1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6124019 MGR.NO. 302 PAGE 001 CONT 6241 SEC 50 JOB 001 RES ENGR TOMPKINS, RICKY PROJ RMC - 624150001 HWY US0380 1710 W. US 380 DECATUR CNTY WISE DIST 02 CONTRACT PRICE $ 352,720.65 REPORT DATE 10/19/2012 15.13.37 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 06,2012 TO OCT 05,2012 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 06, 2012 TIME COMPUTED FROM AUG 13, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 24 56 14 42 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 12 1 1 AWAITING RETROFLECTIVITY DATA COLLECTIOTOTAL DAYS ALLOWED = 24 2 1 AWAITING RETROFLECTIVITY DATA COLLECTIODATE WORK COMPLETED 10/05/12 3 1 PERFORMED RETRO DATA COLLECTION DAYS CHARGED TO DATE = 14 4 1 PERFORMED RETRO DATA COLLECTION ASSESSED LIQ DAMAGES = 0 5 1 WORK COMPLETED AND ACCEPTED LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 0 DAYS AT $ 590 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 61 14 47 0 SATURDAY 0 SUNDAY 0 HOLIDAY 2 AWAITING RETROFLECTIVITY DATA COLLECTION 2 PERFORMED RETRO DATA COLLECTION 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6124019 MGR.NO. 302 PAGE 001 CONT 6241 SEC 50 JOB 001 RES ENGR TOMPKINS, RICKY PROJ RMC - 624150001 HWY US0380 1710 W. US 380 DECATUR CNTY WISE DIST 02 CONTRACT PRICE $ 352,720.65 REPORT DATE 10/19/2012 15.13.38 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 06,2012 TO OCT 05,2012 EST NO 003 & FINAL DIST. 02 COUNTY WISE CONTROL 6241-50-001 PROJECT RMC - 624150001 HIGHWAY US0380 0LIMITS- VARIOUS ROADWAYS WITHIN WISE & JACK COUNTY 0TYPE OF WORK- REFLECTORIZED PAVEMENT MARKINGS 0 0050 REFLECTORIZED PAVEMENT MARKINGS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 VARIOUS ROADWAYS WITHIN WISE & JACK OUNTY 0075 PREPARED BY GLYNIS RODRIGUEZ 0 0080 0500 MOBILIZATION LS 1.000 1.000 2,500.000 2,500.00 0085 0666 REFL PAV MRK TY I (W) 8" (BRK)(060MIL) LF 575.000 523.000 1.000 523.00 0090 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 36,830.000 34,942.000 .500 17,471.00 0095 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 182.000 188.000 12.500 2,350.00 0100 0668 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 729.000 625.000 26.750 16,718.75 0105 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 8,798.000 8,209.000 .500 4,104.50 0110 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 292.000 279.000 .500 139.50 0115 0677 ELIM EXT PAV MRK & MRKS (24") LF 1,216.000 899.000 .950 854.05 0120 8251 RE PM W/RET REQ TY I(W)4"(BRK)(060MIL) LF 43,714.000 48,170.000 .200 9,634.00 0125 8251 RE PM W/RET REQ TY I(W)4"(SLD)(060MIL) LF 789,386.000 666,166.000 .200 133,233.20 0130 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(060MIL) LF 51,623.000 37,870.000 .200 7,574.00 0135 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(060MIL) LF 596,652.000 516,932.000 .200 103,386.40 0140 6153 MLTPLY PV MK W/ WTY (W)(4")(SLD) LF 3,244.000 3,279.000 .650 2,131.35 0145 6153 MLTPLY PV MK W/ WTY (W)(4")(BRK) LF 810.000 830.000 .750 622.50 0150 6153 MLTPLY PV MK W/ WTY 1 (W)(8")(SLD) LF 265.000 279.000 2.000 558.00 0155 6153 MLTPLY PV MK W/ WTY (Y)(4")(SLD) LF 3,244.000 3,600.000 .650 2,340.00 0160 6153 MLTPLY PV MK W/ WTY (Y)(4")(BRK) LF 700.000 500.000 .750 375.00 0165 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 4.000 4.000 400.000 1,600.00 0 SUBTOTAL BID ITEMS $ 306,115.25 0 TOTAL AMOUNT WORK DONE REFLECTORIZED PAVEMENT MARKINGS $ 306,115.25 0 TOTAL AMOUNT WORK DONE CONTROL 6241-50-001 $ 306,115.25 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6124019 MGR.NO. 302 PAGE 001 CONT 6241 SEC 50 JOB 001 RES ENGR TOMPKINS, RICKY PROJ RMC - 624150001 HWY US0380 1710 W. US 380 DECATUR CNTY WISE DIST 02 CONTRACT PRICE $ 352,720.65 REPORT DATE 10/19/2012 15.13.38 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 06,2012 TO OCT 05,2012 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS WITHIN 0 WISE & JACK COUNTY DATE WORK BEGAN AUG 6 , 2012 WORKING DAYS USED 14 PERCENT COMPLETE 100.00 PERCENT TIME USED 58.30 DATE COMPLETED OCT 5 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6241-50-001 RMC - 624150001 02 US0380 WISE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 2,500.000 2,500.00 0666 REFL PAV MRK TY I (W) 8" (BRK)(060MIL) LF 575.000 523.000 1.000 523.00 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 36,830.000 34,942.000 .500 17,471.00 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 182.000 188.000 12.500 2,350.00 0668 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 729.000 625.000 26.750 16,718.75 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 8,798.000 8,209.000 .500 4,104.50 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 292.000 279.000 .500 139.50 0677 ELIM EXT PAV MRK & MRKS (24") LF 1,216.000 899.000 .950 854.05 6153 MLTPLY PV MK W/ WTY (W)(4")(SLD) LF 3,244.000 3,279.000 .650 2,131.35 6153 MLTPLY PV MK W/ WTY (W)(4")(BRK) LF 810.000 830.000 .750 622.50 6153 MLTPLY PV MK W/ WTY (W)(8")(SLD) LF 265.000 279.000 2.000 558.00 6153 MLTPLY PV MK W/ WTY (Y)(4")(SLD) LF 3,244.000 3,600.000 .650 2,340.00 6153 MLTPLY PV MK W/ WTY (Y)(4")(BRK) LF 700.000 500.000 .750 375.00 16834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 4.000 4.000 400.000 1,600.00 8251 RE PM W/RET REQ TY I(W)4"(BRK)(060MIL) LF 43,714.000 48,170.000 .200 9,634.00 8251 RE PM W/RET REQ TY I(W)4"(SLD)(060MIL) LF 789,386.000 666,166.000 .200 133,233.20 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(060MIL) LF 51,623.000 37,870.000 .200 7,574.00 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(060MIL) LF 596,652.000 516,932.000 .200 103,386.40 0 SUBTOTAL BID ITEMS $ 306,115.25 0 CONTRACT TOTAL ALL ITEMS $ 306,115.25 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6124019 MGR.NO. 302 PAGE 001 CONT 6241 SEC 50 JOB 001 RES ENGR TOMPKINS, RICKY PROJ RMC - 624150001 HWY US0380 1710 W. US 380 DECATUR CNTY WISE DIST 02 CONTRACT PRICE $ 352,720.65 REPORT DATE 10/19/2012 15.13.38 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 06,2012 TO OCT 05,2012 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 249 RMC - 624150001 6241-50-001 306,115.25 .00 306,115.25 .00 .00 306,115.25 247,826.95 58,288.30 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 306,115.25 .00 306,115.25 .00 .00 306,115.25 247,826.95 58,288.30 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6124019 MGR.NO. 302 PAGE 001 CONT 6241 SEC 50 JOB 001 RES ENGR TOMPKINS, RICKY PROJ RMC - 624150001 HWY US0380 1710 W. US 380 DECATUR CNTY WISE DIST 02 CONTRACT PRICE $ 352,720.65 REPORT DATE 10/19/2012 15.13.38 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 06,2012 TO OCT 05,2012 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6241-50-001 RMC - 624150001 02 US0380 WISE -LIMITS - VARIOUS ROADWAYS WITHIN WISE & JACK COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 80 0500 MOBILIZATION LS 1.000 0.100 2,500.000 250.00 90 0666 REFL PAV MRK TY I (W) 8" LF 36,830.000 425.000 0.500 212.50 (SLD)(060MIL) 125 8251 RE PM W/RET REQ TY LF 789,386.000 143,050.000 0.200 28,610.00 I(W)4"(SLD)(060MIL) 130 8251 RE PM W/RET REQ TY LF 51,623.000 17,970.000 0.200 3,594.00 I(Y)4"(BRK)(060MIL) 135 8251 RE PM W/RET REQ TY LF 596,652.000 128,109.000 0.200 25,621.80 I(Y)4"(SLD)(060MIL) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 58,288.30 0 TOTAL AMOUNT WORK DONE TO DATE - $ 306,115.25