1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2081804 MGR.NO. 007 PAGE 001 CONT 6169 SEC 05 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 616905001 HWY SH0121 2205 S. SH5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 143,002.50 REPORT DATE 10/27/2008 08.36.30 CONTRACTOR TEXAS LAWN & LANDSCAPE 13170 EST PERIOD OCT 01,2008 TO OCT 31,2008 EST NO 006 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 01, 2008 TIME COMPUTED FROM MAY 12, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 32 153 17 136 BROUGHT FORWARD ADDL DAYS GRANTED = 11 OCT 08 1 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR.TOTAL DAYS ALLOWED = 43 2 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR.DATE WORK COMPLETED 3 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR.DAYS CHARGED TO DATE = 21 4 1 WORK BEGAN TIME NOT STARTED ASSESSED LIQ DAMAGES = 0 5 1 SUNDAY LIQ DAMAGE RATE $ 400 6 1 RAIN 7 1 TOO WET LIQUIDATED DAMAGES 8 1 TOO WET 0 DAYS AT $ 400 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 SATURDAY CERTIFIED AS CORRECT AND 12 1 SUNDAY ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 RAIN 16 1 TOO WET ---------------------------- 17 1 WORK COMPLETED IN LESS THAN SEVEN HOURSAREA/PROJECT ENGINEER 18 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 19 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 20 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 21 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 22 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 23 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 24 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 25 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 26 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 27 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 28 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 29 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 30 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 31 1 TIME SUSPENDED TIL NEXT WORK ORDER LTR. ----- ----- ----- 184 21 163 1 SATURDAY 2 SUNDAY 0 HOLIDAY 17 TIME SUSPENDED TIL NEXT WORK ORDER LTR. 1 WORK BEGAN TIME NOT STARTED 2 RAIN 3 TOO WET 1 WORK COMPLETED IN LESS THAN SEVEN HOURS 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2081804 MGR.NO. 007 PAGE 001 CONT 6169 SEC 05 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 616905001 HWY SH0121 2205 S. SH5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 143,002.50 REPORT DATE 10/27/2008 08.36.30 CONTRACTOR TEXAS LAWN & LANDSCAPE 13170 EST PERIOD OCT 01,2008 TO OCT 31,2008 EST NO 006 DIST. 18 COUNTY COLLIN CONTROL 6169-05-001 PROJECT RMC - 616905001 HIGHWAY SH0121 0LIMITS- VARIOUS ROADWAYS IN THE COLLIN COUNTY MAINTENENCE SECTION 0TYPE OF WORK- VEGETATION MANAGEMENT 0 0005 PREPARED BY MATT PHILLIPS, P.E. 0 0055 VEGETATION MANAGEMENT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 4,965.000 5,254.000 24.500 128,723.00 0060 0730 ADJ EST QUANTITY TO DATE 6,917.000 0065 7039 BROADCAST HERBICIDE VEGETATION CONTROL AC 712.000 847.000 30.000 25,410.00 0065 7039 ADJ EST QUANTITY TO DATE 847.000 0 SUBTOTAL BID ITEMS $ 154,133.00 0 TOTAL AMOUNT WORK DONE VEGETATION MANAGEMENT $ 154,133.00 0 TOTAL AMOUNT WORK DONE CONTROL 6169-05-001 $ 154,133.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2081804 MGR.NO. 007 PAGE 001 CONT 6169 SEC 05 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 616905001 HWY SH0121 2205 S. SH5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 143,002.50 REPORT DATE 10/27/2008 08.36.31 CONTRACTOR TEXAS LAWN & LANDSCAPE 13170 EST PERIOD OCT 01,2008 TO OCT 31,2008 EST NO 006 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN THE COLLIN 0 COUNTY MAINTENENCE SECTION DATE WORK BEGAN MAY 1 , 2008 WORKING DAYS USED 21 PERCENT COMPLETE 99.99 PERCENT TIME USED 48.80 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6169-05-001 RMC - 616905001 18 SH0121 COLLIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 4,965.000 5,254.000 24.500 128,723.00 0730 ADJ EST QUANTITY TO DATE 6,917.000 7039 BROADCAST HERBICIDE VEGETATION CONTROL AC 712.000 847.000 30.000 25,410.00 7039 ADJ EST QUANTITY TO DATE 847.000 0 SUBTOTAL BID ITEMS $ 154,133.00 0 CONTRACT TOTAL ALL ITEMS $ 154,133.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2081804 MGR.NO. 007 PAGE 001 CONT 6169 SEC 05 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 616905001 HWY SH0121 2205 S. SH5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 143,002.50 REPORT DATE 10/27/2008 08.36.31 CONTRACTOR TEXAS LAWN & LANDSCAPE 13170 EST PERIOD OCT 01,2008 TO OCT 31,2008 EST NO 006 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 43 RMC - 616905001 6169-05-001 154,133.00 .00 154,133.00 .00 .00 154,133.00 113,512.00 40,621.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 154,133.00 .00 154,133.00 .00 .00 154,133.00 113,512.00 40,621.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2081804 MGR.NO. 007 PAGE 001 CONT 6169 SEC 05 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 616905001 HWY SH0121 2205 S. SH5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 143,002.50 REPORT DATE 10/27/2008 08.36.31 CONTRACTOR TEXAS LAWN & LANDSCAPE 13170 EST PERIOD OCT 01,2008 TO OCT 31,2008 EST NO 006 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6169-05-001 RMC - 616905001 18 SH0121 COLLIN -LIMITS - VARIOUS ROADWAYS IN THE COLLIN COUNTY MAINTENENCE SECTION LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 4,965.000 1,658.000 24.500 40,621.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 40,621.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 154,133.00