1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5051202 MGR.NO. 058 PAGE 001 CONT 6129 SEC 05 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 612905001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 147,162.50 REPORT DATE 07/03/2008 14.34.24 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUL 11,2005 TO JUL 10,2006 EST NO 014 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 11, 2005 TIME COMPUTED FROM JUL 11, 2005 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 355 355 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 06 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 07/10/06 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5051202 MGR.NO. 058 PAGE 001 CONT 6129 SEC 05 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 612905001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 147,162.50 REPORT DATE 07/03/2008 14.34.24 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUL 11,2005 TO JUL 10,2006 EST NO 014 & FINAL INC. 00644 DIST. 12 COUNTY WALLER CONTROL 6129-05-001 PROJECT RMC - 612905001 HIGHWAY US0290 0LIMITS- VARIOUS HIGHWAYS IN WALLER COUNTY VARIOUS HIGHWAYS IN WALLER COUNTY 0TYPE OF WORK- ASPHALT PAVEMENT REPAIR 0 0050 ASPHALT PAVEMENT REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY ERA PALMER 0 0075 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 2,000.000 2,347.652 34.000 79,820.17 0080 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 1,750.000 1,843.599 36.750 67,752.26 0085 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 300.000 374.887 49.500 18,556.91 0 SUBTOTAL BID ITEMS $ 166,129.34 0 TOTAL AMOUNT WORK DONE ASPHALT PAVEMENT REPAIR $ 166,129.34 0 0135 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0136 POLICE OFFICERS FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6129-05-001 $ 166,129.34 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5051202 MGR.NO. 058 PAGE 001 CONT 6129 SEC 05 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 612905001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 147,162.50 REPORT DATE 07/03/2008 14.34.25 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUL 11,2005 TO JUL 10,2006 EST NO 014 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HIGHWAYS IN WALLER COUNTY 0 VARIOUS HIGHWAYS IN WALLER COUNTY DATE WORK BEGAN JUL 11, 2005 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED JUL 10 2006 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6129-05-001 RMC - 612905001 12 US0290 WALLER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 2,000.000 2,347.652 34.000 79,820.17 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 1,750.000 1,843.599 36.750 67,752.26 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 300.000 374.887 49.500 18,556.91 0 SUBTOTAL BID ITEMS $ 166,129.34 0 CONTRACT TOTAL ALL ITEMS $ 166,129.34 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5051202 MGR.NO. 058 PAGE 001 CONT 6129 SEC 05 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 612905001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 147,162.50 REPORT DATE 07/03/2008 14.34.25 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUL 11,2005 TO JUL 10,2006 EST NO 014 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 237 RMC - 612905001 6129-05-001 166,129.34 .00 166,129.34 .00 .00 166,129.34 166,129.34 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 166,129.34 .00 166,129.34 .00 .00 166,129.34 166,129.34 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5051202 MGR.NO. 058 PAGE 001 CONT 6129 SEC 05 JOB 001 RES ENGR RANFT, GREGORY PROJ RMC - 612905001 HWY US0290 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 147,162.50 REPORT DATE 07/03/2008 14.34.25 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUL 11,2005 TO JUL 10,2006 EST NO 014 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6129-05-001 RMC - 612905001 12 US0290 WALLER -LIMITS - VARIOUS HIGHWAYS IN WALLER COUNTY VARIOUS HIGHWAYS IN WALLER COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 166,129.34