1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11102403 MGR.NO. 770 PAGE 001 CONT 6219 SEC 05 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 621905001 HWY US0062 13301 GATEWAY WEST EL PAS CNTY HUDSPETH DIST 24 CONTRACT PRICE $ 57,600.00 REPORT DATE 03/12/2014 19.08.49 CONTRACTOR E. G. L. CONSTRUCTION, INC. 14284 EST PERIOD OCT 03,2011 TO OCT 31,2013 EST NO 026 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 03, 2011 TIME COMPUTED FROM OCT 03, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 66 729 85 644 BROUGHT FORWARD ADDL DAYS GRANTED = 66 OCT 13 1 1 TOTAL DAYS ALLOWED = 132 2 1 DATE WORK COMPLETED 10/31/13 3 1 DAYS CHARGED TO DATE = 106 4 1 ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 425 6 1 SUNDAY 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 425 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 SATURDAY ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 TIME SUSPENDED 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 SATURDAY 20 1 SUNDAY 21 1 22 1 23 1 24 1 25 1 26 1 SATURDAY 27 1 SUNDAY 28 1 29 1 30 1 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 760 106 654 4 SATURDAY 4 SUNDAY 0 HOLIDAY 1 TIME SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11102403 MGR.NO. 770 PAGE 001 CONT 6219 SEC 05 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 621905001 HWY US0062 13301 GATEWAY WEST EL PAS CNTY HUDSPETH DIST 24 CONTRACT PRICE $ 57,600.00 REPORT DATE 03/12/2014 19.08.50 CONTRACTOR E. G. L. CONSTRUCTION, INC. 14284 EST PERIOD OCT 03,2011 TO OCT 31,2013 EST NO 026 & FINAL DIST. 24 COUNTY HUDSPETH CONTROL 6219-05-001 PROJECT RMC - 621905001 HIGHWAY US0062 0LIMITS- VARIOUS LOCATIONS VARIOUS LOCATIONS 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 CHARLES H. BERRY, JR., P.E. - DISTRICT ENGINEER 0010 DELL CITY MAINTENANCE SECTION (02) 0 0060 MOWING HIGHWAY RIGHT OF WAY NET LENGTH231.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0065 0730 FULL-WIDTH MOWING AC 3,600.000 4,228.800 16.000 67,660.80 0 SUBTOTAL BID ITEMS $ 67,660.80 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY RIGHT OF WAY $ 67,660.80 0 TOTAL AMOUNT WORK DONE CONTROL 6219-05-001 $ 67,660.80 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11102403 MGR.NO. 770 PAGE 001 CONT 6219 SEC 05 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 621905001 HWY US0062 13301 GATEWAY WEST EL PAS CNTY HUDSPETH DIST 24 CONTRACT PRICE $ 57,600.00 REPORT DATE 03/12/2014 19.08.50 CONTRACTOR E. G. L. CONSTRUCTION, INC. 14284 EST PERIOD OCT 03,2011 TO OCT 31,2013 EST NO 026 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS 0 VARIOUS LOCATIONS DATE WORK BEGAN OCT 3 , 2011 WORKING DAYS USED 106 PERCENT COMPLETE 100.00 PERCENT TIME USED 80.30 DATE COMPLETED OCT 31 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6219-05-001 RMC - 621905001 24 US0062 HUDSPETH - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 3,600.000 4,228.800 16.000 67,660.80 0 SUBTOTAL BID ITEMS $ 67,660.80 0 CONTRACT TOTAL ALL ITEMS $ 67,660.80 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11102403 MGR.NO. 770 PAGE 001 CONT 6219 SEC 05 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 621905001 HWY US0062 13301 GATEWAY WEST EL PAS CNTY HUDSPETH DIST 24 CONTRACT PRICE $ 57,600.00 REPORT DATE 03/12/2014 19.08.50 CONTRACTOR E. G. L. CONSTRUCTION, INC. 14284 EST PERIOD OCT 03,2011 TO OCT 31,2013 EST NO 026 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 116 RMC - 621905001 6219-05-001 67,660.80 .00 67,660.80 .00 .00 67,660.80 67,660.80 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 67,660.80 .00 67,660.80 .00 .00 67,660.80 67,660.80 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11102403 MGR.NO. 770 PAGE 001 CONT 6219 SEC 05 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 621905001 HWY US0062 13301 GATEWAY WEST EL PAS CNTY HUDSPETH DIST 24 CONTRACT PRICE $ 57,600.00 REPORT DATE 03/12/2014 19.08.50 CONTRACTOR E. G. L. CONSTRUCTION, INC. 14284 EST PERIOD OCT 03,2011 TO OCT 31,2013 EST NO 026 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6219-05-001 RMC - 621905001 24 US0062 HUDSPETH -LIMITS - VARIOUS LOCATIONS VARIOUS LOCATIONS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 67,660.80