1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11081202 MGR.NO. 060 PAGE 001 CONT 6156 SEC 22 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 615622001 HWY SH0146 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 81,460.00 REPORT DATE 11/03/2009 09.15.35 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN 0 00, 2000 TIME COMPUTED FROM SEP 14, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 17 0 17 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TIME SUSP - LETTER SUBMITTED TOTAL DAYS ALLOWED = 30 2 1 TIME SUSP - LETTER SUBMITTED DATE WORK COMPLETED 3 1 TIME SUSP - LETTER SUBMITTED DAYS CHARGED TO DATE = 0 4 1 TIME SUSP - LETTER SUBMITTED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSP - LETTER SUBMITTED LIQ DAMAGE RATE $ 0 6 1 TIME SUSP - LETTER SUBMITTED 7 1 TIME SUSP - LETTER SUBMITTED LIQUIDATED DAMAGES 8 1 TIME SUSP - LETTER SUBMITTED 0 DAYS AT $ 0 PER DAY 9 1 TIME SUSP - LETTER SUBMITTED TOTAL = $ .00 10 1 TIME SUSP - LETTER SUBMITTED 11 1 TIME SUSP - LETTER SUBMITTED CERTIFIED AS CORRECT AND 12 1 TIME SUSP - LETTER SUBMITTED ONE COPY HAS BEEN GIVEN 13 1 TIME SUSP - LETTER SUBMITTED TO THE CONTRACTOR 14 1 TIME SUSP - LETTER SUBMITTED 15 1 TIME SUSP - LETTER SUBMITTED 16 1 TIME SUSP - LETTER SUBMITTED ---------------------------- 17 1 TIME SUSP - LETTER SUBMITTED AREA/PROJECT ENGINEER 18 1 TIME SUSP - LETTER SUBMITTED 19 1 TIME SUSP - LETTER SUBMITTED 20 1 TIME SUSP - LETTER SUBMITTED 21 1 TIME SUSP - LETTER SUBMITTED 22 1 TIME SUSP - LETTER SUBMITTED 23 1 TIME SUSP - LETTER SUBMITTED 24 1 TIME SUSP - LETTER SUBMITTED 25 1 TIME SUSP - LETTER SUBMITTED 26 1 TIME SUSP - LETTER SUBMITTED 27 1 TIME SUSP - LETTER SUBMITTED 28 1 TIME SUSP - LETTER SUBMITTED 29 1 TIME SUSP - LETTER SUBMITTED 30 1 TIME SUSP - LETTER SUBMITTED 31 1 TIME SUSP - LETTER SUBMITTED ----- ----- ----- 48 0 48 0 SATURDAY 0 SUNDAY 0 HOLIDAY 31 TIME SUSP - LETTER SUBMITTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11081202 MGR.NO. 060 PAGE 001 CONT 6156 SEC 22 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 615622001 HWY SH0146 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 81,460.00 REPORT DATE 11/03/2009 09.15.36 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 INC. 00644 DIST. 12 COUNTY GALVESTON CONTROL 6156-22-001 PROJECT RMC - 615622001 HIGHWAY SH0146 0LIMITS- SH 146 AT NBI #12-085-0051-03-042 AND IH 45 AT NBI #12-085-0500-01-132 0TYPE OF WORK- STL BRDG MEMBER REP & PAINTING STL CAP 0 0005 PREPARED BY: JEFFERY D. THOMSON 0 0055 STEEL BRIDGE MEMBER REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0438 CLEAN AND SEAL EXIST JOINTS LF 58.000 0.000 70.000 .00 0065 0446 CLEAN & PAINT EXIST STR (SYSTEM II) LS 1.000 0.000 41,000.000 .00 0070 0500 MOBILIZATION LS 1.000 0.000 7,400.000 .00 0075 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 0.000 4,000.000 .00 0080 0784 REPAIR STL BRIDGE MEMBERS LS 1.000 0.000 21,000.000 .00 0 TOTAL AMOUNT WORK DONE STEEL BRIDGE MEMBER REPAIR $ .00 0 0130 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0131 UNIFORMED POLICE OFFICERS 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11081202 MGR.NO. 060 PAGE 001 CONT 6156 SEC 22 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 615622001 HWY SH0146 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 81,460.00 REPORT DATE 11/03/2009 09.15.37 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 INC. 00644 0*********************************************************************************************************************************** -LIMITS - SH 146 AT NBI #12-085-0051-03-042 AND 0 IH 45 AT NBI #12-085-0500-01-132 DATE WORK BEGAN WORKING DAYS USED 0 PERCENT COMPLETE 0.00 PERCENT TIME USED 0.00 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6156-22-001 RMC - 615622001 12 SH0146 GALVESTON 0***** NO WORK TO DATE FOR CONTRACT ***** 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11081202 MGR.NO. 060 PAGE 001 CONT 6156 SEC 22 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 615622001 HWY SH0146 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 81,460.00 REPORT DATE 11/03/2009 09.15.37 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 RMC - 615622001 6156-22-001 .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11081202 MGR.NO. 060 PAGE 001 CONT 6156 SEC 22 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 615622001 HWY SH0146 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 81,460.00 REPORT DATE 11/03/2009 09.15.38 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6156-22-001 RMC - 615622001 12 SH0146 GALVESTON -LIMITS - SH 146 AT NBI #12-085-0051-03-042 AND IH 45 AT NBI #12-085-0500-01-132 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 0.00