1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4134029 MGR.NO. 050 PAGE 001 CONT 6255 SEC 28 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625528001 HWY FM0624 1071 N US 281, R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 271,045.80 REPORT DATE 08/05/2013 13.10.29 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD JUL 31,2013 TO JUL 31,2013 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 31, 2013 TIME COMPUTED FROM JUL 31, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 13 TOTAL DAYS ALLOWED = 365 DATE WORK COMPLETED 07/31/13 DAYS CHARGED TO DATE = 0 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 0 DAYS AT $ 590 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - 0 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 1 0 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4134029 MGR.NO. 050 PAGE 001 CONT 6255 SEC 28 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625528001 HWY FM0624 1071 N US 281, R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 271,045.80 REPORT DATE 08/05/2013 13.10.29 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD JUL 31,2013 TO JUL 31,2013 EST NO 002 & FINAL DIST. 16 COUNTY JIM WELLS CONTROL 6255-28-001 PROJECT RMC - 625528001 HIGHWAY FM0624 0LIMITS- VARIOUS . 0TYPE OF WORK- PAVEMENT MARKINGS 0 0005 PREPARED BY RUBEN GARCIA 0 0055 PAVEMENT MARKINGS NET LENGTH 0.999 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0666 REFL PAV MRK TY I (W) 8" (SLD)(090MIL) LF 12,420.000 0.000 .500 .00 0065 0666 REFL PAV MRK TY I (W) 12"(SLD)(090MIL) LF 640.000 0.000 4.000 .00 0070 0668 PREFAB PAV MRK TY C (W) (24") (SLD) LF 74.000 0.000 11.000 .00 0075 0668 PREFAB PAV MRK TY C (W) (ARROW) EA 39.000 0.000 190.000 .00 0080 0668 PREFAB PAV MRK TY C (W) (WORD) EA 12.000 0.000 250.000 .00 0085 0668 PREFAB PAV MRK TY C (Y) (24") (SLD) LF 160.000 0.000 11.000 .00 0090 0672 REFL PAV MRKR TY I-C EA 694.000 0.000 3.000 .00 0095 0672 REFL PAV MRKR TY II-A-A EA 3,073.000 0.000 3.000 .00 0100 0672 REFL PAV MRKR TY II-C-R EA 4,044.000 0.000 3.000 .00 0105 8251 RE PM W/RET REQ TY I(W)4"(BRK)(090MIL) LF 32,950.000 0.000 .240 .00 0110 8251 RE PM W/RET REQ TY I(W)4"(SLD)(090MIL) LF 297,160.000 0.000 .230 .00 0115 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(090MIL) LF 124,920.000 0.000 .240 .00 0120 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(090MIL) LF 437,380.000 0.000 .240 .00 0125 8251 RE PM W/RET REQ TY I(W)6"(BRK)(090MIL) LF 39,600.000 0.000 .370 .00 0 TOTAL AMOUNT WORK DONE PAVEMENT MARKINGS $ .00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4134029 MGR.NO. 050 PAGE 001 CONT 6255 SEC 28 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625528001 HWY FM0624 1071 N US 281, R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 271,045.80 REPORT DATE 08/05/2013 13.10.29 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD JUL 31,2013 TO JUL 31,2013 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN JUL 31, 2013 WORKING DAYS USED 0 PERCENT COMPLETE 0.00 PERCENT TIME USED 0.00 DATE COMPLETED JUL 31 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6255-28-001 RMC - 625528001 16 FM0624 JIM WELLS 0***** NO WORK TO DATE FOR CONTRACT ***** 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4134029 MGR.NO. 050 PAGE 001 CONT 6255 SEC 28 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625528001 HWY FM0624 1071 N US 281, R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 271,045.80 REPORT DATE 08/05/2013 13.10.29 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD JUL 31,2013 TO JUL 31,2013 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 126 RMC - 625528001 6255-28-001 .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** .00 .00 .00 .00 .00 .00 .00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4134029 MGR.NO. 050 PAGE 001 CONT 6255 SEC 28 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 625528001 HWY FM0624 1071 N US 281, R.R. ALICE CNTY JIM WELLS DIST 16 CONTRACT PRICE $ 271,045.80 REPORT DATE 08/05/2013 13.10.29 CONTRACTOR HIGHWAY TECHNOLOGIES, INC. 13982 EST PERIOD JUL 31,2013 TO JUL 31,2013 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6255-28-001 RMC - 625528001 16 FM0624 JIM WELLS -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 0.00