1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11071804 MGR.NO. 006 PAGE 001 CONT 6167 SEC 81 JOB 001 RES ENGR JOHNSON, CHRIS PROJ RMC - 616781001 HWY IH0020 2750 S. WASHINGTON KAUFMA CNTY KAUFMAN DIST 18 CONTRACT PRICE $ 66,812.75 REPORT DATE 11/02/2009 15.57.05 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 019 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 14, 2008 TIME COMPUTED FROM APR 14, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 535 18 517 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTTOTAL DAYS ALLOWED = 30 2 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTDATE WORK COMPLETED 3 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTDAYS CHARGED TO DATE = 18 4 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTASSESSED LIQ DAMAGES = 0 5 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTLIQ DAMAGE RATE $ 400 6 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 7 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT LIQUIDATED DAMAGES 8 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 0 DAYS AT $ 400 PER DAY 9 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTTOTAL = $ .00 10 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 11 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTCERTIFIED AS CORRECT AND 12 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTONE COPY HAS BEEN GIVEN 13 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTTO THE CONTRACTOR 14 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 15 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 16 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT---------------------------- 17 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LTAREA/PROJECT ENGINEER 18 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 19 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 20 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 21 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 22 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 23 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 24 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 25 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 26 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 27 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 28 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 29 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 30 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT 31 1 TIME SUSPENDED UNTIL NEXT WORK ORDER LT ----- ----- ----- 566 18 548 0 SATURDAY 0 SUNDAY 0 HOLIDAY 31 TIME SUSPENDED UNTIL NEXT WORK ORDER LTR 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11071804 MGR.NO. 006 PAGE 001 CONT 6167 SEC 81 JOB 001 RES ENGR JOHNSON, CHRIS PROJ RMC - 616781001 HWY IH0020 2750 S. WASHINGTON KAUFMA CNTY KAUFMAN DIST 18 CONTRACT PRICE $ 66,812.75 REPORT DATE 11/02/2009 15.57.06 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 019 DIST. 18 COUNTY KAUFMAN CONTROL 6167-81-001 PROJECT RMC - 616781001 HIGHWAY IH0020 0LIMITS- VARIOUS LOCATIONS IN KAUFMAN COUNTY MAINTENANCE SECTION 0TYPE OF WORK- CLEANING AND SWEEPING HIGHWAYS 0 0005 ESTIMATE PREPARED BY WILLIAM BEARD 0 0055 CLEANING AND SWEEPING HIGHWAYS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 83.320 83.320 284.000 23,662.88 0065 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 78.690 78.690 305.000 24,000.45 0070 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 10.400 10.400 193.000 2,007.20 0075 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 3.200 3.200 314.000 1,004.80 0080 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 73.020 36.510 221.000 8,068.71 0 SUBTOTAL BID ITEMS $ 58,744.04 0 TOTAL AMOUNT WORK DONE CLEANING AND SWEEPING HIGHWAYS $ 58,744.04 0 TOTAL AMOUNT WORK DONE CONTROL 6167-81-001 $ 58,744.04 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11071804 MGR.NO. 006 PAGE 001 CONT 6167 SEC 81 JOB 001 RES ENGR JOHNSON, CHRIS PROJ RMC - 616781001 HWY IH0020 2750 S. WASHINGTON KAUFMA CNTY KAUFMAN DIST 18 CONTRACT PRICE $ 66,812.75 REPORT DATE 11/02/2009 15.57.06 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 019 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN KAUFMAN 0 COUNTY MAINTENANCE SECTION DATE WORK BEGAN APR 14, 2008 WORKING DAYS USED 18 PERCENT COMPLETE 87.92 PERCENT TIME USED 60.00 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6167-81-001 RMC - 616781001 18 IH0020 KAUFMAN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 83.320 83.320 284.000 23,662.88 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 78.690 78.690 305.000 24,000.45 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 10.400 10.400 193.000 2,007.20 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 3.200 3.200 314.000 1,004.80 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 73.020 36.510 221.000 8,068.71 0 SUBTOTAL BID ITEMS $ 58,744.04 0 CONTRACT TOTAL ALL ITEMS $ 58,744.04 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11071804 MGR.NO. 006 PAGE 001 CONT 6167 SEC 81 JOB 001 RES ENGR JOHNSON, CHRIS PROJ RMC - 616781001 HWY IH0020 2750 S. WASHINGTON KAUFMA CNTY KAUFMAN DIST 18 CONTRACT PRICE $ 66,812.75 REPORT DATE 11/02/2009 15.57.06 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 019 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 130 RMC - 616781001 6167-81-001 58,744.04 .00 58,744.04 .00 .00 58,744.04 58,744.04 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 58,744.04 .00 58,744.04 .00 .00 58,744.04 58,744.04 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11071804 MGR.NO. 006 PAGE 001 CONT 6167 SEC 81 JOB 001 RES ENGR JOHNSON, CHRIS PROJ RMC - 616781001 HWY IH0020 2750 S. WASHINGTON KAUFMA CNTY KAUFMAN DIST 18 CONTRACT PRICE $ 66,812.75 REPORT DATE 11/02/2009 15.57.06 CONTRACTOR ISI CONTRACTING, INC. 12521 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 019 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6167-81-001 RMC - 616781001 18 IH0020 KAUFMAN -LIMITS - VARIOUS LOCATIONS IN KAUFMAN COUNTY MAINTENANCE SECTION - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 58,744.04