1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5084029 MGR.NO. 775 PAGE 001 CONT 6137 SEC 93 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 613793001 HWY IH0045 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 952,150.00 REPORT DATE 12/23/2013 15.55.49 CONTRACTOR THIRD COAST SERVICES LLC 12006 EST PERIOD JUL 07,2008 TO JUL 06,2010 EST NO 026 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 07, 2008 TIME COMPUTED FROM JUL 07, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 724 724 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 10 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 07/06/10 3 1 DAYS CHARGED TO DATE = 730 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 WORK COMPLETED AND ACCEPTED. LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 730 730 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5084029 MGR.NO. 775 PAGE 001 CONT 6137 SEC 93 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 613793001 HWY IH0045 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 952,150.00 REPORT DATE 12/23/2013 15.55.49 CONTRACTOR THIRD COAST SERVICES LLC 12006 EST PERIOD JUL 07,2008 TO JUL 06,2010 EST NO 026 & FINAL DIST. 12 COUNTY HARRIS CONTROL 6137-93-001 PROJECT RMC - 613793001 HIGHWAY IH0045 0LIMITS- VARIOUS HIGHWAYS VARIOUS HIGHWAYS 0TYPE OF WORK- LOOP DETECTOR REPAIR AND REPLACE 0 0050 LOOP DETECTOR REPAIR AND REPLACE MA NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 TRANSPORTATION OPERATIONS/TRAFFIC SIGNALS 0 0075 7353 INSTALL LOOP DETECTOR WIRE IN CONDUIT LF 80,000.000 46,266.000 .300 13,879.80 0080 7353 WIRE SPLICES EA 750.000 655.000 9.000 5,895.00 0085 7353 LOOP LEAD-IN CABLE LF 85,000.000 119,044.000 1.000 119,044.00 0085 7353 ADJ EST QUANTITY TO DATE 140,000.000 0090 7353 JACKING AND BORING LF 1,000.000 2,909.000 10.000 29,090.00 0095 7353 SAW CUT (ASPHALT) LF 75,000.000 54,959.000 6.000 329,754.00 0095 7353 ADJ EST QUANTITY TO DATE 65,800.000 0100 7353 SAW CUT (CONCRETE) LF 48,000.000 31,071.000 6.500 201,961.50 0105 7353 SAW CUT (OLD GROOVE) LF 1,000.000 0.000 4.000 .00 0110 7353 INSTALL PULL BOX (TYPE D) EA 105.000 230.000 400.000 92,000.00 0115 7353 TRENCH AND INSTALL CONDUIT (1 INCH) LF 4,000.000 10,098.000 4.000 40,392.00 0120 7353 TRENCH AND INSTALL CONDUIT (2 INCHES) LF 400.000 5,297.000 6.000 31,782.00 0 SUBTOTAL BID ITEMS $ 863,798.30 0 TOTAL AMOUNT WORK DONE LOOP DETECTOR REPAIR AND REPLACE MA $ 863,798.30 0 TOTAL AMOUNT WORK DONE CONTROL 6137-93-001 $ 863,798.30 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5084029 MGR.NO. 775 PAGE 001 CONT 6137 SEC 93 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 613793001 HWY IH0045 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 952,150.00 REPORT DATE 12/23/2013 15.55.49 CONTRACTOR THIRD COAST SERVICES LLC 12006 EST PERIOD JUL 07,2008 TO JUL 06,2010 EST NO 026 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HIGHWAYS 0 VARIOUS HIGHWAYS DATE WORK BEGAN JUL 7 , 2008 WORKING DAYS USED 730 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED JUL 6 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6137-93-001 RMC - 613793001 12 IH0045 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7353 INSTALL LOOP DETECTOR WIRE IN CONDUIT LF 80,000.000 46,266.000 .300 13,879.80 7353 WIRE SPLICES EA 750.000 655.000 9.000 5,895.00 7353 LOOP LEAD-IN CABLE LF 85,000.000 119,044.000 1.000 119,044.00 7353 ADJ EST QUANTITY TO DATE 140,000.000 7353 JACKING AND BORING LF 1,000.000 2,909.000 10.000 29,090.00 7353 SAW CUT (ASPHALT) LF 75,000.000 54,959.000 6.000 329,754.00 7353 ADJ EST QUANTITY TO DATE 65,800.000 7353 SAW CUT (CONCRETE) LF 48,000.000 31,071.000 6.500 201,961.50 7353 INSTALL PULL BOX (TYPE D) EA 105.000 230.000 400.000 92,000.00 7353 TRENCH AND INSTALL CONDUIT (1 INCH) LF 4,000.000 10,098.000 4.000 40,392.00 7353 TRENCH AND INSTALL CONDUIT (2 INCHES) LF 400.000 5,297.000 6.000 31,782.00 0 SUBTOTAL BID ITEMS $ 863,798.30 0 CONTRACT TOTAL ALL ITEMS $ 863,798.30 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5084029 MGR.NO. 775 PAGE 001 CONT 6137 SEC 93 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 613793001 HWY IH0045 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 952,150.00 REPORT DATE 12/23/2013 15.55.49 CONTRACTOR THIRD COAST SERVICES LLC 12006 EST PERIOD JUL 07,2008 TO JUL 06,2010 EST NO 026 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 RMC - 613793001 6137-93-001 863,798.30 .00 863,798.30 .00 .00 863,798.30 863,798.30 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 863,798.30 .00 863,798.30 .00 .00 863,798.30 863,798.30 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5084029 MGR.NO. 775 PAGE 001 CONT 6137 SEC 93 JOB 001 RES ENGR CORDER, STUART PROJ RMC - 613793001 HWY IH0045 7600 WASHINGTON HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 952,150.00 REPORT DATE 12/23/2013 15.55.50 CONTRACTOR THIRD COAST SERVICES LLC 12006 EST PERIOD JUL 07,2008 TO JUL 06,2010 EST NO 026 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6137-93-001 RMC - 613793001 12 IH0045 HARRIS -LIMITS - VARIOUS HIGHWAYS VARIOUS HIGHWAYS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 863,798.30