400.00 0320 0690 INSTL DOWN GUY W/GUARD EA 50.000 62.000 100.000 6,200.00 0325 0690 INSTL DOWN GUY W/GUARD AND ANCHOR EA 50.000 27.000 200.000 5,400.00 0330 0690 INSTL OF CONDUIT BY TRENCHING & JACKING EA 250.000 150.000 20.000 3,000.00 0335 0690 INSTL OF ELECTRICAL SRV EXCLUDING POLE EA 45.000 77.000 2,100.000 161,700.00 0335 0690 ADJ EST QUANTITY TO DATE 67.000 0340 0690 INSTL OF GROUND BOX W/APRON TYPE D EA 65.000 21.000 500.000 10,500.00 0345 0690 INSTL SOLAR POWERED FLASHER ASSEM EA 35.000 97.000 600.000 58,200.00 0350 0690 INSTL LUMINAIRE HEAD EA 200.000 23.000 100.000 2,300.00 0355 0690 INSTAL PVC CONDUIT BY TRENCHING (1/2") LF 200.000 0.000 2.000 .00 0360 0690 INSTL PVC CONDUIT BY TRENCHING (1 1/2") LF 200.000 315.000 3.000 945.00 0365 0690 INSTL RM CONDUIT BY TENCHING (1 1/2") LF 1,000.000 430.000 6.000 2,580.00 0370 0690 INSTL ILLUMINATION LAMP EA 150.000 20.000 40.000 800.00 0375 0690 REPL 12" LED TRF SIG LAMP UNIT (RED) EA 300.000 17.000 100.000 1,700.00 0380 0690 REPL 12" LED TRF SIG LAMP UNIT (AMBER) EA 100.000 16.000 100.000 1,600.00 0385 0690 REPL 12" LED TRF SIG LAMP UNIT (GREEN) EA 150.000 17.000 200.000 3,400.00 0390 0690 REPL 12" LED TRF SIG LAMP UNIT(GRN ARW) EA 50.000 0.000 110.000 .00 0395 0690 REP 12" LED TRF SIG LAMP UNIT(AMBR ARW) EA 50.000 0.000 170.000 .00 0 SUBTOTAL BID ITEMS $ 1,693,814.80 0 TOTAL AMOUNT WORK DONE MAINTENANCE OF TRAFFIC SIGNALS $ 1,693,814.80 0 TOTAL AMOUNT WORK DONE CONTROL 6158-97-001 $ 1,693,814.80 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7094003 MGR.NO. 775 PAGE 001 CONT 6158 SEC 97 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 615897001 HWY IH0610 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 1,649,800.00 REPORT DATE 05/09/2014 08.32.47 CONTRACTOR LINDSEY ELECTRIC, L.P. 10649 EST PERIOD SEP 03,2009 TO JUL 01,2011 EST NO 024 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN HOUSTON DISTRICT 0 VARIOUS HWYS IN HOUSTON DISTRICT DATE WORK BEGAN SEP 3 , 2009 WORKING DAYS USED 667 PERCENT COMPLETE 100.00 PERCENT TIME USED 91.20 DATE COMPLETED JUL 1 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6158-97-001 RMC - 615897001 12 IH0610 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0690 INSTALL OF SIGNAL RELATED SIGNS EA 275.000 579.000 150.000 86,850.00 0690 INSTALL OF PEDESTRIAN PUSH BUTTONS EA 250.000 198.000 40.000 7,920.00 0690 INSTALL OF FND FOR GROUND MNT CABINETS EA 6.000 2.000 500.000 1,000.00 0690 INSTALL OF CONTROL CABINET (GRND MNT) EA 10.000 5.000 550.000 2,750.00 0690 INSTALL OF FLASHER CABINET EA 50.000 130.000 200.000 26,000.00 0690 INSTAL RM CONDUIT BY TRENCHING (1") LF 1,000.000 310.000 6.000 1,860.00 0690 INSTAL RM CONDUIT BY TRENCHING (2") LF 2,000.000 1,009.000 9.000 9,081.00 0690 INSTAL RM CONDUIT BY TRENCHING (3") LF 500.000 90.000 14.000 1,260.00 0690 INSTAL RM CONDUIT BY TRENCHING (4") LF 500.000 40.000 22.000 880.00 0690 INSTAL PVC CONDUIT BY TRENCHING (1") LF 1,000.000 120.000 4.000 480.00 0690 INSTAL PVC CONDUIT BY TRENCHING (2") LF 2,000.000 80.000 6.000 480.00 0690 INSTL CBL (1 CONDR NO. 6 BARE) LF 1,000.000 1,023.000 .600 613.80 0690 INSTL CBL (1 CONDR NO. 1/0) LF 3,500.000 435.000 1.000 435.00 0690 INSTL CBL (2 CONDR NO. 12 1 SHIELDED) LF 40,000.000 10,550.000 1.000 10,550.00 0690 INSTL CBL (2 CONDR NO. 12) LF 40,000.000 42,394.000 1.500 63,591.00 0690 INSTL CBL (4 CONDR NO. 12) LF 40,000.000 60,923.000 2.000 121,846.00 0690 INSTL CBL (7 CONDR NO. 12) LF 20,000.000 30,607.000 2.500 76,517.50 0690 INSTL CBL (1 CONDR NO. 6) LF 10,000.000 9,585.000 1.000 9,585.00 0690 INSTL CBL(MULTI CONDR COMMUN25PR NO.22) LF 15,000.000 8,065.000 2.000 16,130.00 0690 SPAN CABLE (5/16") LF 26,000.000 50,250.000 2.200 110,550.00 0690 SPAN CABLE (3/8") LF 10,000.000 1,450.000 2.200 3,190.00 0690 INSTL OF CBL BY MESSENGER CBL(2 CONDR) LF 30,000.000 25,199.000 1.500 37,798.50 0690 INSTL OF CBL BY MESSENGER CBL(4 CONDR) LF 18,000.000 16,376.000 1.500 24,564.00 0690 INSTL OF CBL BY MESSENGER CBL(7 CONDR) LF 26,000.000 26,506.000 1.500 39,759.00 0690 INSTL CBL BY MESSENGER (1 CONDR POWER) LF 2,000.000 145.000 1.100 159.50 0690 INSTLCBLMSNGRMULTICONDRCOMM UN25PRNO.22) LF 24,000.000 22,938.000 2.750 63,079.50 0690 INSTL PHOTO CELL EA 80.000 13.000 20.000 260.00 0690 INSTAL OF FND FOR STRAIN SGL POLE EA 20.000 6.000 500.000 3,000.00 0690 INSTAL OF FND FOR PEDESTAL POLE EA 100.000 314.000 200.000 62,800.00 0690 INSTAL OF FND FOR MAST ARM POLE EA 10.000 3.000 1,000.000 3,000.00 0690 INSTAL OF SIGNAL POLE (STEEL SERV) EA 30.000 5.000 200.000 1,000.00 0690 INSTAL OF TIMBER POLE (35') EA 20.000 6.000 300.000 1,800.00 0690 INSTAL OF TIMBER POLE (40') EA 25.000 27.000 300.000 8,100.00 0690 INSTAL OF TIMBER POLE (45') EA 10.000 1.000 300.000 300.00 0690 INSTL OF MAST ARM SGL POLE (SINGLE ARM) EA 8.000 3.000 400.000 1,200.00 0690 INSTL OF MAST ARM SGL POLE (DUAL ARM) EA 8.000 1.000 500.000 500.00 0690 INSTL SGL POLE(4 1/2"OD PED W/TRANS BS) EA 125.000 309.000 300.000 92,700.00 0690 INSTL STEEL STRAIN POLE EA 10.000 13.000 300.000 3,900.00 0690 INSTL LUMINAIRE HEAD AND MAST ARMS EA 30.000 30.000 200.000 6,000.00 0690 SOLDER AND WEATHERPROOF SPLICE EA 600.000 1,487.000 40.000 59,480.00 0690 INSTL SGL HD ASSM(LED)(1W1S)PED W/BRKT EA 125.000 193.000 400.000 77,200.00 0690 INSTL SGL HD ASSM(LED)(1W1S)W/BRKT BKPL EA 125.000 495.000 275.000 136,125.00 0690 INSTL SGL HD ASSM(LED)(1W3S)W/BRKT BKPL EA 675.000 363.000 565.000 205,095.00 0690 INSTL SGL HD ASSM(LED)(1W4S)W/BRKT BKPL EA 100.000 78.000 650.000 50,700.00 0690 INSTLSGLHDASSM 1 (CLSLED)(1W5S)W/BRKT BKPL EA 15.000 6.000 900.000 5,400.00 0690 INSTL DOWN GUY W/GUARD EA 50.000 62.000 100.000 6,200.00 0690 INSTL DOWN GUY W/GUARD AND ANCHOR EA 50.000 27.000 200.000 5,400.00 0690 INSTL OF CONDUIT BY TRENCHING & JACKING EA 250.000 150.000 20.000 3,000.00 0690 INSTL OF ELECTRICAL SRV EXCLUDING POLE EA 45.000 77.000 2,100.000 161,700.00 0690 ADJ EST QUANTITY TO DATE 67.000 0690 INSTL OF GROUND BOX W/APRON TYPE D EA 65.000 21.000 500.000 10,500.00 0690 INSTL SOLAR POWERED FLASHER ASSEM EA 35.000 97.000 600.000 58,200.00 0690 INSTL LUMINAIRE HEAD EA 200.000 23.000 100.000 2,300.00 0690 INSTL PVC CONDUIT BY TRENCHING (1 1/2") LF 200.000 315.000 3.000 945.00 0690 INSTL RM CONDUIT BY TENCHING (1 1/2") LF 1,000.000 430.000 6.000 2,580.00 0690 INSTL ILLUMINATION LAMP EA 150.000 20.000 40.000 800.00 0690 REPL 12" LED TRF SIG LAMP UNIT (RED) EA 300.000 17.000 100.000 1,700.00 0690 REPL 12" LED TRF SIG LAMP UNIT (AMBER) EA 100.000 16.000 100.000 1,600.00 0690 REPL 12" LED TRF SIG LAMP UNIT (GREEN) EA 150.000 17.000 200.000 3,400.00 0 SUBTOTAL BID ITEMS $ 1,693,814.80 0 CONTRACT TOTAL ALL ITEMS $ 1,693,814.80 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7094003 MGR.NO. 775 PAGE 001 CONT 6158 SEC 97 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 615897001 HWY IH0610 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 1,649,800.00 REPORT DATE 05/09/2014 08.32.47 CONTRACTOR LINDSEY ELECTRIC, L.P. 10649 EST PERIOD SEP 03,2009 TO JUL 01,2011 EST NO 024 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 RMC - 615897001 6158-97-001 1,693,814.80 .00 1,693,814.80 .00 .00 1,693,814.80 1,693,814.80 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 1,693,814.80 .00 1,693,814.80 .00 .00 1,693,814.80 1,693,814.80 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7094003 MGR.NO. 775 PAGE 001 CONT 6158 SEC 97 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 615897001 HWY IH0610 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 1,649,800.00 REPORT DATE 05/09/2014 08.32.47 CONTRACTOR LINDSEY ELECTRIC, L.P. 10649 EST PERIOD SEP 03,2009 TO JUL 01,2011 EST NO 024 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6158-97-001 RMC - 615897001 12 IH0610 HARRIS -LIMITS - VARIOUS HWYS IN HOUSTON DISTRICT VARIOUS HWYS IN HOUSTON DISTRICT - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 1,693,814.80