1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8124004 MGR.NO. 305 PAGE 001 CONT 6244 SEC 28 JOB 001 RES ENGR HAND, JAMES PROJ RMC - 624428001 HWY US0377 2281 E. WASHINGTON STEPHE CNTY HOOD DIST 02 CONTRACT PRICE $ 351,790.00 REPORT DATE 11/20/2012 08.14.23 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD OCT 08,2012 TO OCT 15,2012 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 08, 2012 TIME COMPUTED FROM OCT 15, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 12 TOTAL DAYS ALLOWED = 30 DATE WORK COMPLETED 10/15/12 DAYS CHARGED TO DATE = 1 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 8 1 WORK ORDER 0 DAYS AT $ 590 PER DAY 9 1 TIME NOT STARTED TOTAL = $ .00 10 1 TIME NOT STARTED 11 1 TIME NOT STARTED CERTIFIED AS CORRECT AND 12 1 TIME NOT STARTED ONE COPY HAS BEEN GIVEN 13 1 SATURDAY TO THE CONTRACTOR 14 1 SUNDAY 15 1 ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 8 1 7 1 SATURDAY 1 SUNDAY 0 HOLIDAY 1 WORK ORDER 4 TIME NOT STARTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8124004 MGR.NO. 305 PAGE 001 CONT 6244 SEC 28 JOB 001 RES ENGR HAND, JAMES PROJ RMC - 624428001 HWY US0377 2281 E. WASHINGTON STEPHE CNTY HOOD DIST 02 CONTRACT PRICE $ 351,790.00 REPORT DATE 11/20/2012 08.14.23 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD OCT 08,2012 TO OCT 15,2012 EST NO 002 & FINAL DIST. 02 COUNTY HOOD CONTROL 6244-28-001 PROJECT RMC - 624428001 HIGHWAY US0377 0LIMITS- VARIOUS ROADWAYS WITHIN HOOD, SOMERVELL & ERATH COUNTIES 0TYPE OF WORK- FLEXIBLE PAVEMENT STRUCTURE REPAIR 0 0050 FLEXIBLE PAVEMENT STRUCTURE REPAIR NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 VARIOUS ROADWAYS WITHIN HOOD, SOMERVELL & ERATH CO 0075 PREPARED BY GLYNIS RODRIGUEZ 0 0080 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR TON 3,000.000 2,982.020 117.210 349,522.56 0085 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 1.000 10.000 160.000 1,600.00 0 SUBTOTAL BID ITEMS $ 351,122.56 0 TOTAL AMOUNT WORK DONE FLEXIBLE PAVEMENT STRUCTURE REPAIR $ 351,122.56 0 TOTAL AMOUNT WORK DONE CONTROL 6244-28-001 $ 351,122.56 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8124004 MGR.NO. 305 PAGE 001 CONT 6244 SEC 28 JOB 001 RES ENGR HAND, JAMES PROJ RMC - 624428001 HWY US0377 2281 E. WASHINGTON STEPHE CNTY HOOD DIST 02 CONTRACT PRICE $ 351,790.00 REPORT DATE 11/20/2012 08.14.24 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD OCT 08,2012 TO OCT 15,2012 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS WITHIN 0 HOOD, SOMERVELL & ERATH COUNTIES DATE WORK BEGAN OCT 8 , 2012 WORKING DAYS USED 1 PERCENT COMPLETE 100.00 PERCENT TIME USED 3.30 DATE COMPLETED OCT 15 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6244-28-001 RMC - 624428001 02 US0377 HOOD - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR TON 3,000.000 2,982.020 117.210 349,522.56 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 1.000 10.000 160.000 1,600.00 0 SUBTOTAL BID ITEMS $ 351,122.56 0 CONTRACT TOTAL ALL ITEMS $ 351,122.56 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8124004 MGR.NO. 305 PAGE 001 CONT 6244 SEC 28 JOB 001 RES ENGR HAND, JAMES PROJ RMC - 624428001 HWY US0377 2281 E. WASHINGTON STEPHE CNTY HOOD DIST 02 CONTRACT PRICE $ 351,790.00 REPORT DATE 11/20/2012 08.14.24 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD OCT 08,2012 TO OCT 15,2012 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 112 RMC - 624428001 6244-28-001 351,122.56 .00 351,122.56 .00 .00 351,122.56 351,122.56 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 351,122.56 .00 351,122.56 .00 .00 351,122.56 351,122.56 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8124004 MGR.NO. 305 PAGE 001 CONT 6244 SEC 28 JOB 001 RES ENGR HAND, JAMES PROJ RMC - 624428001 HWY US0377 2281 E. WASHINGTON STEPHE CNTY HOOD DIST 02 CONTRACT PRICE $ 351,790.00 REPORT DATE 11/20/2012 08.14.24 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD OCT 08,2012 TO OCT 15,2012 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6244-28-001 RMC - 624428001 02 US0377 HOOD -LIMITS - VARIOUS ROADWAYS WITHIN HOOD, SOMERVELL & ERATH COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 351,122.56