1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4051231 MGR.NO. 054 PAGE 001 CONT 6128 SEC 74 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ SUP - 612874001 HWY FM1959 702 FM1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 48,680.00 REPORT DATE 06/13/2013 13.59.05 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2005 TO MAY 31,2007 EST NO 025 & FINAL THE CENTER SERVING PERSONS WITH MENTAL RETARDATION 10036 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 01, 2005 TIME COMPUTED FROM JUN 01, 2005 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 699 699 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAY 07 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 05/31/07 3 1 DAYS CHARGED TO DATE = 730 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 730 730 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4051231 MGR.NO. 054 PAGE 001 CONT 6128 SEC 74 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ SUP - 612874001 HWY FM1959 702 FM1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 48,680.00 REPORT DATE 06/13/2013 13.59.06 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2005 TO MAY 31,2007 EST NO 025 & FINAL THE CENTER SERVING PERSONS WITH MENTAL RETARDATION 10036 DIST. 12 COUNTY HARRIS CONTROL 6128-74-001 PROJECT SUP - 612874001 HIGHWAY FM1959 0LIMITS- 702 FM1959 702 FM1959 0TYPE OF WORK- LANDSCAPE MAINTENANCE (YARD) 0 0050 LANDSCAPE MAINTENANCE (YARD) NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY SEVERO BASQUEZ JR. 0 0075 1004 LANDSCAPE MAINTENANCE MO 24.000 24.000 410.000 9,840.00 0080 1004 SHRUB PLANTING AND REMOVAL EA 16.000 0.000 25.000 .00 0085 1004 PLANT INSTALLATION CYC 9.000 9.000 180.000 1,620.00 0090 1004 FLOWER BED MAINTENANCE CYC 48.000 48.000 410.000 19,680.00 0095 1004 LEAF RAKING CYC 20.000 20.000 400.000 8,000.00 0100 1004 PRUNING AND TRIMMING TREES AND SHRUBS CYC 12.000 10.000 500.000 5,000.00 0105 1004 MULCHING CYC 4.000 4.000 400.000 1,600.00 0110 1004 FERTILIZATION CYC 4.000 4.000 185.000 740.00 0115 1004 PESTICIDE,FUNGICIDE,AND HERBICIDE CYC 2.000 2.000 400.000 800.00 0 SUBTOTAL BID ITEMS $ 47,280.00 0 TOTAL AMOUNT WORK DONE LANDSCAPE MAINTENANCE (YARD) $ 47,280.00 0 TOTAL AMOUNT WORK DONE CONTROL 6128-74-001 $ 47,280.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4051231 MGR.NO. 054 PAGE 001 CONT 6128 SEC 74 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ SUP - 612874001 HWY FM1959 702 FM1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 48,680.00 REPORT DATE 06/13/2013 13.59.06 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2005 TO MAY 31,2007 EST NO 025 & FINAL THE CENTER SERVING PERSONS WITH MENTAL RETARDATION 10036 0*********************************************************************************************************************************** -LIMITS - 702 FM1959 0 702 FM1959 DATE WORK BEGAN JUN 1 , 2005 WORKING DAYS USED 730 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED MAY 31 2007 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6128-74-001 SUP - 612874001 12 FM1959 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -1004 LANDSCAPE MAINTENANCE MO 24.000 24.000 410.000 9,840.00 1004 PLANT INSTALLATION CYC 9.000 9.000 180.000 1,620.00 1004 FLOWER BED MAINTENANCE CYC 48.000 48.000 410.000 19,680.00 1004 LEAF RAKING CYC 20.000 20.000 400.000 8,000.00 1004 PRUNING AND TRIMMING TREES AND SHRUBS CYC 12.000 10.000 500.000 5,000.00 1004 MULCHING CYC 4.000 4.000 400.000 1,600.00 1004 FERTILIZATION CYC 4.000 4.000 185.000 740.00 1004 PESTICIDE,FUNGICIDE,AND HERBICIDE CYC 2.000 2.000 400.000 800.00 0 SUBTOTAL BID ITEMS $ 47,280.00 0 CONTRACT TOTAL ALL ITEMS $ 47,280.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4051231 MGR.NO. 054 PAGE 001 CONT 6128 SEC 74 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ SUP - 612874001 HWY FM1959 702 FM1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 48,680.00 REPORT DATE 06/13/2013 13.59.06 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2005 TO MAY 31,2007 EST NO 025 & FINAL THE CENTER SERVING PERSONS WITH MENTAL RETARDATION 10036 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 SUP - 612874001 6128-74-001 47,280.00 .00 47,280.00 .00 .00 47,280.00 47,280.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 47,280.00 .00 47,280.00 .00 .00 47,280.00 47,280.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4051231 MGR.NO. 054 PAGE 001 CONT 6128 SEC 74 JOB 001 RES ENGR WAKELAND, MAUREEN PROJ SUP - 612874001 HWY FM1959 702 FM1959 HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 48,680.00 REPORT DATE 06/13/2013 13.59.06 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2005 TO MAY 31,2007 EST NO 025 & FINAL THE CENTER SERVING PERSONS WITH MENTAL RETARDATION 10036 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6128-74-001 SUP - 612874001 12 FM1959 HARRIS -LIMITS - 702 FM1959 702 FM1959 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 47,280.00