1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4084011 MGR.NO. 007 PAGE 001 CONT 6175 SEC 84 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 617584001 HWY US0075 2205 S.SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 702,922.17 REPORT DATE 12/02/2008 08.53.54 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 003 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 17, 2008 TIME COMPUTED FROM SEP 09, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 100 53 34 19 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 08 1 1 TIME SUSP - LETTER SUBMITTED TOTAL DAYS ALLOWED = 100 2 1 TIME SUSP - LETTER SUBMITTED DATE WORK COMPLETED 3 1 TIME SUSP - LETTER SUBMITTED DAYS CHARGED TO DATE = 34 4 1 TIME SUSP - LETTER SUBMITTED ASSESSED LIQ DAMAGES = 0 5 1 TIME SUSP - LETTER SUBMITTED LIQ DAMAGE RATE $ 500 6 1 TIME SUSP - LETTER SUBMITTED 7 1 TIME SUSP - LETTER SUBMITTED LIQUIDATED DAMAGES 8 1 TIME SUSP - LETTER SUBMITTED 0 DAYS AT $ 500 PER DAY 9 1 TIME SUSP - LETTER SUBMITTED TOTAL = $ .00 10 1 TIME SUSP - LETTER SUBMITTED 11 1 TIME SUSP - LETTER SUBMITTED CERTIFIED AS CORRECT AND 12 1 TIME SUSP - LETTER SUBMITTED ONE COPY HAS BEEN GIVEN 13 1 TIME SUSP - LETTER SUBMITTED TO THE CONTRACTOR 14 1 TIME SUSP - LETTER SUBMITTED 15 1 TIME SUSP - LETTER SUBMITTED 16 1 TIME SUSP - LETTER SUBMITTED ---------------------------- 17 1 TIME SUSP - LETTER SUBMITTED AREA/PROJECT ENGINEER 18 1 TIME SUSP - LETTER SUBMITTED 19 1 TIME SUSP - LETTER SUBMITTED 20 1 TIME SUSP - LETTER SUBMITTED 21 1 TIME SUSP - LETTER SUBMITTED 22 1 TIME SUSP - LETTER SUBMITTED 23 1 TIME SUSP - LETTER SUBMITTED 24 1 TIME SUSP - LETTER SUBMITTED 25 1 TIME SUSP - LETTER SUBMITTED 26 1 TIME SUSP - LETTER SUBMITTED 27 1 TIME SUSP - LETTER SUBMITTED 28 1 TIME SUSP - LETTER SUBMITTED 29 1 TIME SUSP - LETTER SUBMITTED 30 1 TIME SUSP - LETTER SUBMITTED 0 ----- ----- ----- 83 34 49 0 SATURDAY 0 SUNDAY 0 HOLIDAY 30 TIME SUSP - LETTER SUBMITTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4084011 MGR.NO. 007 PAGE 001 CONT 6175 SEC 84 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 617584001 HWY US0075 2205 S.SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 702,922.17 REPORT DATE 12/02/2008 08.53.54 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 003 DIST. 18 COUNTY COLLIN CONTROL 6175-84-001 PROJECT RMC - 617584001 HIGHWAY US0075 0LIMITS- VARIOUS LOCATIONS IN COLLIN COUNTY MAINTENANCE SECTION 0TYPE OF WORK- REPAIR SPALLED AREAS 0 0005 PREPARED BY MUHAMMAD JAMAL ELAHI 0 0055 REPAIR SPALLED AREAS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0361 FULL-DEPTH REPAIR CRCP (13") SY 60.000 60.000 380.000 22,800.00 0065 0720 SPALLING REPAIR (POLYMERIC)(SEMIRIGID) GAL 17,439.030 6,918.000 39.000 269,802.00 0 SUBTOTAL BID ITEMS $ 292,602.00 0 TOTAL AMOUNT WORK DONE REPAIR SPALLED AREAS $ 292,602.00 0 TOTAL AMOUNT WORK DONE CONTROL 6175-84-001 $ 292,602.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4084011 MGR.NO. 007 PAGE 001 CONT 6175 SEC 84 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 617584001 HWY US0075 2205 S.SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 702,922.17 REPORT DATE 12/02/2008 08.53.54 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 003 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN COLLIN 0 COUNTY MAINTENANCE SECTION DATE WORK BEGAN SEP 17, 2008 WORKING DAYS USED 34 PERCENT COMPLETE 41.62 PERCENT TIME USED 34.00 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6175-84-001 RMC - 617584001 18 US0075 COLLIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0361 FULL-DEPTH REPAIR CRCP (13") SY 60.000 60.000 380.000 22,800.00 0720 SPALLING REPAIR (POLYMERIC)(SEMIRIGID) GAL 17,439.030 6,918.000 39.000 269,802.00 0 SUBTOTAL BID ITEMS $ 292,602.00 0 CONTRACT TOTAL ALL ITEMS $ 292,602.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4084011 MGR.NO. 007 PAGE 001 CONT 6175 SEC 84 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 617584001 HWY US0075 2205 S.SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 702,922.17 REPORT DATE 12/02/2008 08.53.54 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 003 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 43 RMC - 617584001 6175-84-001 292,602.00 .00 292,602.00 .00 .00 292,602.00 292,602.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 292,602.00 .00 292,602.00 .00 .00 292,602.00 292,602.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4084011 MGR.NO. 007 PAGE 001 CONT 6175 SEC 84 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 617584001 HWY US0075 2205 S.SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 702,922.17 REPORT DATE 12/02/2008 08.53.55 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD NOV 01,2008 TO NOV 30,2008 EST NO 003 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6175-84-001 RMC - 617584001 18 US0075 COLLIN -LIMITS - VARIOUS LOCATIONS IN COLLIN COUNTY MAINTENANCE SECTION - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 292,602.00