1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10110202 MGR.NO. 054 PAGE 001 CONT 6230 SEC 95 JOB 001 RES ENGR CEDILLO P.E., GREG PROJ RMC - 623095001 HWY IH0020 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 38,762.72 REPORT DATE 06/29/2012 17.15.46 CONTRACTOR MHB CONSTRUCTION, INC. 14869 EST PERIOD APR 21,2012 TO MAY 10,2012 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 21, 2012 TIME COMPUTED FROM APR 28, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 34 10 1 9 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAY 12 1 1 TOTAL DAYS ALLOWED = 34 2 1 DATE WORK COMPLETED 05/10/12 3 1 DAYS CHARGED TO DATE = 9 4 1 ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 570 6 1 SUNDAY 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 570 PER DAY 9 1 TOTAL = $ .00 10 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 20 9 11 1 SATURDAY 1 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10110202 MGR.NO. 054 PAGE 001 CONT 6230 SEC 95 JOB 001 RES ENGR CEDILLO P.E., GREG PROJ RMC - 623095001 HWY IH0020 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 38,762.72 REPORT DATE 06/29/2012 17.15.46 CONTRACTOR MHB CONSTRUCTION, INC. 14869 EST PERIOD APR 21,2012 TO MAY 10,2012 EST NO 003 & FINAL DIST. 02 COUNTY TARRANT CONTROL 6230-95-001 PROJECT RMC - 623095001 HIGHWAY IH0020 0LIMITS- IH 20 @ GRANBURY WB SERVICE ROAD IN FORT WORTH 0TYPE OF WORK- DRAINAGE IMPROVEMENT 0 0050 DRAINAGE IMPROVEMENT NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 DRAINAGE IMPROVEMENT IH 20 @ GRANBURY WB SRV RD 0075 PREPARED BY: JANET DAVIS 0 0080 0104 REMOVING CONC (PAV) SY 20.000 19.230 45.000 865.35 0085 0104 REMOVING CONC (CURB) LF 55.000 5.000 10.000 50.00 0090 0105 REMOVING STAB BASE & ASPH PAV (8"-10") SY 25.000 15.310 100.000 1,531.00 0095 0247 FL BS (CMP IN PLC)(TY A GR 4)(FNAL POS) CY 6.000 0.000 54.000 .00 0100 0305 SALV, HAUL & STKPL RCL APH PV (4 TO 6") SY 23.000 15.310 1.000 15.31 0105 0340 D-GR HMA(METH) TY-B PG64-22 TON 17.000 3.000 110.000 330.00 0110 0360 CONC PVMT (CONT REINF-CRCP)(HES)(8") SY 24.000 19.230 140.000 2,692.20 0130 0401 FLOWABLE BACKFILL CY 2.000 2.000 188.000 376.00 0135 0402 TRENCH EXCAVATION PROTECTION LF 50.000 23.000 10.000 230.00 0140 0481 PVC PIPE (SCH 80)(4 IN) LF 100.000 90.000 50.000 4,500.00 0145 0500 MOBILIZATION LS 1.000 1.000 10,000.000 10,000.00 0150 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 3,800.000 7,600.00 0155 0512 PORT CTB (DES SOURCE)(LOW PROF)(TY 1) LF 100.000 100.000 9.400 940.00 0160 0512 PORT CTB (DES SOURCE)(LOW PROF)(TY 2) LF 20.000 20.000 11.400 228.00 0165 0512 PORT CTB (MOVE)(LOW PROF)(TY 1) LF 100.000 100.000 8.000 800.00 0170 0512 PORT CTB (MOVE)(LOW PROF)(TY 2) LF 20.000 20.000 6.500 130.00 0175 0512 PORT CTB (STKPL)(LOW PROF)(TY 1) LF 100.000 100.000 7.250 725.00 0180 0512 PORT CTB (STKPL)(LOW 1 PROF)(TY 2) LF 20.000 20.000 9.500 190.00 0185 0529 CONC CURB (MONO) (TY II) LF 55.000 5.000 3.000 15.00 0190 0531 CONC SIDEWALKS (4") SY 40.000 29.800 36.000 1,072.80 0195 0662 WK ZN PAV MRK REMOV (W) 4" (BRK) LF 136.000 0.000 .080 .00 0200 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 20.000 100.000 .050 5.00 0205 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 58.000 400.000 .380 152.00 0210 0666 REFL PAV MRK TY I (Y) 8" (SLD)(100MIL) LF 260.000 286.000 .500 143.00 0215 0666 REFL PAV MRK TY I (Y) 24"(SLD)(100MIL) LF 182.000 201.000 .500 100.50 0220 0666 REF PAV MRK TY II (W) 4" (BRK) LF 20.000 100.000 2.350 235.00 0225 0666 REF PAV MRK TY II (W) 4" (SLD) LF 58.000 400.000 3.500 1,400.00 0230 0666 REF PAV MRK TY II (Y) 8" (SLD) LF 260.000 286.000 .180 51.48 0235 0666 REF PAV MRK TY II (Y) 24" (SLD) LF 182.000 201.000 2.000 402.00 0240 0672 REFL PAV MRKR TY II-A-A EA 14.000 14.000 3.000 42.00 0245 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 200.000 0.000 .500 .00 0250 0677 ELIM EXT PAV MRK & MRKS (12") LF 140.000 0.000 .600 .00 0260 0677*ELIM EXT PAV MRK & MRKS ( 8") LF 288.000 288.000 5.130 1,477.44 0265 0677*ELIM EXT PAV MRK & MRKS (24") LF 196.000 196.000 6.230 1,221.08 0 SUBTOTAL BID ITEMS $ 37,520.16 0 TOTAL AMOUNT WORK DONE DRAINAGE IMPROVEMENT $ 37,520.16 0 TOTAL AMOUNT WORK DONE CONTROL 6230-95-001 $ 37,520.16 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10110202 MGR.NO. 054 PAGE 001 CONT 6230 SEC 95 JOB 001 RES ENGR CEDILLO P.E., GREG PROJ RMC - 623095001 HWY IH0020 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 38,762.72 REPORT DATE 06/29/2012 17.15.46 CONTRACTOR MHB CONSTRUCTION, INC. 14869 EST PERIOD APR 21,2012 TO MAY 10,2012 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - IH 20 @ GRANBURY WB SERVICE ROAD 0 IN FORT WORTH DATE WORK BEGAN APR 21, 2012 WORKING DAYS USED 9 PERCENT COMPLETE 100.00 PERCENT TIME USED 26.40 DATE COMPLETED MAY 10 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6230-95-001 RMC - 623095001 02 IH0020 TARRANT - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0104 REMOVING CONC (PAV) SY 20.000 19.230 45.000 865.35 0104 REMOVING CONC (CURB) LF 55.000 5.000 10.000 50.00 0105 REMOVING STAB BASE & ASPH PAV (8"-10") SY 25.000 15.310 100.000 1,531.00 0305 SALV, HAUL & STKPL RCL APH PV (4 TO 6") SY 23.000 15.310 1.000 15.31 0340 D-GR HMA(METH) TY-B PG64-22 TON 17.000 3.000 110.000 330.00 0360 CONC PVMT (CONT REINF-CRCP)(HES)(8") SY 24.000 19.230 140.000 2,692.20 0401 FLOWABLE BACKFILL CY 2.000 2.000 188.000 376.00 0402 TRENCH EXCAVATION PROTECTION LF 50.000 23.000 10.000 230.00 0481 PVC PIPE (SCH 80)(4 IN) LF 100.000 90.000 50.000 4,500.00 0500 MOBILIZATION LS 1.000 1.000 10,000.000 10,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 3,800.000 7,600.00 0512 PORT CTB (DES SOURCE)(LOW PROF)(TY 1) LF 100.000 100.000 9.400 940.00 0512 PORT CTB (DES SOURCE)(LOW PROF)(TY 2) LF 20.000 20.000 11.400 228.00 0512 PORT CTB (MOVE)(LOW PROF)(TY 1) LF 100.000 100.000 8.000 800.00 0512 PORT CTB (MOVE)(LOW PROF)(TY 2) LF 20.000 20.000 6.500 130.00 0512 PORT CTB (STKPL)(LOW PROF)(TY 1) LF 100.000 100.000 7.250 725.00 10512 PORT CTB (STKPL)(LOW PROF)(TY 2) LF 20.000 20.000 9.500 190.00 0529 CONC CURB (MONO) (TY II) LF 55.000 5.000 3.000 15.00 0531 CONC SIDEWALKS (4") SY 40.000 29.800 36.000 1,072.80 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 20.000 100.000 .050 5.00 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 58.000 400.000 .380 152.00 0666 REFL PAV MRK TY I (Y) 8" (SLD)(100MIL) LF 260.000 286.000 .500 143.00 0666 REFL PAV MRK TY I (Y) 24"(SLD)(100MIL) LF 182.000 201.000 .500 100.50 0666 REF PAV MRK TY II (W) 4" (BRK) LF 20.000 100.000 2.350 235.00 0666 REF PAV MRK TY II (W) 4" (SLD) LF 58.000 400.000 3.500 1,400.00 0666 REF PAV MRK TY II (Y) 8" (SLD) LF 260.000 286.000 .180 51.48 0666 REF PAV MRK TY II (Y) 24" (SLD) LF 182.000 201.000 2.000 402.00 0672 REFL PAV MRKR TY II-A-A EA 14.000 14.000 3.000 42.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00677* ELIM EXT PAV MRK & MRKS ( 8") LF 288.000 288.000 5.130 1,477.44 0677* ELIM EXT PAV MRK & MRKS (24") LF 196.000 196.000 6.230 1,221.08 0 SUBTOTAL BID ITEMS $ 37,520.16 0 CONTRACT TOTAL ALL ITEMS $ 37,520.16 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10110202 MGR.NO. 054 PAGE 001 CONT 6230 SEC 95 JOB 001 RES ENGR CEDILLO P.E., GREG PROJ RMC - 623095001 HWY IH0020 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 38,762.72 REPORT DATE 06/29/2012 17.15.46 CONTRACTOR MHB CONSTRUCTION, INC. 14869 EST PERIOD APR 21,2012 TO MAY 10,2012 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 220 RMC - 623095001 6230-95-001 37,520.16 .00 37,520.16 .00 .00 37,520.16 34,821.64 2,698.52 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 37,520.16 .00 37,520.16 .00 .00 37,520.16 34,821.64 2,698.52 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10110202 MGR.NO. 054 PAGE 001 CONT 6230 SEC 95 JOB 001 RES ENGR CEDILLO P.E., GREG PROJ RMC - 623095001 HWY IH0020 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 38,762.72 REPORT DATE 06/29/2012 17.15.47 CONTRACTOR MHB CONSTRUCTION, INC. 14869 EST PERIOD APR 21,2012 TO MAY 10,2012 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6230-95-001 RMC - 623095001 02 IH0020 TARRANT -LIMITS - IH 20 @ GRANBURY WB SERVICE ROAD IN FORT WORTH LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) - * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 260 0677* ELIM EXT PAV MRK & MRKS ( LF 0.000 288.000 5.130 1,477.44 8") 265 0677* ELIM EXT PAV MRK & MRKS LF 0.000 196.000 6.230 1,221.08 (24") 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 2,698.52 0 TOTAL AMOUNT WORK DONE TO DATE - $ 37,520.16