1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8081230 MGR.NO. 063 PAGE 001 CONT 6140 SEC 31 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 614031001 HWY IH0610 8301 HEMPSTEAD RD HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 462,879.67 REPORT DATE 10/10/2013 14.58.40 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL ON OUR OWN SERVICES, INC. 09648 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2008 TIME COMPUTED FROM SEP 01, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 334 334 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 08/31/09 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8081230 MGR.NO. 063 PAGE 001 CONT 6140 SEC 31 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 614031001 HWY IH0610 8301 HEMPSTEAD RD HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 462,879.67 REPORT DATE 10/10/2013 14.58.41 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL ON OUR OWN SERVICES, INC. 09648 DIST. 12 COUNTY HARRIS CONTROL 6140-31-001 PROJECT SUP - 614031001 HIGHWAY IH0610 0LIMITS- VARIOUS AREAS IN CENTRAL HARRIS AREA . 0TYPE OF WORK- LITTER REMOVAL 0 0005 PREPARED BY TAMEKA PETERS 0 0055 LITTER REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL AC 500.000 48.000 13.000 624.00 0065 0734 LITTER REMOVAL - TRACT (1) CYC 52.000 51.000 876.600 44,706.60 0070 0734 LITTER REMOVAL - TRACT (2) CYC 52.000 51.000 815.330 41,581.83 0075 0734 LITTER REMOVAL - TRACT (3) CYC 26.000 25.000 1,140.420 28,510.50 0080 0734 LITTER REMOVAL - TRACT (4) CYC 52.000 50.000 518.480 25,924.00 0085 0734 LITTER REMOVAL - TRACT (5) CYC 52.000 51.000 1,045.240 53,307.24 0090 0734 LITTER REMOVAL - TRACT (6) CYC 26.000 26.000 924.490 24,036.74 0095 0734 LITTER REMOVAL - TRACT (7) CYC 52.000 48.000 1,077.440 51,717.12 0100 0734 LITTER REMOVAL - TRACT (8) CYC 52.000 45.000 1,421.300 63,958.50 0105 0734 LITTER REMOVAL - TRACT (9) CYC 52.000 51.000 333.230 16,994.73 0110 0734 LITTER REMOVAL - TRACT (10) CYC 26.000 24.000 1,110.800 26,659.20 0115 0734 LITTER REMOVAL - TRACT (11) CYC 26.000 25.000 1,515.050 37,876.25 0120 0734 LITTER REMOVAL - TRACT (12) CYC 17.000 17.000 298.540 5,075.18 0125 0734 LITTER REMOVAL - TRACT (13) CYC 26.000 25.000 322.800 8,070.00 0130 0734 LITTER REMOVAL - TRACT (14) CYC 13.000 13.000 338.130 4,395.69 0200 9000*WAGE INCREASE EA 4,762.620 4,948.090 1.000 4,948.09 0 SUBTOTAL BID ITEMS $ 438,385.67 0 TOTAL AMOUNT WORK DONE LITTER REMOVAL $ 438,385.67 0 TOTAL AMOUNT WORK DONE CONTROL 6140-31-001 $ 438,385.67 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8081230 MGR.NO. 063 PAGE 001 CONT 6140 SEC 31 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 614031001 HWY IH0610 8301 HEMPSTEAD RD HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 462,879.67 REPORT DATE 10/10/2013 14.58.41 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL ON OUR OWN SERVICES, INC. 09648 0*********************************************************************************************************************************** -LIMITS - VARIOUS AREAS IN CENTRAL HARRIS AREA 0 . DATE WORK BEGAN SEP 1 , 2008 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED AUG 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6140-31-001 SUP - 614031001 12 IH0610 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL AC 500.000 48.000 13.000 624.00 0734 LITTER REMOVAL - TRACT (1) CYC 52.000 51.000 876.600 44,706.60 0734 LITTER REMOVAL - TRACT (2) CYC 52.000 51.000 815.330 41,581.83 0734 LITTER REMOVAL - TRACT (3) CYC 26.000 25.000 1,140.420 28,510.50 0734 LITTER REMOVAL - TRACT (4) CYC 52.000 50.000 518.480 25,924.00 0734 LITTER REMOVAL - TRACT (5) CYC 52.000 51.000 1,045.240 53,307.24 0734 LITTER REMOVAL - TRACT (6) CYC 26.000 26.000 924.490 24,036.74 0734 LITTER REMOVAL - TRACT (7) CYC 52.000 48.000 1,077.440 51,717.12 0734 LITTER REMOVAL - TRACT (8) CYC 52.000 45.000 1,421.300 63,958.50 0734 LITTER REMOVAL - TRACT (9) CYC 52.000 51.000 333.230 16,994.73 0734 LITTER REMOVAL - TRACT (10) CYC 26.000 24.000 1,110.800 26,659.20 0734 LITTER REMOVAL - TRACT (11) CYC 26.000 25.000 1,515.050 37,876.25 0734 LITTER REMOVAL - TRACT (12) CYC 17.000 17.000 298.540 5,075.18 0734 LITTER REMOVAL - TRACT (13) CYC 26.000 25.000 322.800 8,070.00 0734 LITTER REMOVAL - TRACT (14) CYC 13.000 13.000 338.130 4,395.69 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* WAGE INCREASE EA 4,762.620 4,948.090 1.000 4,948.09 0 SUBTOTAL BID ITEMS $ 438,385.67 0 CONTRACT TOTAL ALL ITEMS $ 438,385.67 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8081230 MGR.NO. 063 PAGE 001 CONT 6140 SEC 31 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 614031001 HWY IH0610 8301 HEMPSTEAD RD HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 462,879.67 REPORT DATE 10/10/2013 14.58.41 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL ON OUR OWN SERVICES, INC. 09648 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 SUP - 614031001 6140-31-001 438,385.67 .00 438,385.67 .00 .00 438,385.67 438,385.67 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 438,385.67 .00 438,385.67 .00 .00 438,385.67 438,385.67 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8081230 MGR.NO. 063 PAGE 001 CONT 6140 SEC 31 JOB 001 RES ENGR HALVORSEN, CLIFFORD PROJ SUP - 614031001 HWY IH0610 8301 HEMPSTEAD RD HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 462,879.67 REPORT DATE 10/10/2013 14.58.41 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 013 & FINAL ON OUR OWN SERVICES, INC. 09648 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6140-31-001 SUP - 614031001 12 IH0610 HARRIS -LIMITS - VARIOUS AREAS IN CENTRAL HARRIS AREA . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 438,385.67