1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4124014 MGR.NO. 001 PAGE 001 CONT 6236 SEC 95 JOB 001 RES ENGR COPPOCK, GEORGE PROJ RMC - 623695001 HWY BI0045F 100 SW CR 1000 CORSICANA CNTY NAVARRO DIST 18 CONTRACT PRICE $ 631,870.32 REPORT DATE 11/05/2012 11.42.54 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 09,2012 TO OCT 09,2012 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 09, 2012 TIME COMPUTED FROM JUL 09, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 41 84 52 32 BROUGHT FORWARD ADDL DAYS GRANTED = 4 OCT 12 1 1 TOO WET TOTAL DAYS ALLOWED = 45 2 1 RAIN DATE WORK COMPLETED 10/09/12 3 1 DAYS CHARGED TO DATE = 56 4 1 ASSESSED LIQ DAMAGES = 11 5 1 LIQ DAMAGE RATE $ 610 6 1 SATURDAY 7 1 SUNDAY LIQUIDATED DAMAGES 8 1 11 DAYS AT $ 610 PER DAY 9 1 WORK COMPLETED AND ACCEPTED TOTAL = $ 6,710.00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 93 56 37 1 SATURDAY 1 SUNDAY 0 HOLIDAY 1 TOO WET 1 RAIN 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4124014 MGR.NO. 001 PAGE 001 CONT 6236 SEC 95 JOB 001 RES ENGR COPPOCK, GEORGE PROJ RMC - 623695001 HWY BI0045F 100 SW CR 1000 CORSICANA CNTY NAVARRO DIST 18 CONTRACT PRICE $ 631,870.32 REPORT DATE 11/05/2012 11.42.56 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 09,2012 TO OCT 09,2012 EST NO 004 & FINAL DIST. 18 COUNTY NAVARRO CONTROL 6236-95-001 PROJECT RMC - 623695001 HIGHWAY BI0045F 0LIMITS- .1 MILE SOUTH OF HARDY AVENUE IN NAVARRO COUNTY MAINTENANCE SECTION 0TYPE OF WORK- REMOVE AND REPLACE TRAVEL LANES 0 0005 ESTIMATE PREPARED BY GEORGE COPPOCK 0 0055 REMOVE AND REPLACE TRAVEL LANES NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0105 REMOVE STAB BASE & ASPH PAV (13"-18") SY 4,500.000 4,704.000 10.000 47,040.00 0060 0105 ADJ EST QUANTITY TO DATE 4,704.000 0065 0132 EMBANKMENT (FINAL)(DENS CONT)(TY A) CY 1,660.000 1,549.500 20.000 30,990.00 0070 0134 BACKFILL (TY A OR B) STA 24.000 24.000 500.000 12,000.00 0075 0164 BROADCAST SEED (PERM) (URBAN) (SANDY) SY 3,000.000 3,000.000 .390 1,170.00 0080 0315 FOG SEAL (CSS-1) GAL 675.000 500.000 7.500 3,750.00 0085 0316 ASPH (AC-20-5TR) GAL 21,370.000 19,647.000 4.000 78,588.00 0090 0316 AGGR (TY-PL GR-3) CY 463.000 448.000 100.000 44,800.00 0095 0340 D-GR HMA(METH) TY-B PG64-22 TON 2,901.000 3,145.000 70.000 220,150.00 0095 0340 ADJ EST QUANTITY TO DATE 3,145.000 0100 0340 D-GR HMA(METH) TY-C PG64-22 TON 711.000 930.000 80.000 74,400.00 0100 0340 ADJ EST QUANTITY TO DATE 930.000 0105 0500 MOBILIZATION LS 1.000 1.000 60,000.000 60,000.00 0110 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 7,000.000 14,000.00 0115 0662 WK ZN PAV MRK REMOV (TRAF BTN) TY W EA 2,500.000 4,730.000 1.700 8,041.00 0120 0662 WK ZN PAV MRK REMOV (TRAF BTN) TY Y EA 2,500.000 8,700.000 1.700 14,790.00 0125 0662 WK ZN PAV MRK REMOV (W) 4" (SLD) LF 16,612.000 7,600.000 .680 5,168.00 0130 0662 WK ZN PAV MRK REMOV (Y) 4" (SLD) LF 16,612.000 8,880.000 .680 6,038.40 0135 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 3,250.000 3,250.000 .420 1,365.00 0140 0666 REFL PAV MRK TY I (W) 4" 1 (SLD)(100MIL) LF 13,000.000 13,000.000 .420 5,460.00 0145 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 1,800.000 1,800.000 1.000 1,800.00 0150 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 68.000 68.000 6.000 408.00 0155 0666 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 14.000 14.000 135.000 1,890.00 0160 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 13.000 13.000 175.000 2,275.00 0165 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 15,200.000 15,200.000 .420 6,384.00 0170 0666 REFL PAV MRK TY I (Y) 12"(SLD)(100MIL) LF 910.000 820.000 3.000 2,460.00 0175 0672 REFL PAV MRKR TY I-C EA 340.000 340.000 3.500 1,190.00 0180 0672 REFL PAV MRKR TY II-A-A EA 246.000 246.000 3.500 861.00 0185 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 13,750.000 13,976.000 .350 4,891.60 0190 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 1,700.000 630.000 .700 441.00 0195 0677 ELIM EXT PAV MRK & MRKS (12") LF 900.000 645.000 1.000 645.00 0200 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 14.000 8.000 50.000 400.00 0205 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 13.000 8.000 50.000 400.00 0210 6834 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 2.000 3,000.000 6,000.00 0211 0110*EXCAVATION (ROADWAY) CY 1,140.000 1,176.440 9.940 11,693.81 0220 0662*WK ZN PAV MRK SHT TERM (TAB) TY W EA 1,200.000 1,200.000 .900 1,080.00 0225 0662*WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 650.000 650.000 .900 585.00 0 SUBTOTAL BID ITEMS $ 671,154.81 0 TOTAL AMOUNT WORK DONE REMOVE AND REPLACE TRAVEL LANES $ 671,154.81 0 TOTAL AMOUNT WORK DONE CONTROL 6236-95-001 $ 671,154.81 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4124014 MGR.NO. 001 PAGE 001 CONT 6236 SEC 95 JOB 001 RES ENGR COPPOCK, GEORGE PROJ RMC - 623695001 HWY BI0045F 100 SW CR 1000 CORSICANA CNTY NAVARRO DIST 18 CONTRACT PRICE $ 631,870.32 REPORT DATE 11/05/2012 11.42.56 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 09,2012 TO OCT 09,2012 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - .1 MILE SOUTH OF HARDY AVENUE IN 0 NAVARRO COUNTY MAINTENANCE SECTION DATE WORK BEGAN JUL 9 , 2012 WORKING DAYS USED 56 PERCENT COMPLETE 100.00 PERCENT TIME USED 124.40 DATE COMPLETED OCT 9 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6236-95-001 RMC - 623695001 18 BI0045F NAVARRO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0105 REMOVE STAB BASE & ASPH PAV (13"-18") SY 4,500.000 4,704.000 10.000 47,040.00 0105 ADJ EST QUANTITY TO DATE 4,704.000 0132 EMBANKMENT (FINAL)(DENS CONT)(TY A) CY 1,660.000 1,549.500 20.000 30,990.00 0134 BACKFILL (TY A OR B) STA 24.000 24.000 500.000 12,000.00 0164 BROADCAST SEED (PERM) (URBAN) (SANDY) SY 3,000.000 3,000.000 .390 1,170.00 0315 FOG SEAL (CSS-1) GAL 675.000 500.000 7.500 3,750.00 0316 ASPH (AC-20-5TR) GAL 21,370.000 19,647.000 4.000 78,588.00 0316 AGGR (TY-PL GR-3) CY 463.000 448.000 100.000 44,800.00 0340 D-GR HMA(METH) TY-B PG64-22 TON 2,901.000 3,145.000 70.000 220,150.00 0340 ADJ EST QUANTITY TO DATE 3,145.000 0340 D-GR HMA(METH) TY-C PG64-22 TON 711.000 930.000 80.000 74,400.00 0340 ADJ EST QUANTITY TO DATE 930.000 0500 MOBILIZATION LS 1.000 1.000 60,000.000 60,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 7,000.000 14,000.00 0662 WK ZN PAV MRK REMOV (TRAF BTN) TY W EA 2,500.000 4,730.000 1.700 8,041.00 0662 WK ZN PAV MRK REMOV (TRAF BTN) TY Y EA 2,500.000 8,700.000 1.700 14,790.00 0662 WK ZN PAV MRK REMOV (W) 4" (SLD) LF 16,612.000 7,600.000 .680 5,168.00 0662 WK ZN PAV MRK REMOV (Y) 4" 1 (SLD) LF 16,612.000 8,880.000 .680 6,038.40 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 3,250.000 3,250.000 .420 1,365.00 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 13,000.000 13,000.000 .420 5,460.00 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 1,800.000 1,800.000 1.000 1,800.00 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 68.000 68.000 6.000 408.00 0666 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 14.000 14.000 135.000 1,890.00 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 13.000 13.000 175.000 2,275.00 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 15,200.000 15,200.000 .420 6,384.00 0666 REFL PAV MRK TY I (Y) 12"(SLD)(100MIL) LF 910.000 820.000 3.000 2,460.00 0672 REFL PAV MRKR TY I-C EA 340.000 340.000 3.500 1,190.00 0672 REFL PAV MRKR TY II-A-A EA 246.000 246.000 3.500 861.00 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 13,750.000 13,976.000 .350 4,891.60 0677 ELIM EXT PAV MRK & MRKS ( 8") LF 1,700.000 630.000 .700 441.00 0677 ELIM EXT PAV MRK & MRKS (12") LF 900.000 645.000 1.000 645.00 0677 ELIM EXT PAV MRK & MRKS (ARROW) EA 14.000 8.000 50.000 400.00 0677 ELIM EXT PAV MRK & MRKS (WORD) EA 13.000 8.000 50.000 400.00 6834 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 2.000 3,000.000 6,000.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00110* EXCAVATION (ROADWAY) CY 1,140.000 1,176.440 9.940 11,693.81 0662* WK ZN PAV MRK SHT TERM (TAB) TY W EA 1,200.000 1,200.000 .900 1,080.00 0662* WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 650.000 650.000 .900 585.00 0 SUBTOTAL BID ITEMS $ 671,154.81 0 CONTRACT TOTAL ALL ITEMS $ 671,154.81 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4124014 MGR.NO. 001 PAGE 001 CONT 6236 SEC 95 JOB 001 RES ENGR COPPOCK, GEORGE PROJ RMC - 623695001 HWY BI0045F 100 SW CR 1000 CORSICANA CNTY NAVARRO DIST 18 CONTRACT PRICE $ 631,870.32 REPORT DATE 11/05/2012 11.42.56 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 09,2012 TO OCT 09,2012 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 175 RMC - 623695001 6236-95-001 671,154.81 .00 671,154.81 .00 6,710.00 664,444.81 591,266.81 73,178.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 671,154.81 .00 671,154.81 .00 6,710.00 664,444.81 591,266.81 73,178.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4124014 MGR.NO. 001 PAGE 001 CONT 6236 SEC 95 JOB 001 RES ENGR COPPOCK, GEORGE PROJ RMC - 623695001 HWY BI0045F 100 SW CR 1000 CORSICANA CNTY NAVARRO DIST 18 CONTRACT PRICE $ 631,870.32 REPORT DATE 11/05/2012 11.42.57 CONTRACTOR BIG CREEK CONSTRUCTION, LTD. 8175 EST PERIOD JUL 09,2012 TO OCT 09,2012 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6236-95-001 RMC - 623695001 18 BI0045F NAVARRO -LIMITS - .1 MILE SOUTH OF HARDY AVENUE IN NAVARRO COUNTY MAINTENANCE SECTION LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0105 REMOVE STAB BASE & ASPH PAV SY 4,500.000 204.000 10.000 2,040.00 (13"-18") 95 0340 D-GR HMA(METH) TY-B PG64-22 TON 2,901.000 244.000 70.000 17,080.00 100 0340 D-GR HMA(METH) TY-C PG64-22 TON 711.000 219.000 80.000 17,520.00 105 0500 MOBILIZATION LS 1.000 0.200 60,000.000 12,000.00 135 0666 REFL PAV MRK TY I (W) 4" LF 3,250.000 3,250.000 0.420 1,365.00 (BRK)(100MIL) 140 0666 REFL PAV MRK TY I (W) 4" LF 13,000.000 13,000.000 0.420 5,460.00 (SLD)(100MIL) 145 0666 REFL PAV MRK TY I (W) 8" LF 1,800.000 1,800.000 1.000 1,800.00 (SLD)(100MIL) 150 0666 REFL PAV MRK TY I (W) LF 68.000 68.000 6.000 408.00 24"(SLD)(100MIL) 155 0666 REFL PAV MRK TY I (W) EA 14.000 14.000 135.000 1,890.00 (ARROW) (100MIL) 160 0666 REFL PAV MRK TY I (W) (WORD) EA 13.000 13.000 175.000 2,275.00 (100MIL) 165 0666 REFL PAV MRK TY I (Y) 4" LF 15,200.000 15,200.000 0.420 6,384.00 (BRK)(100MIL) 170 0666 REFL PAV MRK TY I (Y) LF 910.000 820.000 3.000 2,460.00 12"(SLD)(100MIL) 175 0672 REFL PAV MRKR TY I-C EA 340.000 340.000 3.500 1,190.00 180 0672 REFL PAV MRKR TY II-A-A EA 246.000 246.000 3.500 861.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 220 0662* WK ZN PAV MRK SHT TERM (TAB) EA 0.000 1,200.000 0.900 1,080.00 TY W 225 0662* WK ZN PAV MRK SHT TERM (TAB) EA 0.000 650.000 0.900 585.00 TY Y-2 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 74,398.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 671,154.81