1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11110209 MGR.NO. 309 PAGE 001 CONT 6228 SEC 96 JOB 001 RES ENGR JONES, SCOTT PROJ RMC - 622896001 HWY US0281 1429 W. BANKHEAD HWY WEAT CNTY PALO PINTO DIST 02 CONTRACT PRICE $ 311,208.72 REPORT DATE 02/06/2014 10.26.11 CONTRACTOR LONESTAR HAWK, INC. 13911 EST PERIOD JUL 02,2012 TO JAN 18,2014 EST NO 015 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 02, 2012 TIME COMPUTED FROM JUL 09, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 92 426 45 381 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 14 1 1 NO CURRENT WORK ORDER TOTAL DAYS ALLOWED = 92 2 1 NO CURRENT WORK ORDER DATE WORK COMPLETED 01/18/14 3 1 NO CURRENT WORK ORDER DAYS CHARGED TO DATE = 48 4 1 NO CURRENT WORK ORDER ASSESSED LIQ DAMAGES = 0 5 1 NO CURRENT WORK ORDER LIQ DAMAGE RATE $ 590 6 1 NO CURRENT WORK ORDER 7 1 NO CURRENT WORK ORDER LIQUIDATED DAMAGES 8 1 TIME NOT STARTED 0 DAYS AT $ 590 PER DAY 9 1 TIME NOT STARTED TOTAL = $ .00 10 1 TIME NOT STARTED 11 1 TIME NOT STARTED CERTIFIED AS CORRECT AND 12 1 TIME NOT STARTED ONE COPY HAS BEEN GIVEN 13 1 TIME NOT STARTED TO THE CONTRACTOR 14 1 TIME NOT STARTED 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 SATURDAY - - - - 0 ----- ----- ----- 444 48 396 1 SATURDAY 0 SUNDAY 0 HOLIDAY 7 NO CURRENT WORK ORDER 7 TIME NOT STARTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11110209 MGR.NO. 309 PAGE 001 CONT 6228 SEC 96 JOB 001 RES ENGR JONES, SCOTT PROJ RMC - 622896001 HWY US0281 1429 W. BANKHEAD HWY WEAT CNTY PALO PINTO DIST 02 CONTRACT PRICE $ 311,208.72 REPORT DATE 02/06/2014 10.26.12 CONTRACTOR LONESTAR HAWK, INC. 13911 EST PERIOD JUL 02,2012 TO JAN 18,2014 EST NO 015 & FINAL DIST. 02 COUNTY PALO PINTO CONTROL 6228-96-001 PROJECT RMC - 622896001 HIGHWAY US0281 0LIMITS- VARIOUS ROADWAYS WITHIN PALO PINTO COUNTY 0TYPE OF WORK- ROADSIDE MOWING 0 0050 ROADSIDE MOWING NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 VARIOUS ROADWAYS WITHIN PALO PINTO COUNTY 0075 PREPARED BY GLYNIS RODRIGUEZ 0 0080 0730 FULL-WIDTH MOWING AC 13,528.000 13,528.000 22.990 311,008.72 0085 0730 SPOT MOWING AC 200.000 0.000 1.000 .00 0 SUBTOTAL BID ITEMS $ 311,008.72 0 TOTAL AMOUNT WORK DONE ROADSIDE MOWING $ 311,008.72 0 TOTAL AMOUNT WORK DONE CONTROL 6228-96-001 $ 311,008.72 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11110209 MGR.NO. 309 PAGE 001 CONT 6228 SEC 96 JOB 001 RES ENGR JONES, SCOTT PROJ RMC - 622896001 HWY US0281 1429 W. BANKHEAD HWY WEAT CNTY PALO PINTO DIST 02 CONTRACT PRICE $ 311,208.72 REPORT DATE 02/06/2014 10.26.12 CONTRACTOR LONESTAR HAWK, INC. 13911 EST PERIOD JUL 02,2012 TO JAN 18,2014 EST NO 015 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS WITHIN 0 PALO PINTO COUNTY DATE WORK BEGAN JUL 2 , 2012 WORKING DAYS USED 48 PERCENT COMPLETE 100.00 PERCENT TIME USED 52.10 DATE COMPLETED JAN 18 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6228-96-001 RMC - 622896001 02 US0281 PALO PINTO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 13,528.000 13,528.000 22.990 311,008.72 0 SUBTOTAL BID ITEMS $ 311,008.72 0 CONTRACT TOTAL ALL ITEMS $ 311,008.72 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11110209 MGR.NO. 309 PAGE 001 CONT 6228 SEC 96 JOB 001 RES ENGR JONES, SCOTT PROJ RMC - 622896001 HWY US0281 1429 W. BANKHEAD HWY WEAT CNTY PALO PINTO DIST 02 CONTRACT PRICE $ 311,208.72 REPORT DATE 02/06/2014 10.26.12 CONTRACTOR LONESTAR HAWK, INC. 13911 EST PERIOD JUL 02,2012 TO JAN 18,2014 EST NO 015 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 182 RMC - 622896001 6228-96-001 311,008.72 .00 311,008.72 .00 .00 311,008.72 233,256.54 77,752.18 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 311,008.72 .00 311,008.72 .00 .00 311,008.72 233,256.54 77,752.18 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11110209 MGR.NO. 309 PAGE 001 CONT 6228 SEC 96 JOB 001 RES ENGR JONES, SCOTT PROJ RMC - 622896001 HWY US0281 1429 W. BANKHEAD HWY WEAT CNTY PALO PINTO DIST 02 CONTRACT PRICE $ 311,208.72 REPORT DATE 02/06/2014 10.26.13 CONTRACTOR LONESTAR HAWK, INC. 13911 EST PERIOD JUL 02,2012 TO JAN 18,2014 EST NO 015 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6228-96-001 RMC - 622896001 02 US0281 PALO PINTO -LIMITS - VARIOUS ROADWAYS WITHIN PALO PINTO COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 80 0730 FULL-WIDTH MOWING AC 13,528.000 3,382.000 22.990 77,752.18 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 77,752.18 0 TOTAL AMOUNT WORK DONE TO DATE - $ 311,008.72