1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7130234 MGR.NO. 305 PAGE 001 CONT 6260 SEC 44 JOB 001 RES ENGR HAND, JAMES PROJ SUP - 626044001 HWY US0377 503 BIG BEND TRAIL GLEN R CNTY HOOD DIST 02 CONTRACT PRICE $ 78,897.75 REPORT DATE 11/04/2014 14.19.43 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD AUG 01,2014 TO AUG 31,2014 EST NO 014 & SUPPLM FRESH START OF MONROE INC. 15255 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 21, 2013 TIME COMPUTED FROM AUG 08, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 358 358 0 BROUGHT FORWARD ADDL DAYS GRANTED = 60 AUG 14 1 1 TOTAL DAYS ALLOWED = 425 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 389 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 570 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 570 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 389 389 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7130234 MGR.NO. 305 PAGE 001 CONT 6260 SEC 44 JOB 001 RES ENGR HAND, JAMES PROJ SUP - 626044001 HWY US0377 503 BIG BEND TRAIL GLEN R CNTY HOOD DIST 02 CONTRACT PRICE $ 78,897.75 REPORT DATE 11/04/2014 14.19.44 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD AUG 01,2014 TO AUG 31,2014 EST NO 014 & SUPPLM FRESH START OF MONROE INC. 15255 DIST. 02 COUNTY HOOD CONTROL 6260-44-001 PROJECT SUP - 626044001 HIGHWAY US0377 0LIMITS- VARIOUS ROADWAYS WITHIN HOOD, SOMERVELL & ERATH COUNTIES 0TYPE OF WORK- LITTER REMOVAL 0 0050 LITTER REMOVAL NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 VARIOUS ROADWAYS WITHIN HOOD, SOMERVELL & ERATH CO 0075 PREPARED BY DORA SOTO 0 0080 0734 LITTER REMOVAL(SPOT) AC 100.000 0.000 25.000 .00 0085 0734 LITTER REMOVAL - TRACT (1) AC 205.000 205.000 8.110 1,662.55 0090 0734 LITTER REMOVAL - TRACT (2) AC 148.000 148.000 17.470 2,585.56 0095 0734 LITTER REMOVAL - TRACT (3) AC 286.000 286.000 16.960 4,850.56 0100 0734 LITTER REMOVAL - TRACT (4) AC 46.000 69.000 14.560 1,004.64 0105 0734 LITTER REMOVAL - TRACT (5) AC 72.000 72.000 14.030 1,010.16 0110 0734 LITTER REMOVAL - TRACT (6) AC 435.000 435.000 13.590 5,911.65 0115 0734 LITTER REMOVAL - TRACT (7) AC 972.000 1,296.000 12.980 16,822.08 0120 0734 LITTER REMOVAL - TRACT (8) AC 360.000 360.000 16.220 5,839.20 0125 0734 LITTER REMOVAL - TRACT (9) AC 284.000 284.000 14.230 4,041.32 0130 0734 LITTER REMOVAL - TRACT (10) AC 120.000 140.000 16.220 2,270.80 0135 0734 LITTER REMOVAL - TRACT (11) AC 96.000 96.000 14.030 1,346.88 0140 0734 LITTER REMOVAL - TRACT (12) AC 738.000 738.000 14.560 10,745.28 0145 0734 LITTER REMOVAL - TRACT (13) AC 36.000 36.000 14.890 536.04 0150 0734 LITTER REMOVAL - TRACT (14) AC 72.000 78.000 14.890 1,161.42 0155 0734 LITTER REMOVAL - TRACT (15) AC 72.000 72.000 14.030 1,010.16 0160 0734 LITTER REMOVAL - TRACT (16) AC 314.000 314.000 13.990 4,392.86 0165 0734 LITTER REMOVAL - TRACT (17) AC 465.000 465.000 13.790 6,412.35 0170 0734 LITTER REMOVAL - TRACT (18) AC 236.000 295.000 16.490 4,864.55 0175 0734 LITTER REMOVAL - TRACT (19) AC 66.000 66.000 15.100 996.60 0180 0734 LITTER REMOVAL - TRACT (20) AC 196.000 196.000 13.140 2,575.44 0185 0734 LITTER REMOVAL - TRACT (21) AC 134.000 134.000 17.050 2,284.70 0 SUBTOTAL BID ITEMS $ 82,324.80 0 TOTAL AMOUNT WORK DONE LITTER REMOVAL $ 82,324.80 0 TOTAL AMOUNT WORK DONE CONTROL 6260-44-001 $ 82,324.80 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7130234 MGR.NO. 305 PAGE 001 CONT 6260 SEC 44 JOB 001 RES ENGR HAND, JAMES PROJ SUP - 626044001 HWY US0377 503 BIG BEND TRAIL GLEN R CNTY HOOD DIST 02 CONTRACT PRICE $ 78,897.75 REPORT DATE 11/04/2014 14.19.45 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD AUG 01,2014 TO AUG 31,2014 EST NO 014 & SUPPLM FRESH START OF MONROE INC. 15255 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS WITHIN 0 HOOD, SOMERVELL & ERATH COUNTIES DATE WORK BEGAN AUG 21, 2013 WORKING DAYS USED 389 PERCENT COMPLETE 99.99 PERCENT TIME USED 91.50 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6260-44-001 SUP - 626044001 02 US0377 HOOD - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) AC 205.000 205.000 8.110 1,662.55 0734 LITTER REMOVAL - TRACT (2) AC 148.000 148.000 17.470 2,585.56 0734 LITTER REMOVAL - TRACT (3) AC 286.000 286.000 16.960 4,850.56 0734 LITTER REMOVAL - TRACT (4) AC 46.000 69.000 14.560 1,004.64 0734 LITTER REMOVAL - TRACT (5) AC 72.000 72.000 14.030 1,010.16 0734 LITTER REMOVAL - TRACT (6) AC 435.000 435.000 13.590 5,911.65 0734 LITTER REMOVAL - TRACT (7) AC 972.000 1,296.000 12.980 16,822.08 0734 LITTER REMOVAL - TRACT (8) AC 360.000 360.000 16.220 5,839.20 0734 LITTER REMOVAL - TRACT (9) AC 284.000 284.000 14.230 4,041.32 0734 LITTER REMOVAL - TRACT (10) AC 120.000 140.000 16.220 2,270.80 0734 LITTER REMOVAL - TRACT (11) AC 96.000 96.000 14.030 1,346.88 0734 LITTER REMOVAL - TRACT (12) AC 738.000 738.000 14.560 10,745.28 0734 LITTER REMOVAL - TRACT (13) AC 36.000 36.000 14.890 536.04 0734 LITTER REMOVAL - TRACT (14) AC 72.000 78.000 14.890 1,161.42 0734 LITTER REMOVAL - TRACT (15) AC 72.000 72.000 14.030 1,010.16 0734 LITTER REMOVAL - TRACT (16) AC 314.000 314.000 13.990 4,392.86 0734 LITTER REMOVAL - TRACT (17) AC 465.000 465.000 13.790 6,412.35 0734 LITTER REMOVAL - TRACT (18) AC 236.000 295.000 16.490 4,864.55 0734 LITTER REMOVAL - TRACT (19) AC 66.000 66.000 15.100 996.60 0734 LITTER REMOVAL - TRACT (20) AC 196.000 196.000 13.140 2,575.44 0734 LITTER REMOVAL - TRACT (21) AC 134.000 134.000 17.050 2,284.70 0 SUBTOTAL BID ITEMS $ 82,324.80 0 CONTRACT TOTAL ALL ITEMS $ 82,324.80 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7130234 MGR.NO. 305 PAGE 001 CONT 6260 SEC 44 JOB 001 RES ENGR HAND, JAMES PROJ SUP - 626044001 HWY US0377 503 BIG BEND TRAIL GLEN R CNTY HOOD DIST 02 CONTRACT PRICE $ 78,897.75 REPORT DATE 11/04/2014 14.19.45 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD AUG 01,2014 TO AUG 31,2014 EST NO 014 & SUPPLM FRESH START OF MONROE INC. 15255 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 112 SUP - 626044001 6260-44-001 82,324.80 .00 82,324.80 .00 .00 82,324.80 82,324.80 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 82,324.80 .00 82,324.80 .00 .00 82,324.80 82,324.80 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7130234 MGR.NO. 305 PAGE 001 CONT 6260 SEC 44 JOB 001 RES ENGR HAND, JAMES PROJ SUP - 626044001 HWY US0377 503 BIG BEND TRAIL GLEN R CNTY HOOD DIST 02 CONTRACT PRICE $ 78,897.75 REPORT DATE 11/04/2014 14.19.45 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD AUG 01,2014 TO AUG 31,2014 EST NO 014 & SUPPLM FRESH START OF MONROE INC. 15255 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6260-44-001 SUP - 626044001 02 US0377 HOOD -LIMITS - VARIOUS ROADWAYS WITHIN HOOD, SOMERVELL & ERATH COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 82,324.80