1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6074006 MGR.NO. 007 PAGE 001 CONT 6159 SEC 52 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 615952001 HWY US0075 2205 S SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 370,700.00 REPORT DATE 06/16/2008 15.30.38 CONTRACTOR JOEL CONSTRUCTION 12865 EST PERIOD NOV 08,2007 TO JUN 05,2008 EST NO 008 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 08, 2007 TIME COMPUTED FROM NOV 08, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 206 206 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 08 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 06/05/08 3 1 DAYS CHARGED TO DATE = 210 4 1 ASSESSED LIQ DAMAGES = 0 5 1 WORK COMPLETED AND ACCEPTED LIQ DAMAGE RATE $ 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 211 210 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6074006 MGR.NO. 007 PAGE 001 CONT 6159 SEC 52 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 615952001 HWY US0075 2205 S SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 370,700.00 REPORT DATE 06/16/2008 15.30.39 CONTRACTOR JOEL CONSTRUCTION 12865 EST PERIOD NOV 08,2007 TO JUN 05,2008 EST NO 008 & FINAL DIST. 18 COUNTY COLLIN CONTROL 6159-52-001 PROJECT RMC - 615952001 HIGHWAY US0075 0LIMITS- VARIOUS LOCATIONS IN COLLIN COUNTY MAINTENANCE SECTION 0TYPE OF WORK- POTHOLE REPAIR 0 0050 POTHOLE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY TOMMY HENDERSON 0 0075 0700 POTHOLE REPAIR (STANDARD) CY 300.000 300.000 49.000 14,700.00 0080 0700 POTHOLE REPAIR (SAW-CUT) CY 4,000.000 4,000.000 89.000 356,000.00 0 SUBTOTAL BID ITEMS $ 370,700.00 0 TOTAL AMOUNT WORK DONE POTHOLE REPAIR $ 370,700.00 0 TOTAL AMOUNT WORK DONE CONTROL 6159-52-001 $ 370,700.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6074006 MGR.NO. 007 PAGE 001 CONT 6159 SEC 52 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 615952001 HWY US0075 2205 S SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 370,700.00 REPORT DATE 06/16/2008 15.30.40 CONTRACTOR JOEL CONSTRUCTION 12865 EST PERIOD NOV 08,2007 TO JUN 05,2008 EST NO 008 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN COLLIN 0 COUNTY MAINTENANCE SECTION DATE WORK BEGAN NOV 8 , 2007 WORKING DAYS USED 210 PERCENT COMPLETE 100.00 PERCENT TIME USED 57.50 DATE COMPLETED JUN 5 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6159-52-001 RMC - 615952001 18 US0075 COLLIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0700 POTHOLE REPAIR (STANDARD) CY 300.000 300.000 49.000 14,700.00 0700 POTHOLE REPAIR (SAW-CUT) CY 4,000.000 4,000.000 89.000 356,000.00 0 SUBTOTAL BID ITEMS $ 370,700.00 0 CONTRACT TOTAL ALL ITEMS $ 370,700.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6074006 MGR.NO. 007 PAGE 001 CONT 6159 SEC 52 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 615952001 HWY US0075 2205 S SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 370,700.00 REPORT DATE 06/16/2008 15.30.40 CONTRACTOR JOEL CONSTRUCTION 12865 EST PERIOD NOV 08,2007 TO JUN 05,2008 EST NO 008 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 43 RMC - 615952001 6159-52-001 370,700.00 .00 370,700.00 .00 .00 370,700.00 359,604.00 11,096.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 370,700.00 .00 370,700.00 .00 .00 370,700.00 359,604.00 11,096.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6074006 MGR.NO. 007 PAGE 001 CONT 6159 SEC 52 JOB 001 RES ENGR MURPHY, DANNY PROJ RMC - 615952001 HWY US0075 2205 S SH 5 MCKINNEY CNTY COLLIN DIST 18 CONTRACT PRICE $ 370,700.00 REPORT DATE 06/16/2008 15.30.40 CONTRACTOR JOEL CONSTRUCTION 12865 EST PERIOD NOV 08,2007 TO JUN 05,2008 EST NO 008 & FINAL ********************************************************************************************************** - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6159-52-001 RMC - 615952001 18 US0075 COLLIN -LIMITS - VARIOUS LOCATIONS IN COLLIN COUNTY MAINTENANCE SECTION ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 00700 POTHOLE REPAIR (STANDARD) CY 300.000 132.000 49.000 6,468.00 0700 POTHOLE REPAIR (SAW-CUT) CY 4,000.000 52.000 89.000 4,628.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 11,096.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 370,700.00