1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2121803 MGR.NO. 007 PAGE 001 CONT 6235 SEC 10 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 623510001 HWY SH0121 2205 S. SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 93,459.46 REPORT DATE 11/29/2012 06.54.39 CONTRACTOR ANTHONY SERVICES 6911 EST PERIOD MAY 01,2012 TO NOV 07,2012 EST NO 008 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 01, 2012 TIME COMPUTED FROM MAY 08, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 22 184 1 183 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 12 1 1 WORK BEGAN TIME NOT STARTED TOTAL DAYS ALLOWED = 22 2 1 WORK BEGAN TIME NOT STARTED DATE WORK COMPLETED 11/07/12 3 1 WORK BEGAN TIME NOT STARTED DAYS CHARGED TO DATE = 1 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 WORK BEGAN TIME NOT STARTED LIQ DAMAGE RATE $ 570 6 1 WORK BEGAN TIME NOT STARTED 7 1 WORK COMPLETED AND ACCEPTED LIQUIDATED DAMAGES 0 DAYS AT $ 570 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 191 1 190 0 SATURDAY 1 SUNDAY 0 HOLIDAY 5 WORK BEGAN TIME NOT STARTED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2121803 MGR.NO. 007 PAGE 001 CONT 6235 SEC 10 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 623510001 HWY SH0121 2205 S. SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 93,459.46 REPORT DATE 11/29/2012 06.54.40 CONTRACTOR ANTHONY SERVICES 6911 EST PERIOD MAY 01,2012 TO NOV 07,2012 EST NO 008 & FINAL DIST. 18 COUNTY COLLIN CONTROL 6235-10-001 PROJECT RMC - 623510001 HIGHWAY SH0121 0LIMITS- VARIOUS LOCATIONS IN THE COLLIN COUNTY MAINTENANCE SECTION 0TYPE OF WORK- VEGETATION MANAGEMENT 0 0050 VEGETATION MANAGEMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY JUAN PAREDES 0 0075 0730 FULL-WIDTH MOWING AC 3,277.000 3,277.000 24.980 81,859.46 0080 7039 BROADCAST HERBICIDE VEGETATION CONTROL AC 580.000 580.000 20.000 11,600.00 0 SUBTOTAL BID ITEMS $ 93,459.46 0 TOTAL AMOUNT WORK DONE VEGETATION MANAGEMENT $ 93,459.46 0 TOTAL AMOUNT WORK DONE CONTROL 6235-10-001 $ 93,459.46 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2121803 MGR.NO. 007 PAGE 001 CONT 6235 SEC 10 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 623510001 HWY SH0121 2205 S. SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 93,459.46 REPORT DATE 11/29/2012 06.54.40 CONTRACTOR ANTHONY SERVICES 6911 EST PERIOD MAY 01,2012 TO NOV 07,2012 EST NO 008 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN THE COLLIN COUNTY 0 MAINTENANCE SECTION DATE WORK BEGAN MAY 1 , 2012 WORKING DAYS USED 1 PERCENT COMPLETE 100.00 PERCENT TIME USED 4.50 DATE COMPLETED NOV 7 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6235-10-001 RMC - 623510001 18 SH0121 COLLIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 3,277.000 3,277.000 24.980 81,859.46 7039 BROADCAST HERBICIDE VEGETATION CONTROL AC 580.000 580.000 20.000 11,600.00 0 SUBTOTAL BID ITEMS $ 93,459.46 0 CONTRACT TOTAL ALL ITEMS $ 93,459.46 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2121803 MGR.NO. 007 PAGE 001 CONT 6235 SEC 10 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 623510001 HWY SH0121 2205 S. SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 93,459.46 REPORT DATE 11/29/2012 06.54.40 CONTRACTOR ANTHONY SERVICES 6911 EST PERIOD MAY 01,2012 TO NOV 07,2012 EST NO 008 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 43 RMC - 623510001 6235-10-001 93,459.46 .00 93,459.46 .00 .00 93,459.46 93,459.46 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 93,459.46 .00 93,459.46 .00 .00 93,459.46 93,459.46 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2121803 MGR.NO. 007 PAGE 001 CONT 6235 SEC 10 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 623510001 HWY SH0121 2205 S. SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 93,459.46 REPORT DATE 11/29/2012 06.54.40 CONTRACTOR ANTHONY SERVICES 6911 EST PERIOD MAY 01,2012 TO NOV 07,2012 EST NO 008 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6235-10-001 RMC - 623510001 18 SH0121 COLLIN -LIMITS - VARIOUS LOCATIONS IN THE COLLIN COUNTY MAINTENANCE SECTION - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 93,459.46