1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3062403 MGR.NO. 770 PAGE 001 CONT 6144 SEC 01 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 614401001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 96,000.00 REPORT DATE 08/15/2008 10.53.24 CONTRACTOR TEX OP CONSTRUCTION, LP 12399 EST PERIOD JUL 01,2008 TO JUL 03,2008 EST NO 025 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 05, 2006 TIME COMPUTED FROM JUL 05, 2006 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 727 727 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 08 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 07/03/08 3 1 PROJECT COMPLETE & ACCEPTED DAYS CHARGED TO DATE = 730 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 450 0 LIQUIDATED DAMAGES 0 DAYS AT $ 450 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 730 730 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3062403 MGR.NO. 770 PAGE 001 CONT 6144 SEC 01 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 614401001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 96,000.00 REPORT DATE 08/15/2008 10.53.24 CONTRACTOR TEX OP CONSTRUCTION, LP 12399 EST PERIOD JUL 01,2008 TO JUL 03,2008 EST NO 025 DIST. 24 COUNTY EL PASO CONTROL 6144-01-001 PROJECT RMC - 614401001 HIGHWAY IH0010 0LIMITS- VARIOUS LOCATIONS VARIOUS LOCATIONS 0TYPE OF WORK- MILLING AND PLANING 0 0005 CHARLES H. BERRY, P.E.- DISTRICT ENGINEER 0010 EAST AREA AND WEST ARE MAINTENANCE SECTIONS 0 0060 MILLING AND PLANING NET LENGTH100.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0065 0354 PLANE ASPH CONC PAV(0" TO 3") SY 100,000.000 6,400.000 .960 6,144.00 0 SUBTOTAL BID ITEMS $ 6,144.00 0 0070 CHANGE ORDER NO.1 IS FOR ADDITIONAL WORK ADDED BY TXDOT ON 0071 IH-10.(NEW LIMITS NOT SHOWN IN THE PLANS). NEW PRICE FOR THIS 0072 ITEM OF WORK DUE TO HAUL BEING FURTHER THAN THAT SHOWN IN 0073 THE PLANS. 0 0075 9001*PLANE ASPH CONC PAV (0" TO 3") SY 25,000.000 3,353.330 1.150 3,856.33 0 SUBTOTAL BID ITEMS $ 3,856.33 0 TOTAL AMOUNT WORK DONE MILLING AND PLANING $ 10,000.33 0 TOTAL AMOUNT WORK DONE CONTROL 6144-01-001 $ 10,000.33 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3062403 MGR.NO. 770 PAGE 001 CONT 6144 SEC 01 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 614401001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 96,000.00 REPORT DATE 08/15/2008 10.53.24 CONTRACTOR TEX OP CONSTRUCTION, LP 12399 EST PERIOD JUL 01,2008 TO JUL 03,2008 EST NO 025 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS 0 VARIOUS LOCATIONS DATE WORK BEGAN JUL 5 , 2006 WORKING DAYS USED 730 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED JUL 3 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6144-01-001 RMC - 614401001 24 IH0010 EL PASO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0354 PLANE ASPH CONC PAV(0" TO 3") SY 100,000.000 6,400.000 .960 6,144.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* PLANE ASPH CONC PAV (0" TO 3") SY 25,000.000 3,353.330 1.150 3,856.33 0 SUBTOTAL BID ITEMS $ 10,000.33 0 CONTRACT TOTAL ALL ITEMS $ 10,000.33 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3062403 MGR.NO. 770 PAGE 001 CONT 6144 SEC 01 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 614401001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 96,000.00 REPORT DATE 08/15/2008 10.53.24 CONTRACTOR TEX OP CONSTRUCTION, LP 12399 EST PERIOD JUL 01,2008 TO JUL 03,2008 EST NO 025 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 72 RMC - 614401001 6144-01-001 10,000.33 .00 10,000.33 .00 .00 10,000.33 10,000.33 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 10,000.33 .00 10,000.33 .00 .00 10,000.33 10,000.33 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3062403 MGR.NO. 770 PAGE 001 CONT 6144 SEC 01 JOB 001 RES ENGR DUBRULE, MONICA PROJ RMC - 614401001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 96,000.00 REPORT DATE 08/15/2008 10.53.24 CONTRACTOR TEX OP CONSTRUCTION, LP 12399 EST PERIOD JUL 01,2008 TO JUL 03,2008 EST NO 025 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6144-01-001 RMC - 614401001 24 IH0010 EL PASO -LIMITS - VARIOUS LOCATIONS VARIOUS LOCATIONS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 10,000.33