1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4131602 MGR.NO. 050 PAGE 001 CONT 6255 SEC 29 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625529001 HWY US0281 1071 N. US 281 RR ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 74,855.00 REPORT DATE 08/29/2013 13.03.52 CONTRACTOR SHORT-LINE CORPORATION 15530 EST PERIOD JUL 15,2013 TO AUG 16,2013 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 15, 2013 TIME COMPUTED FROM JUL 15, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 45 17 9 8 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 13 1 1 TOTAL DAYS ALLOWED = 45 2 1 DATE WORK COMPLETED 08/16/13 3 1 SATURDAY DAYS CHARGED TO DATE = 20 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 570 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 570 PER DAY 9 1 TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 WORK COMPLETED AND ACCEPTED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 33 20 13 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4131602 MGR.NO. 050 PAGE 001 CONT 6255 SEC 29 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625529001 HWY US0281 1071 N. US 281 RR ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 74,855.00 REPORT DATE 08/29/2013 13.03.52 CONTRACTOR SHORT-LINE CORPORATION 15530 EST PERIOD JUL 15,2013 TO AUG 16,2013 EST NO 002 & FINAL DIST. 16 COUNTY JIM WELLS CONTROL 6255-29-001 PROJECT RMC - 625529001 HIGHWAY US0281 0LIMITS- VARIOUS . 0TYPE OF WORK- INSTALLATION OF SMALL SIGNS 0 0005 PREPARED BY ORLANDO J CARRILLO 0 0055 INSTALLATION OF SMALL SIGNS NET LENGTH 0.999 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0636 REPLACE EXISTING ALUMINUM SIGNS (TY A) SF 912.000 912.000 15.000 13,680.00 0065 0644 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 50.000 51.000 300.000 15,300.00 0070 0644 IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM) EA 81.000 81.000 400.000 32,400.00 0075 0644 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 20.000 20.000 500.000 10,000.00 0080 0644 REMOVE SM RD SN SUP & AM EA 151.000 141.000 25.000 3,525.00 0085 9608*UNIQUE CHANGE ORDER ITEM 1 DOL 151.000 151.000 55.500 8,380.50 0 SUBTOTAL BID ITEMS $ 83,285.50 0 TOTAL AMOUNT WORK DONE INSTALLATION OF SMALL SIGNS $ 83,285.50 0 TOTAL AMOUNT WORK DONE CONTROL 6255-29-001 $ 83,285.50 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4131602 MGR.NO. 050 PAGE 001 CONT 6255 SEC 29 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625529001 HWY US0281 1071 N. US 281 RR ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 74,855.00 REPORT DATE 08/29/2013 13.03.53 CONTRACTOR SHORT-LINE CORPORATION 15530 EST PERIOD JUL 15,2013 TO AUG 16,2013 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN JUL 15, 2013 WORKING DAYS USED 20 PERCENT COMPLETE 100.00 PERCENT TIME USED 44.40 DATE COMPLETED AUG 16 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6255-29-001 RMC - 625529001 16 US0281 JIM WELLS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0636 REPLACE EXISTING ALUMINUM SIGNS (TY A) SF 912.000 912.000 15.000 13,680.00 0644 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 50.000 51.000 300.000 15,300.00 0644 IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM) EA 81.000 81.000 400.000 32,400.00 0644 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 20.000 20.000 500.000 10,000.00 0644 REMOVE SM RD SN SUP & AM EA 151.000 141.000 25.000 3,525.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09608* UNIQUE CHANGE ORDER ITEM 1 DOL 151.000 151.000 55.500 8,380.50 0 SUBTOTAL BID ITEMS $ 83,285.50 0 CONTRACT TOTAL ALL ITEMS $ 83,285.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4131602 MGR.NO. 050 PAGE 001 CONT 6255 SEC 29 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625529001 HWY US0281 1071 N. US 281 RR ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 74,855.00 REPORT DATE 08/29/2013 13.03.53 CONTRACTOR SHORT-LINE CORPORATION 15530 EST PERIOD JUL 15,2013 TO AUG 16,2013 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 126 RMC - 625529001 6255-29-001 83,285.50 .00 83,285.50 .00 .00 83,285.50 71,406.50 11,879.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 83,285.50 .00 83,285.50 .00 .00 83,285.50 71,406.50 11,879.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4131602 MGR.NO. 050 PAGE 001 CONT 6255 SEC 29 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625529001 HWY US0281 1071 N. US 281 RR ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 74,855.00 REPORT DATE 08/29/2013 13.03.53 CONTRACTOR SHORT-LINE CORPORATION 15530 EST PERIOD JUL 15,2013 TO AUG 16,2013 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6255-29-001 RMC - 625529001 16 US0281 JIM WELLS -LIMITS - VARIOUS . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0644 IN SM RD SN SUP&AM EA 50.000 16.000 300.000 4,800.00 TY10BWG(1)SA(P) 75 0644 IN SM RD SN SUP&AM EA 20.000 4.000 500.000 2,000.00 TY10BWG(1)SA(T) 80 0644 REMOVE SM RD SN SUP & AM EA 151.000 141.000 25.000 3,525.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 85 9608* UNIQUE CHANGE ORDER ITEM 1 DOL 0.000 28.000 55.500 1,554.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 11,879.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 83,285.50