1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7124001 MGR.NO. 310 PAGE 001 CONT 6234 SEC 43 JOB 001 RES ENGR PHILLIPS, GARY PROJ RMC - 623443001 HWY IH0820 508 BLUE MOUND RD. SAGINA CNTY TARRANT DIST 02 CONTRACT PRICE $ 445,745.23 REPORT DATE 12/20/2012 17.10.33 CONTRACTOR TRP CONSTRUCTION GROUP, LLC 15053 EST PERIOD OCT 09,2012 TO NOV 26,2012 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 10, 2012 TIME COMPUTED FROM OCT 09, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 25 23 18 5 BROUGHT FORWARD ADDL DAYS GRANTED = 2 NOV 12 1 1 TOTAL DAYS ALLOWED = 27 2 1 NOT A SCHEDULED WORK DAY DATE WORK COMPLETED 11/26/12 3 1 SATURDAY DAYS CHARGED TO DATE = 27 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 7 1 WORK DELAYED DUE TO CONSTRUCTION CONFLI LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 NOT A SCHEDULED WORK DAY TOTAL = $ .00 10 1 SATURDAY 11 1 TOO WINDY AND DUSTY CERTIFIED AS CORRECT AND 12 1 TOO COLD ONE COPY HAS BEEN GIVEN 13 1 TOO COLD TO THE CONTRACTOR 14 1 15 1 16 1 NOT A SCHEDULED WORK DAY ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 20 1 TOO WET 21 1 HOLIDAY 22 1 HOLIDAY 23 1 HOLIDAY 24 1 SATURDAY 25 1 SUNDAY 26 1 TOO WET - - ----- ----- ----- 49 27 22 3 SATURDAY 2 SUNDAY 3 HOLIDAY 3 NOT A SCHEDULED WORK DAY 1 WORK DELAYED DUE TO CONSTRUCTION CONFLIC 1 TOO WINDY AND DUSTY 2 TOO COLD 2 TOO WET 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7124001 MGR.NO. 310 PAGE 001 CONT 6234 SEC 43 JOB 001 RES ENGR PHILLIPS, GARY PROJ RMC - 623443001 HWY IH0820 508 BLUE MOUND RD. SAGINA CNTY TARRANT DIST 02 CONTRACT PRICE $ 445,745.23 REPORT DATE 12/20/2012 17.10.33 CONTRACTOR TRP CONSTRUCTION GROUP, LLC 15053 EST PERIOD OCT 09,2012 TO NOV 26,2012 EST NO 002 & FINAL DIST. 02 COUNTY TARRANT CONTROL 6234-43-001 PROJECT RMC - 623443001 HIGHWAY IH0820 0LIMITS- VARIOUS ROADWAYS WITHIN NORTH TARRANT COUNTY 0TYPE OF WORK- REFLECTORIZED PAVEMENT MARKINGS 0 0050 REFLECTORIZED PAVEMENT MARKINGS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 VARIOUS ROADWAYS WITHIN NORTH TARRANT COUNTY 0075 PREPARED BY GLYNIS RODRIGUEZ 0 0080 0500 MOBILIZATION LS 1.000 1.000 13,400.000 13,400.00 0085 0666 REFL PAV MRK TY I (W) 6" (BRK)(090MIL) LF 151,250.000 147,861.000 .400 59,144.40 0090 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 130,185.000 111,291.000 .470 52,306.77 0095 0666 REFL PAV MRK TY I (W) 8" (SLD)(090MIL) LF 2,530.000 2,973.000 .800 2,378.40 0100 0666 REFL PAV MRK TY I (Y) 8" (SLD)(090MIL) LF 2,860.000 1,199.000 .810 971.19 0105 0666 PAVEMENT SEALER 8" LF 2,530.000 4,172.000 .500 2,086.00 0110 0666 REF PAV MRK TY I (BLACK)6"(BRK)(090MIL) LF 90,420.000 105,580.000 .450 47,511.00 0115 0668 PREFAB PAV MRK TY C (W) (12") (SLD) LF 300.000 321.000 5.000 1,605.00 0120 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 300.000 485.000 9.000 4,365.00 0125 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 8.000 9.000 175.000 1,575.00 0130 0668 PREFAB PAV MRK TY C (W) (RR XING) EA 2.000 2.000 600.000 1,200.00 0135 0668 PREFAB PAV MRK TY C (W) (WORD) EA 8.000 9.000 260.000 2,340.00 0140 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 185,468.000 38,063.000 .160 6,090.08 0145 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 3,630.000 2,981.000 .480 1,430.88 0150 0677 ELIM EXT PAV MRK & MRKS (12") LF 100.000 277.000 2.000 554.00 1 0155 0677 ELIM EXT PAV MRK & MRKS (24") LF 100.000 0.000 2.000 .00 0160 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 20.000 27.000 50.000 1,350.00 0165 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 18.000 23.000 55.000 1,265.00 0170 8251 RE PM W/RET REQ TY I(W)4"(BRK)(060MIL) LF 39,215.000 45,100.000 .260 11,726.00 0175 8251 RE PM W/RET REQ TY I(W)4"(BRK)(090MIL) LF 22,220.000 9,190.000 .330 3,032.70 0180 8251 RE PM W/RET REQ TY I(W)4"(SLD)(060MIL) LF 426,415.000 385,738.000 .200 77,147.60 0185 8251 RE PM W/RET REQ TY I(W)4"(SLD)(090MIL) LF 44,440.000 29,364.000 .270 7,928.28 0190 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(060MIL) LF 427,955.000 411,010.000 .200 82,202.00 0195 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(090MIL) LF 1,650.000 0.000 1.000 .00 0200 8251 PAVEMENT SEALER 4" LF 68,310.000 9,190.000 .080 735.20 0205 8251 PAVEMENT SEALER 6" LF 140,670.000 99,904.000 .090 8,991.36 0210 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 10.000 0.000 150.000 .00 0215 9001*OFF DUTY OFFICER LS 1.000 1.000 5,509.350 5,509.35 0220 9001*OFF DUTY OFFICERS LS 1.000 1.000 3,219.730 3,219.73 0 SUBTOTAL BID ITEMS $ 400,064.94 0 TOTAL AMOUNT WORK DONE REFLECTORIZED PAVEMENT MARKINGS $ 400,064.94 0 TOTAL AMOUNT WORK DONE CONTROL 6234-43-001 $ 400,064.94 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7124001 MGR.NO. 310 PAGE 001 CONT 6234 SEC 43 JOB 001 RES ENGR PHILLIPS, GARY PROJ RMC - 623443001 HWY IH0820 508 BLUE MOUND RD. SAGINA CNTY TARRANT DIST 02 CONTRACT PRICE $ 445,745.23 REPORT DATE 12/20/2012 17.10.33 CONTRACTOR TRP CONSTRUCTION GROUP, LLC 15053 EST PERIOD OCT 09,2012 TO NOV 26,2012 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS WITHIN 0 NORTH TARRANT COUNTY DATE WORK BEGAN OCT 10, 2012 WORKING DAYS USED 27 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED NOV 26 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6234-43-001 RMC - 623443001 02 IH0820 TARRANT - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 13,400.000 13,400.00 0666 REFL PAV MRK TY I (W) 6" (BRK)(090MIL) LF 151,250.000 147,861.000 .400 59,144.40 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 130,185.000 111,291.000 .470 52,306.77 0666 REFL PAV MRK TY I (W) 8" (SLD)(090MIL) LF 2,530.000 2,973.000 .800 2,378.40 0666 REFL PAV MRK TY I (Y) 8" (SLD)(090MIL) LF 2,860.000 1,199.000 .810 971.19 0666 PAVEMENT SEALER 8" LF 2,530.000 4,172.000 .500 2,086.00 0666 REF PAV MRK TY I (BLACK)6"(BRK)(090MIL) LF 90,420.000 105,580.000 .450 47,511.00 0668 PREFAB PAV MRK TY C (W) (12") (SLD) LF 300.000 321.000 5.000 1,605.00 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 300.000 485.000 9.000 4,365.00 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 8.000 9.000 175.000 1,575.00 0668 PREFAB PAV MRK TY C (W) (RR XING) EA 2.000 2.000 600.000 1,200.00 0668 PREFAB PAV MRK TY C (W) (WORD) EA 8.000 9.000 260.000 2,340.00 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 185,468.000 38,063.000 .160 6,090.08 0677 ELIM EXT PAV MRK & MRKS ( 1 8") LF 3,630.000 2,981.000 .480 1,430.88 0677 ELIM EXT PAV MRK & MRKS (12") LF 100.000 277.000 2.000 554.00 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 20.000 27.000 50.000 1,350.00 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 18.000 23.000 55.000 1,265.00 8251 RE PM W/RET REQ TY I(W)4"(BRK)(060MIL) LF 39,215.000 45,100.000 .260 11,726.00 8251 RE PM W/RET REQ TY I(W)4"(BRK)(090MIL) LF 22,220.000 9,190.000 .330 3,032.70 8251 RE PM W/RET REQ TY I(W)4"(SLD)(060MIL) LF 426,415.000 385,738.000 .200 77,147.60 8251 RE PM W/RET REQ TY I(W)4"(SLD)(090MIL) LF 44,440.000 29,364.000 .270 7,928.28 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(060MIL) LF 427,955.000 411,010.000 .200 82,202.00 8251 PAVEMENT SEALER 4" LF 68,310.000 9,190.000 .080 735.20 8251 PAVEMENT SEALER 6" LF 140,670.000 99,904.000 .090 8,991.36 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* OFF DUTY OFFICER LS 1.000 1.000 5,509.350 5,509.35 9001* OFF DUTY OFFICERS LS 1.000 1.000 3,219.730 3,219.73 0 SUBTOTAL BID ITEMS $ 400,064.94 0 CONTRACT TOTAL ALL ITEMS $ 400,064.94 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7124001 MGR.NO. 310 PAGE 001 CONT 6234 SEC 43 JOB 001 RES ENGR PHILLIPS, GARY PROJ RMC - 623443001 HWY IH0820 508 BLUE MOUND RD. SAGINA CNTY TARRANT DIST 02 CONTRACT PRICE $ 445,745.23 REPORT DATE 12/20/2012 17.10.33 CONTRACTOR TRP CONSTRUCTION GROUP, LLC 15053 EST PERIOD OCT 09,2012 TO NOV 26,2012 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 220 RMC - 623443001 6234-43-001 400,064.94 .00 400,064.94 .00 .00 400,064.94 216,415.89 183,649.05 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 400,064.94 .00 400,064.94 .00 .00 400,064.94 216,415.89 183,649.05 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7124001 MGR.NO. 310 PAGE 001 CONT 6234 SEC 43 JOB 001 RES ENGR PHILLIPS, GARY PROJ RMC - 623443001 HWY IH0820 508 BLUE MOUND RD. SAGINA CNTY TARRANT DIST 02 CONTRACT PRICE $ 445,745.23 REPORT DATE 12/20/2012 17.10.33 CONTRACTOR TRP CONSTRUCTION GROUP, LLC 15053 EST PERIOD OCT 09,2012 TO NOV 26,2012 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6234-43-001 RMC - 623443001 02 IH0820 TARRANT -LIMITS - VARIOUS ROADWAYS WITHIN NORTH TARRANT COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 80 0500 MOBILIZATION LS 1.000 0.100 13,400.000 1,340.00 85 0666 REFL PAV MRK TY I (W) 6" LF 151,250.000 66,690.000 0.400 26,676.00 (BRK)(090MIL) 90 0666 REFL PAV MRK TY I (W) 8" LF 130,185.000 45,482.000 0.470 21,376.54 (SLD)(060MIL) 110 0666 REF PAV MRK TY I LF 90,420.000 55,640.000 0.450 25,038.00 (BLACK)6"(BRK)(090MIL) 115 0668 PREFAB PAV MRK TY C (W) LF 300.000 261.000 5.000 1,305.00 (12") (SLD) 120 0668 PREFAB PAV MRK TY C (W) LF 300.000 377.000 9.000 3,393.00 (24") (SLD) 170 8251 RE PM W/RET REQ TY LF 39,215.000 32,820.000 0.260 8,533.20 I(W)4"(BRK)(060MIL) 180 8251 RE PM W/RET REQ TY LF 426,415.000 212,701.000 0.200 42,540.20 I(W)4"(SLD)(060MIL) 185 8251 RE PM W/RET REQ TY LF 44,440.000 29,364.000 0.270 7,928.28 I(W)4"(SLD)(090MIL) 190 8251 RE PM W/RET REQ TY LF 427,955.000 189,063.000 0.200 37,812.60 I(Y)4"(SLD)(060MIL) 205 8251 PAVEMENT SEALER 6" LF 140,670.000 49,850.000 0.090 4,486.50 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 220 9001* OFF DUTY OFFICERS LS 0.000 1.000 3,219.730 3,219.73 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 183,649.05 0 TOTAL AMOUNT WORK DONE TO DATE - $ 400,064.94