1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6080201 MGR.NO. 770 PAGE 001 CONT 6140 SEC 18 JOB 001 RES ENGR SCHILLER, RICHARD PROJ RMC - 614018001 HWY IH0820 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 69,230.00 REPORT DATE 10/01/2008 14.57.42 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD AUG 03,2008 TO AUG 13,2008 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 03, 2008 TIME COMPUTED FROM AUG 03, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 64 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 08 TOTAL DAYS ALLOWED = 64 DATE WORK COMPLETED 08/13/08 3 1 DAYS CHARGED TO DATE = 7 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 NO WK FRI WHEN WKG NIGHT SCHEDULE 0 DAYS AT $ 400 PER DAY 9 1 SATURDAY TOTAL = $ .00 10 1 RAIN 11 1 RAIN CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 11 7 4 1 SATURDAY 0 SUNDAY 0 HOLIDAY 1 NO WK FRI WHEN WKG NIGHT SCHEDULE 2 RAIN 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6080201 MGR.NO. 770 PAGE 001 CONT 6140 SEC 18 JOB 001 RES ENGR SCHILLER, RICHARD PROJ RMC - 614018001 HWY IH0820 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 69,230.00 REPORT DATE 10/01/2008 14.57.44 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD AUG 03,2008 TO AUG 13,2008 EST NO 004 & FINAL DIST. 02 COUNTY TARRANT CONTROL 6140-18-001 PROJECT RMC - 614018001 HIGHWAY IH0820 0LIMITS- IH 820 WB TO IH 35W SB CONNECTOR RAMP 0TYPE OF WORK- BRIDGE REPAIR 0 0050 REPAIR STEEL BRIDGE MEMBERS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 BRIDGE REPAIR IN NORTH TARRANT COUNTY 0075 PREPARED BY: CATHY WOOD 0 0080 0500 MOBILIZATION LS 1.000 1.000 9,000.000 9,000.00 0085 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 4,100.000 12,300.00 0090 0662 WK ZN PAV MRK REMOV (Y) 4" (SLD) LF 300.000 476.000 5.500 2,618.00 0095 0666 REFL PAV MRK TY I (Y) 4" (SLD)(090MIL) LF 300.000 0.000 10.000 .00 0100 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 300.000 0.000 3.300 .00 0105 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 300.000 0.000 3.300 .00 0110 0784 REPAIR STL BRIDGE MEMBERS LS 1.000 1.000 38,000.000 38,000.00 0115 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 30.000 28.000 110.000 3,080.00 0120 9000*OFF DUTY POLICE OFFICERS EA 5,200.000 5,200.000 1.000 5,200.00 0 SUBTOTAL BID ITEMS $ 70,198.00 0 TOTAL AMOUNT WORK DONE REPAIR STEEL BRIDGE MEMBERS $ 70,198.00 0 TOTAL AMOUNT WORK DONE CONTROL 6140-18-001 $ 70,198.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6080201 MGR.NO. 770 PAGE 001 CONT 6140 SEC 18 JOB 001 RES ENGR SCHILLER, RICHARD PROJ RMC - 614018001 HWY IH0820 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 69,230.00 REPORT DATE 10/01/2008 14.57.44 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD AUG 03,2008 TO AUG 13,2008 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - IH 820 WB TO IH 35W SB 0 CONNECTOR RAMP DATE WORK BEGAN AUG 3 , 2008 WORKING DAYS USED 7 PERCENT COMPLETE 100.00 PERCENT TIME USED 10.90 DATE COMPLETED AUG 13 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6140-18-001 RMC - 614018001 02 IH0820 TARRANT - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 9,000.000 9,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 4,100.000 12,300.00 0662 WK ZN PAV MRK REMOV (Y) 4" (SLD) LF 300.000 476.000 5.500 2,618.00 0784 REPAIR STL BRIDGE MEMBERS LS 1.000 1.000 38,000.000 38,000.00 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 30.000 28.000 110.000 3,080.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* OFF DUTY POLICE OFFICERS EA 5,200.000 5,200.000 1.000 5,200.00 0 SUBTOTAL BID ITEMS $ 70,198.00 0 CONTRACT TOTAL ALL ITEMS $ 70,198.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6080201 MGR.NO. 770 PAGE 001 CONT 6140 SEC 18 JOB 001 RES ENGR SCHILLER, RICHARD PROJ RMC - 614018001 HWY IH0820 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 69,230.00 REPORT DATE 10/01/2008 14.57.44 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD AUG 03,2008 TO AUG 13,2008 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 220 RMC - 614018001 6140-18-001 70,198.00 .00 70,198.00 .00 .00 70,198.00 68,988.00 1,210.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 70,198.00 .00 70,198.00 .00 .00 70,198.00 68,988.00 1,210.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6080201 MGR.NO. 770 PAGE 001 CONT 6140 SEC 18 JOB 001 RES ENGR SCHILLER, RICHARD PROJ RMC - 614018001 HWY IH0820 2501 SW LOOP 820 FORT WOR CNTY TARRANT DIST 02 CONTRACT PRICE $ 69,230.00 REPORT DATE 10/01/2008 14.57.44 CONTRACTOR GIBSON & ASSOCIATES, INC. 3781 EST PERIOD AUG 03,2008 TO AUG 13,2008 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6140-18-001 RMC - 614018001 02 IH0820 TARRANT -LIMITS - IH 820 WB TO IH 35W SB CONNECTOR RAMP LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 115 6834 PORTABLE CHANGEABLE MESSAGE DAY 30.000 11.000 110.000 1,210.00 SIGN --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 1,210.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 70,198.00